parallax background

Projects
ICRC superintends and regulates PPPs in Nigeria

FEC approved PPP Projects

 

S/N

Project Name & Description / Current Status

 

 

MDA / Grantor

 

 

 

ConcessionairePPP ProcessValue of Concession (NGN)/Project costFBC Issue DateApproval Date /Duration of Concession
1

Provision of Engineering Infrastructure for Katampe District, FCT Design, Finance, Build and Transfer of Engineering Infrastructure for Development of Katampe

 

Status: PPP Currently on Hold

Federal Capital Development Authority (FCDA)

Deanshanger Project Limited

 

Solicited; Open

NGN

61,194,747,645

ICRC FBC Compliance Certification:  9 Feb, 2010

 

 

 

FEC Approval: May, 2010

 

 

Duration:        8 years

2

Lekki Deep Sea Port

Development and Operation of A Deep Water Port in the Lagos Free Trade Zone at Ijebu Lekki, Lagos State

 

Status: PPP currently at Implementation Phase

Federal Ministry of Transportation / Nigeria Ports AuthorityLekki Port LFTZ EnterprisesSolicited; OpenNGN 504,000,000,000

ICRC FBC Compliance Certification: March 2011

 

 

FEC Approval: April, 2011

 

Duration:      45 years

3.

Security, Monitoring and Enforcement Concession

NIMASA wishes to effectively enhancing the security of ships and ports, minimising the incidents of piracy and armed robbery at sea, and other incidents of maritime security breaches within the Nigerian waters, and generally protect the Maritime domain in consonance with the International Maritime Organisation (IMO) conventions.

 

Status: Project on Hold

Nigerian Maritime Administration and Safety Agency (NIMASA)Global West Vessel Specialist Nigeria LimitedRestricted Bidding (Sole Source) with Security Clearance by ONSA

NGN

37,224,000,000

ICRC FBC Compliance Certificate:

16 Aug, 2011

 

 

3rd April 2012

 

Duration: 10years

4

Kainji Hydro Electric Power Plant

Concession of the Hydropower to improve national power generation

 

Status: Project at Implementation Phase

BPE / Federal Ministry of Power

Mainstream Energy Solutions Limited

 

Solicited; Open

NGN

114,690,823,560

In view of Emergency in the Power sector, ICRC supported BPE on the transaction for National Interest

February, 2013

 

Duration:

30 years

5

Shiroro Hydro Electric Power Plant

Concession of the Hydropower to improve national power generation

 

Status: Project at Implementation Phase

BPE / Federal Ministry of Power

North South Power Company Limited

 

Solicited; Open

NGN

48,692,526,480

In view of Emergency in the Power sector, ICRC supported BPE on the transaction for National Interest

February, 2013

 

Duration:

30 years

6Development of Phase 4B Port Facilities at Onne Oil and Gas Free-ZoneFederal Ministry of Transportation (FMoT)Deep Offshore Services Nigeria LtdUnsolicited

                             NGN

1,020,952,173,789.90

 17 May, 2013
7Construction of Berth 21 at Greenview Terminal ApapaFederal Ministry of Transportation (FMoT)Green View LimitedSolicited; Open

NGN

41,506, 944,577.0

 28 Mar, 2014
8

Development of FESTAC Phase 2 Housing Estate, Lagos

Concession for the Reclamation and infrastructural Development of the land

 

Status: Yet to commence due to Court cases with Amuwo Odofin Community Chiefs

Federal Ministry of Lands, Housing & Urban Development / Federal Housing AuthorityNew FESTAC Property Development Company LtdSolicited: Open

NGN

18,983,650,000.0

 

8 Sep, 2014

 

Duration: 30 years

9

Debt Management Office (DMO) Complex

DMO proposes to provide modern office complex, involving the design, finance, build, operate, maintain and transfer of the building; and receive rents and service charges derived from the lease of 15 floors of the first tower and all 20 floors of the second tower

 

Status: Project yet to achieve Financial Close

Debt Management OfficeLOH & OR Construction Company LimitedUnsolicited; Swiss Challenge Procurement

                        NGN

41,506, 944,577.0

ICRC FBC Compliance Certification:

23 Jan, 2015

 

 

 

FEC Approval: 13 May, 2015

 

 

Duration: 30 years

10

Trans-Nigeria Gas Pipeline: Nigerian

(Solicited Proposal): The project involves the construction of 614km gas pipeline from Ajaokuta to Kano (AKK) with off take Gas Stations in Abuja, Kaduna and Kano.

 

Status:

Contracts for Lot 1 and Lot 3 were signed in April 2018 while that of Lot 2 was not executed. Lot 2 was shared to Lots 1 and 3, which became  Segments 1 and 2. These are being negotiated by the EPC Contractors, the Chinese financial institutions and the NNPC for financial close

 

Federal Ministry of Petroleum / Nigeria National Petroleum Corporation (NNPC)

Lot 1: Oando/OilServe consortium

 

Lot 3: China Petroleum Pipeline (CPP)/Brentex consortium

Solicited; OpenNGN 1,022,000,000,000.0

ICRC Compliance Certification:  10 July, 2017

 

FEC approval: 13 Dec, 2017

 

 

11

Development of Hydroelectric power at existing Small & Medium dams across the Country

 

Development of Hydroelectric power from existing 6 Small & Medium from dams across the Country

Federal Executive Council (FEC) gave an approval on the 30th November 2016 for 6 dams.

1.     Bakolori Dam, Zamfara State

2.     Omi - Kampe Dam, Kogi State

3.     Ikere Gorge Dam, Oyo State (swiss challenge)

4.     Jibiya Dam, Katsina State

5.     Zobe Dam, Katsina State

 

Federal Ministry of Power, Works & Housing (Power)
  1. Bakalori – Pan-African Global Infrastructure Company Ltd
  2. Omi – Kampe – Messrs Quaint Power Infrastructure Nigeria Ltd/Engie
  3. Ikere – Messrs Power Control & Appliances Ltd
  4. Zobe & Jibiya - Pan-African Global Infrastructure Company Ltd

 

Solicited; Open

1.     Bakolori Dam, Zamfara State - ₦ 1,553,167,000.0

2.     Omi - Kampe Dam, Kogi State    ₦1,212,452,500

3.     Ikere Dam, Oyo State (swiss challenge) ₦ 3,650,000,000.0

4.     Jibiya Dam, Katsina State ₦ 1,315,470,000.0

5.     Zobe Dam, Katsina State ₦ 434,630,000.0

 

FBC issued: 29 Oct 2018

FEC approval: (one approval for small Dams)

 

Duration: 30 years

March 27, 2018

12

Warehouse in a Box– Abuja and Lagos

The Project seeks to provide physical infrastructure – an insulated warehouse, made up of pre-engineered modular components (prefabricated insulated expanded polystyrene sandwiched panels) – as well as the fittings and operating components, including offices, furnishings, racking, kitting, security and office equipment.

Federal Ministry of HealthMDS Logistics LtdSolicited; Open

NGN

668,880,000.0

ICRC FBC Compliance Certification:

6 Sept 2018

 

 

FEC Approval: 28 Nov, 2018

 

 

Duration: 5 years

13

Roof Top Solar Powered Project, Power House

Design, Build, Finance, Operate a 750kw Day Time and 75kw Night Time Hybrid Solar Power Facility in a PPP arrangement at the Power House, Maitama, Abuja

Federal Ministry of Power, Works and Housing (Power Sector)Proserve Energy Services LtdSolicited; Open

NGN

690,079,950.0

(Equipment Only)

ICRC FBC Compliance Certification: 27 Feb, 2018

FEC Approval: 13 Sep, 2018

 

 

Duration:

10 years

14

Ado Ekiti, Ekiti

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Agro Universal ConsortiumSolicited; Open

NGN

485,767,625.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

15

Akure, Ondo

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Agro Universal ConsortiumSolicited; Open

NGN

105,775,991.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

16

Bauchi, Bauchi

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Agro Universal ConsortiumSolicited; Open

NGN

128,663,089.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

17

Bulasa, Zamfara

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Matrixville ConsortiumSolicited; Open

NGN

2,073,800,654.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

18

Ezillo, Ebonyi

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Ebony Agro Industries LimitedSolicited; Open

NGN

1,893,793,273.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

19

Gaya, Kano

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Agro Universal ConsortiumSolicited; Open

NGN

236,930,364.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

20

 

Gombe, Gombe

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Servewell Agricultural Service LimitedSolicited; Open

NGN

429,426,464.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

21

Ibadan, Oyo

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Independent Grain Handling and Storage LimitedSolicited; Open

NGN

575,912,947.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

22

Igbariam, Anambra

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Coscharis Farms LimitedSolicited; Open

NGN

254,241,286.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

23

Ikenne, Ogun

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Agro Universal ConsortiumSolicited; Open

NGN

626,505,802.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

24

Jahun, Jigawa

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Matrixville ConsortiumSolicited; Open

NGN

487,677,696.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

25

Jos, Plateau

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Agro Universal ConsortiumSolicited; Open

NGN

176,688,747.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

26

Kaduna, Kaduna

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Matrixville ConsortiumSolicited; Open

NGN

541,806,691.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

27

Kwali, Abuja

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Matrixville ConsortiumSolicited; Open

NGN

2,246,942,955.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

28

Lafiagi, Kwara

Concession and Leasing of Grain Storage Facilities

 Matrixville ConsortiumSolicited; Open

NGN

227,649,132.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

29

Makurdi, Benue

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Upland Grains Production Company LimitedSolicited; Open

NGN

442,382,759.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

30

Minna, Niger

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Niger Resources LimitedSolicited; Open

NGN

3,759,277,152.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

31

Ogoja, Cross River

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Agro Universal ConsortiumSolicited; Open

NGN

27,613,845.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

32

Sokoto, Sokoto

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Agro Universal ConsortiumSolicited; Open

NGN

196,719,866.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

33

Uyo, Akwa Ibom

Concession and Leasing of Grain Storage Facilities

Federal Ministry of Agriculture and Rural Development (FMARD)Neon Farms Africa ConsortiumSolicited; Open

NGN

182,163,107.0

ICRC FBC Compliance Certification: 12 Jun, 2018

 

 

FEC Approval: 19 Sep, 2018

 

Duration:

10 years

34

ECOWAS Biometric ID Cards System

 

This project involves the adoption of smart card and biometric technology to secure the identification of documents as a prerequisite for managing migration and to enhance regional security, which is the outcome of the deliberation of ECOWAS Heads of Governments in order to meet the challenges posed by migration.

Federal Ministry of InteriorEuphoria Press LimitedUnsolicited Bid

NGN

14,700,000,000.0

ICRC FBC Compliance Certification: 24 May, 2018

FEC Approval: 28 Nov, 2018

 

 

Duration: 10 Years

35

Development of Abuja-Warri Railway Line with Branch Line and Extensions from Jakura-Lokoja and Agbarho-Warri (ii) Warri New Sea Port

 

The 2-projects are:

i.         Abuja-Baro-Itakpe-Ajaokuta-Warri Railway Line (269.12km) with branch and extension lines to Jakura-Lokoja (41km) and Agbarho-Warri (5km)

 

ii.         Development of Warri new Seaport, Warri, Delta State

 

The preferred PPP project model is Design-Build-Operate and Transfer (DBOT) designed to promote passenger and freight services, promote regional infrastructure development, preserve the life span of roads, encourage inter-model transport system, job creation and promote economic recovery and growth plans of the Federal Government, etc.

 

Federal Ministry of TransportationMessrs. China Railway Construction Company International (CRCC(I))Solicited

NGN3.199 billion for the railway and N880.089 million for Warri new sea port.

 

FBC issued: 27 Nov 2018November, 2018
36

Concession of the Power Components of Gurara 1 30MW Dam

 

This is for the O & M of the dam, as the FMoWR has completed the construction of this facility and its multi-purpose assets.

Federal Ministry of Water Resources Solicited; Open

₦ 6,679,288,975.0

 

FBC issued: 18 Mar 2019May 19, 2019
37

Development of Small & Medium Enterprise (SME) Portal Project

 

A technology enabled platform project that will encourage more MSMEs to be attracted into the formal sector

Federal Ministry of Industry Trade and Investment Solicited; Open FBC issued: 26 Apr 2019May 19, 2019
38

Gurara Facility Management

 

The project involves procurement of a Facility Manager to manage, operate and maintain all infrastructure facilities and services in Gurara dam.

Federal Ministry of Water Resources Solicited; Open FBC issued: 26 Apr 2019May 19, 2019
39

Establishment of Military & Paramilitary Clothing & Accessories Factory at DICON, Kaduna State

 

Establishment of selected weapons and military equipment assembly lines
ii. Establishment of Mobile Solar

Powered Generating set
iii. Production of Ballistic Vests and Procurement of Raw Material

 

 

Federal Ministry of DefenceSur Corporate WearSolicited; OpenUS$13 millionFBC issued: 01 Feb 201912th July, 2019
40

Development, deployment and management of Automated Customs Gateway Portal for Import Duty Exemption Certificate (IDEC) and Imported Vehicle identification Number Registration (VREG) (Revalidated)

 

Development, deployment and management of Automated Customs Gateway Portal for Import Duty Exemption Certificate (IDEC) and Imported Vehicle identification Number Registration (VREG)

Federal Ministry of Finance, Budget and National PlanningFour Core Technology solution Ltd.Solicited; Open₦10 Billion.FBC issued: May 2019

FEC Approval: October 30, 2019

Concession Period: 10 years

 

41Design, Development, Deployment and Management of a Secure Automated Fare Collection (AFC) Solution for the Nigerian Railway Corporation (NRC) Rail Network.Federal Ministry of Transportation/ Nigerian Railway CorporationSecure ID Nigeria ltd 

NGN

900,000,000.0

FBC issued September 2019FEC has approved FBC Compliance Certificate 29th January, 2020 concession period 10 years
42

The Renovation of Students Hostel

 

The proposed project is for the rehabilitation of student hostels within Kaduna Polytechnic premises. The hostels will be managed to ensure highest standard of living conditions for the students.

Federal Ministry of Education (Kaduna Polytechnic)Mark Point Multilinks LtdUnsolicitedSeven Hundred and forty-four Million, Two Hundred and Sixty-four Thousand Naira Only (N744,264,000.0).FBC issued: 12 Feb 2020

FEC Approval: 08 July, 2020

 

 

Duration: 19 Years

 

 

43

 

Presidential Initiative on Custom Modernization “E-Customs Project”

Nigeria Custom Service (NCS)Trade Modernization Project Ltd. 

NGN3.1 Billion

 

FBC issued: 22 May 2019September 20, 2020
44

Rehabilitation, Expansion and Operation of the Nigerian Correctional Service Shoe, Garment and Leather Factories

 

An unsolicited proposal for the Rehabilitation, Expansion and Operation of the Nigerian Prisons Service Shoe Factory (NPS SF) Aba, Abia State under Public Private Partnership between Erojim Investment limited (EIL) and the Nigeria prisons service.

 

 

Nigeria Correctional Service (NCS)Messrs. ErojimSolicited; Open

Total Cost for Shoe Garment and Tannery                                      US$11,866, ,865

 

 

FBC issued: 6 May 20207th Oct 2020
45

Development of Port Harcourt Railway Industrial Park

 

The FGN intends to develop a Railway Industrial Park in Ubima, Rivers State through PPP arrangements with the following facility components for commercial vehicles and rolling stock assembly, Oil and Gas materials supply Industrial Park, Textile Industrial Park, Light Industry Park for Fast Moving Commodities and Goods (FMCGs).

 

Federal Ministry of TransportationChina Civil Engineering Construction Corporation Ltd. (abbreviation CCECC)Solicited; OpenUS$291,253,619FBC issued: 24 Aug 20207th Oct 2020
46

Development of Bonny Deep Sea Port

 

The FGN intends to develop the Bonny Deep Water Port through PPP arrangements in order to improve transportation opportunities and boost economic activities along south-south, south east, north central and north east geo-political economic corridors and ease pressure on the western ports – Apapa and Tin Can Island which at the moment handles about 90% of cargo throughput in the country

Federal Ministry of TransportationChina Civil Engineering Construction Corporation Ltd. (abbreviation CCECC)Solicited; OpenUS$550,025,361 millionFBC issued: 24 Aug 20207th Oct 2020
47

Ibom Deep Sea Port Project

(Solicited Proposal): The Ibom Deep Sea Port (IDSP) project involves the development of a Greenfield Deepsea Port and accompanying Free Trade Zone (FTZ) in Akwa Ibom State in the South-South geopolitical zone of Nigeria. The proposed Port and FTZ are part of the proposed Ibom Industrial City initiative that will be established on a 14,400-hectare site donated by the Akwa Ibom State Government (AKSG) at no value. The IDSP project is intended to become a major national and regional economic gateway that will provide additional container handling capacity for the country. In addition to containers, the IDSP is expected to handle petroleum products (export and import), crude oil and natural gas (export), vehicles (import) and bulk trade in natural resources (import and export).

 

Federal Ministry of Transportation (FMoT) Federal Ministry of Transportation / Akwa Ibom State Government

 

Bollore/Power China   Consortium Bollore Africa Logistics-PowerChina International Group LimitedSolicited

$USD 2.016 Billion

US$2,016,198 billion

September 17, 2020December 16 2020
48

Deployment of Police Specialised Services Automation project

The project is the automation of police services to capture revenues accruing to the police through specialised services like VIP coverage etc, and remit same to the force.

Nigeria Police ForceParkway Projects LimitedUnsolicitedNGN 2,047,726,450.0.FBC issued 15th Dec 2020, revalidated on Tuesday 13th July 2021FEC approval on Wednesday 14th July 2021
49The NAHCON seek to engage a private sector operator to DFBOT a building at its landed property located at Hajj Complex, along Katsina Road, Kano State.  The plan is to build a 4blocks complex housing 376 units of shops, 8 portal steel blocks, a mosque, convenience and parking spacesNational Hajj Commission of Nigeria (NAHCON)DID Al-Amana Nigeria LimitedUnsolicited

NGN 1812.7 Billion

 

 

FBC issued November 22, 2021FEC approval December 12, 2021
50Deployment of a Revenue Assurance System (RAS)Federal Ministry of Communications/Nigeria Communications Commission (NCC)3R Revenue Assurance ltdSolicitedNGN11.9 BillionFBC Issued December 17, 2021FEC approval January 26, 2022 concession period 10 years
51

Onitsha River Port project

 

This project will serve as a pilot scheme for concession of other River ports under PPP arrangements namely: Onitsha, Lokoja, Baro and

Oguta River Ports.

 

Onitsha River Port located in Anambra State is being funded under the IDA Credit.

Federal Ministry of Transport (FMoT)/ National Inland Waterways Authority (NIWA)Universal Elysium ConsortiumsolicitedNGN 3,935,833,337.0FBC Issued August 23, 2021FEC approval February 2, 2022 Concession period 30 years
52Federal Coastal Fishery Terminal, Ebughu, Akwa Ibom StateFederal Ministry of Agriculture and Rural DevelopmentMessrs Alfin Fisheries LimitedUnsolicitedN3,685,055,000.00 (Three Billion, Six Hundred and Eighty-Five Million and Fifty-Five Thousand Naira.

28 Feb 2018,

 

(revalidation)

September 27, 2021

FEC approval February 16, 2022 concession period 11 years
53Redevelopment of K’Maroun Complex in Ijora Lagos StateOgun Osun River Basin Development AuthorityMessrs. Asiko International Energy (Nigeria) LimitedUnsolicited

NGN 890,000,000.0

Eight Hundred and Ninety Million Naira Only

FBC issued on January 12, 2022FEC Approval April 6, 2022
54

The Development of Deep-Sea Port in Badagry, Lagos.

 

The project is a Greenfield development designed to cater for containers, dry bulk, liquids, Ro-Ro, oil & gas products, and also operate a free trade and local logistic zones.

Federal Ministry of Transportation/ Nigerian Ports AuthorityBadagry Port Development Limited.Solicited$ 2,777,233,000.00 (Two Billion, Seven Hundred and Seventy-Seven Million Two Hundred and Thirty Three Thousand Dollars.

 

FBC issued (revalidated) April 25, 2022

FEC approval August 3, 2022 concession period 45 years
55

Development of a Maintenance, Repairs and Overhaul (MRO) Facility

The FGN intends to establish an MRO facility for aircraft maintenance, inspections and supply of parts to the aviation sector

Federal Ministry of AviationAJW Consortium – AJ Walter and Gloresly Pro-ProjectSolicited$ 1.5 Million One Million Five Hundred Thousand Dollars only. FBC issued August 18, 2022FEC Approval October 12, 2022
56

Concession of Planetarium and Museum

The project seeks to equip, operate and maintain the Planetarium and Museum at the Obasanjo Space Centre Abuja.

National Space Research & Development Agency (NASRDA)Milky-way VisualsSolicited

N3,593,532,207.0

Three Billion Five Hundred and Ninety Three Million Five Hundred and Thirty Two Thousand two Hundred and Seven Naira Only.

FBC issued on July 25 2022FEC Approval November 2, 2022
57Research and Development of Satellite Technology and Equipment for the Provision of cost-effective satellite broadband to rural NigeriaNational Space Research & Development Agency (NASRDA)Messrs Gilat Eleo TechnologyUnsolicited

4,074,371,000.0

Four Million and Seventy-Four Million Three hundred and Seventy-One Thousand Naira Only

FBC issued on June 28, 2022FEC Approval November 30, 2022
58Redevelopment of the Nigerian Police DIG Quarters at Maitama District, Abuja, through Public Private Partnership arrangementNigeria Police ForceCosgrove NigeriaSolicited

20,138,230,886.0

Twenty-Two Billion One Hundred and Thirty-Eight Million Two hundred and Thirty Thousand and Eighty-Six Naira Only.

FBC issuedFEC Approval November 30, 2022

TOTAL COST OF PROJECTS APPROVED –

 

NGN - 3,030,433,553,378.9

Three Trillion, Thirty Billion, Four Hundred and Thirty-Three Million, Five Hundred and Fifty Three Thousand, Three Hundred and Seventy Eight Naira, Nine Kobo.

 

* USD - $5,661,076,845

Five Billion, Six Hundred and Sixty-One Million, Seventy-Six Thousand, Eight Hundred and Forty-Five Dollars.