ICRC superintends and regulates PPPs in Nigeria

Projects Under Custody (Post-Contract)



LIST OF CONCESSION AGREEMENTS UNDER ICRC CUSTODY – JULY, 2021

S/NPROJECT DESCRIPTION GOVT AGENCYCONCESSIONAIREDURATIONSTATUS
Ports Infrastructure Sector
LAGOS PORT COMPLEX
1

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Apapa)

Nigerian Ports Authority (NPA)Apapa Bulk Terminal Ltd “A”

25years

3rd April 2006 – 2nd April 2031

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Railway construction work is at completion stage and will add great value to port activities in the Western Ports.

2

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Apapa)

Nigerian Ports Authority (NPA)Apapa Bulk Terminal Ltd “B”

25years

3rd April 2006 – 2nd April 2031

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Railway construction work is at completion stage and will add great value to port activities in the Western Ports.

3

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Apapa)

Nigerian Ports Authority (NPA)ENL Consortium Ltd (Terminal C)

10 years (Initially)

2006 – 2016

15 years

3rd April 2006 – 2nd April 2021

* Extension of additional 5 years granted to expire in 2021

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Railway construction work is at completion stage and will add great value to port activities in the Western Ports.

The Commission is engaging the Parties and other stakeholders on the contract expiration.

4

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Apapa)

Nigerian Ports Authority (NPA)ENL Consortium Ltd (Terminal D)

10 years (Initially)

2006 – 2016

15 years

3rd April 2006 – 2nd April 2021

* Extension of additional 5 years granted to expire in 2021

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Railway construction work connecting the port to evacuate goods is at completion stage..

The Commission is engaging the Parties and other stakeholders on the contract expiration.

5

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Apapa)

Nigerian Ports Authority (NPA)Greenview Development Nigeria Ltd (Terminal E)

25 years

3rd April 2006 – 2nd April 2031

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Railway construction work connecting the port to evacuate goods is at completion stage.

6

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Apapa)

Nigerian Ports Authority (NPA)

APMT Terminals Apapa Ltd

25 years

20th March -19th March 2031

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Railway construction work connecting the port to evacuate goods is at completion stage.

TIN CAN PORT COMPLEX
7.

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Tincan Island)

Nigerian Ports Authority (NPA)Five Star Logistics Ltd

15 years (Initially)

10th May 2006- 2nd May 2021

* Extension of additional 5yrs granted to expire 2nd May 2026

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Access road to Tincan Island Port is under re-construction.

Improvement on security situation around Tincan port.

8

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Tincan Island)

 

Nigerian Ports Authority (NPA)Ports and Terminal Multi-Service Ltd

25 years

18th August 2009 -17 August 2034

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Access road to Tincan Island Port is under re-construction.

Improvement on security situation around Tincan port.

9

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Tincan Island)

Nigerian Ports Authority (NPA)Ports and Cargo Handlings Services Ltd

10 years Initially

10th May 2006 – 9th May 2021

15 years

* Extension of additional 5 years granted to expire in 2021

Under implementation.

Access road to Tincan Island Port is under re-construction.

The Commission is engaging the Parties, Federal Ministry of Transportation and stakeholders on the contract expiration.

10

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Tincan Island)

Nigerian Ports Authority (NPA)Tincan Island Container Terminal Ltd (TCIT)

Initially 15

1st June 2006 – 31st May 2026

20 years

* Extension of additional 5 years granted to expire in 2026

Under implementation.

Access road to Tincan Island Port is under re-construction.

Improvement on security situation around Tincan port.

11

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Tincan Island)

Nigerian Ports Authority (NPA)Josepdam Ports Services Nig Ltd

10 years (Initially)

11th May 2006 – 10th May 2021

15 years

*Extension of additional 5yrs granted to expire in 2021

Under implementation.

Access road to Tincan Island Port is under re-construction.

The Commission is engaging the Parties, Federal Ministry of Transportation and stakeholders on the contract expiration.

ONNE PORT COMPLEX
12

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Onne)

Nigerian Ports Authority (NPA)Brawal Oil Services Ltd

25 years

6th August – 5th August 2031

Under implementation.

Reduction in the volume of cargo traffic at the port.

Insecurity along the waterways is being resolved.

13

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Onne)

Nigerian Ports Authority (NPA)West African Container Terminal Ltd (WACT)

25 years

1st September, 2007 -31st August, 2032

Under implementation.

Reduction in the volume of cargo traffic at the port.

Insecurity along the waterways is being resolved.

14

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Onne)

Nigerian Ports Authority (NPA)Intels Nigeria Ltd (Onne- FLT)

25 years

22nd June 2006 – 21st June 2031

Under implementation.

Reduction in the volume of cargo traffic at the port.

Insecurity along the waterways is being resolved.

15

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Onne)

Nigerian Ports Authority (NPA)Intels Nigeria Ltd (Onne – FOT)

25 years

22nd June 2006 – 21st June 2031

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Reduction in the volume of cargo traffic at the port.

Insecurity along the waterways is being resolved.

CALABAR PORT COMPLEX
16

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Calabar)

Nigerian Ports Authority (NPA)Intels Nigeria Ltd (Calabar)

25 years

21 June 2006 - 20th June 2032

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Demobilization of the Delta Queen Rig is on-going.

Urgent intervention is needed on the access roads to the port.

17

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Calabar)

Nigerian Ports Authority (NPA)

Shoreline Logistics Nigeria Ltd

(Addax Logistics Nig Limited)

25 years

26th May 2007 – 25th May 2032

Under implementation.

The reconstruction of the collapsed berth at the Terminal is about to commenced.

18

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Calabar)

Nigerian Ports Authority (NPA)Ecomarine (ECM) Terminals Ltd

Initially 25 years

1st August 2007 – 31st July 2037

* Extension of additional 5 years granted to expire in 2037

Under implementation.

Low volume of traffic visiting the terminal. Terminal has a depth of 5.4 metres as against 9.4 metres.

DELTA PORT COMPLEX
19

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Warri)

Nigerian Ports Authority (NPA)Intels Nigeria Ltd (Terminal A -Warri)

25 years

21st June 2006 – 22nd June 2031

Under implementation.

High freight rate and insurance cost on vessels visiting the port due to the insecurity problem is being resolved.

Port Access roads are undergoing re-construction.

20

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Warri)

Nigerian Ports Authority (NPA)Intels Nigeria Ltd (Terminal B -Warri)

25 years

21st June 2006 – 22nd June 2031

Under implementation.

High freight rate and insurance cost on vessels visiting the port due to the insecurity problem is being resolved.

Port Access roads are undergoing re-construction.

21

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Warri)

Nigerian Ports Authority (NPA)Associated Maritime Services Ltd

Initially 10 years

11th June 2006 -10th June 2021

15 years.

* Extension of additional 5 years granted to expire in 2022

Under implementation.

The Commission is engaging the Parties, Federal Ministry of Transportation and stakeholders on the contract expiration.

High freight rate and insurance cost on vessels visiting the port due to the insecurity problem is being resolved.

Port Access roads are undergoing re-construction.

22

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Warri)

Nigerian Ports Authority (NPA)Julius Berger Services Nigeria Ltd

25 years

1st April 2007 – 31 March 2032

Under implementation.

High freight rate and insurance cost on vessels visiting the port due to the insecurity problem is being resolved.

Port Access roads are undergoing re-construction.

23Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal B Old Port (Warri)Nigerian Ports Authority (NPA)

Ocean & cargo Terminal Services

25 years

22nd February, 2019

21st February, 2044

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

High freight rate and insurance cost on vessels visiting the port due to the insecurity problem.

Port Access roads are undergoing rehabilitation.

RIVERS PORT COMPLEX
24

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Port Harcourt)

Nigerian Ports Authority (NPA)Port and Terminal Operators Nig Ltd

Initially 15 years

23rd June 2006 -22nd June May 2006 – May 2026

20 years

* Extension of additional 5 years granted to expire in 2026

Under implementation.

The Commission is engaging the parties on the payment of outstanding lease/& throughput fees.

25

Concession for the Development, Finance, Maintenance, Operate and Transfer of Port Terminal (Port Harcourt)

Nigerian Ports Authority (NPA)BUA Ports and Terminals Ltd

20 years

9th August 2006 – 8th August 2026

Under implementation.

Low level in the volume of cargo traffic at the port.

.

Lekki Deep-Water Port Complex

 

26Development and Operation of Deep-Water Port (Lekki, Lagos)Lekki Port LFTZ Enterprise LimitedThe Nigerian Ports Authority/Lagos State Government45 years (April 21st 2011 – April 20th 2056)

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Eastern Breakwater core dumping is ongoing.

Production of tubular steel piles ongoing in the Pile Fabrication yard.

Dredging is ongoing. Approximately 6.5 M m3 dredged to date.

Healthcare Infrastructure Sector

 

27

Concession for the Operation, Management and Provision of Primary, Secondary and Tertiary Health Care at the Garki Hospital Abuja

Federal Capital Territory Administration (FCTA)NISA Premier Hospital Ltd

15 Years from

20th March 2007

To 19th March, 2022

Under implementation.

The Commission is engaging the FCTA Health Secretariat on the expiration of the Contract.

28

Concession for the operation and maintenance of two Warehouses located in Lagos and Abuja, through an Operate and Management contract

(Warehouse in a Box)

Federal Ministry of Health

MDS Logistics Limited

5 years

14th May – 13 May 2024

Under implementation.

The two facilities in Lagos and Abuja are fully operational.

Public Building Infrastructure Sector

 

29

Concession for the Design, Finance, Build, Operate, Maintain and Transfer the Debt Management Office’s Corporate Office Building, Abuja

The Debt Management Office (DMO)LOH & OR Construction Nigeria Limited

30 years from effective date

Contract Signed in 2015

The Commission is monitoring compliance with the terms and conditions of the agreement.

The contract has not commenced due to the Concessionaire’s inability to achieve financial close

ICRC is engaging the Debt Management Office on its alternative options for the project since it has not commenced.

30

Concession for the renovation of 18 Blocks Student Hostel of the Kaduna Polytechnic

Mark Point Project Limited

The Kaduna Polytechnic

Contract is for 14 years from effective date.

Contract Signed on 21st August, 2020.

Expire on 20th August 2034.

Contract is under re-construction phase

Concessionaire has mobilized to site and re construction work has commenced.

Inland Container Depot Infrastructure Sector

 

31

Concession for Build, Own, and Operate a Container Freight Station of Inland Container Depot (Abia State)

Nigerian Shippers Council (NSC)Eastgate Inland Container Depot Ltd30 Years from 2007

The contract is under review by the Parties

No significant progress has been recorded on the contract implementation.

Contract Implementation is about 5%

32Concession for Build, Own, and Operate a Container Freight Station of Inland Container Depot (Oyo State)Nigerian Shippers Council (NSC)Catamaran Logistics Ltd25 Years from 2007

This contract is under review by the Parties

No significant progress has been recorded on the contract implementation.

Contract Implementation is about 10%

33Concession for Build, Own, and Operate a Container Freight Station of Inland Container Depot (Plateau State)Nigerian Shippers Council (NSC)Duncan Maritime Ventures Nigeria Ltd25 Years from 2007

Contract Implementation is about 29.70%

Land Acquisition and Compensation has been completed

Issuance of Letters of Exchange/Certificate of Occupancy Executed

Administrative Block - 97% completed.

34Concession for Build, Own, and Operate a Container Freight Station of Inland Container Depot (Kano State)Nigerian Shippers Council (NSC)Dala Inland Dry Port Nigeria Ltd25 Years from 2007

The new investor for the project has injected N2.5 billion into the project construction work

Investor has mobilized to site

Contract Implementation is about 55%.

35Concession for Build, Own, and Operate a Container Freight Station of Inland Container Depot (Katsina State)Nigerian Shippers Council (NSC)Equatorial Marine Oil and Gas Company Ltd25 Years from 2007

A Ministerial Task Force for the completion of Funtua Inland Dry Port has been constituted to ensure completion and commissioning in March, 2022.

Contract Implementation is about 68%.

36Concession for Build, Own, and Operate a Container Freight Station of Inland Container Depot (Borno State)Nigerian Shippers Council (NSC)Migfo Nigeria Limited25 Years from 2007

No significant progress has been recorded on the contract implementation.

Work has been suspended at the site as a result of insecurity.

Contract Implementation is about 5%.

Telecommunications (Fibre Optic) Infrastructure Sector

 

37

Concession Agreement for the Design, Build, Finance, Operate TCN’s Fibre Optic Cable Telecommunications Infrastructure for the Western part of Nigeria

Transmission Company of NigeriaPhase 3 Telecom Ltd

15 Years

March 2006 -2021

Under implementation.

Parties have signed the Addendum to the principal agreement after the concurrences to the agreement by the Federal Ministry of Justice (FMoJ), TCN Board & NERC.

38

Concession Agreement for the Design, Build, Finance, Operate TCN’s Fibre Optic Cable Telecommunications Infrastructure for the Eastern part of Nigeria

Transmission Company of NigeriaAlheri Engineering Services L td

15 Years

March 2006 -2021

Under implementation.

Parties have signed the Addendum to the principal agreement after the concurrences to the agreement by the Federal Ministry of Justice (FMoJ), TCN Board & NERC.

Aviation Infrastructure Sector
39

Concession to Design, Develop, Finance, Construct, Complete, Test, Commission, Operate, Manage, Maintain and Transfer of the Muritala Muhammed Airport Ikeja – Lagos Domestic Terminal (Lagos)

The Federal Airports Authority of Nigeria (FAAN)Bi -Courtney Ltd

Initially 12 Years

April 24th 2003 – April 23rd 2015
Now 36 years

*Extension granted through an Addendum to the Concession Agreement signed by Parties on 2nd February 2007 for an extension of 36 years

Under implementation.

A joint Committee has been set up by FAAN and Bi-Courtney to resolve the contractual disputes between the parties.

40Concession for the Construction and Development of a Four-Star Hotel at the Muritala Muhammed Airport Ikeja - LagosFederal Ministry of Transportation /Federal Airports Authority of NigeriaBi -Courtney Ltd

40 Years

September 27th 2005

To September 26th 2045

Construction Stalled

A joint Committee has been set up by FAAN and Bi-Courtney to resolve the contractual disputes between the parties.

41Concession for the Construction and Development of a Conference Centre at the Muritala Muhammed Airport Ikeja - LagosFederal Airports Authority of NigeriaBi -Courtney Ltd

40 Years

November 21st 2006 – 20th November 2046

Construction Stalled

A joint Committee has been set up by FAAN and Bi-Courtney to resolve the contractual disputes between the parties.

42Concession for the Acquisition, Installation, Operation and Management of World Class Integrated System in Designated Airports (MMA –Lagos, Abuja & Kano)The Federal Airports Authority of NigeriaMaevis Nigeria Ltd

10 years

October 2007 – October 2017

Terminated -2012

Terminated

The Commission is engaging the parties on amicable settlement of the dispute through the Mediation process.

District Engineering Infrastructure Sector

 

43

Concession for the Development of Engineering Infrastructure for Arterial roads, Storm water drainage network, Sewage network, Electrical distribution network and Telcom duct at the Katampe District, Phase II Federal Capital Territory

(FCT) Abuja

The Federal Capital Development Authority (FCDA)/

Federal Capital Territory Authority (FCTA)

Deanshanger Project Ltd

 5 years

October 2010 – October 2015

Contract Execution Stalled

The FCT inter-ministerial Committee is working to resolve the challenges of executing the contract

Housing Development Infrastructure Sector

44

Concession Agreement for the Reclamation and Infrastructural Development of FESTAC Phase II Housing Development Project –FESTAC Town, Lagos

Federal Ministry of Lands, Housing and Urban Development/The Federal Housing Authority (FHA)New FESTAC Property Development Company Ltd

30 years

8th September 2014 -7th September 2044

Currently stalled as a result of a court case  The Community is in court over land ownership with the Federal Housing Authority.

The project land area has been encroached by the local communities

The Parties are working together to limit the rate of encroachment on the project land.

Marine (Security) Infrastructure Sector

45Concession for the Tracking of Ships, Cargoes, Enforce Regulatory Compliance and Surveillance of the Entire Nigeria Maritime Domain – LagosNIMASAMessrs Global West Vessels

10 years

3rd April, 2012

Contract Suspended

The Court has ordered for an out-of-court settlement of the dispute between NIMASA and Global West Vessel Specialist Limited.

Parties are in arbitration to resolve the matter.

Mining (Iron ore) Infrastructure Sector

 

46Concession for the Rehabilitation, Completion, Management and Operation of the National Iron Ore Mining Company Ltd, including the right to Expand, Prospect, Explore, Excavate, Extract and Sales of the Ore and Products there fromFederal Ministry of Solid Minerals Development/National Iron Ore Mining Company Ltd

Global Infrastructure Nig Ltd/Global Steel Holdings Ltd

First entered into on 17th February, 2005 Following International Settlement, Modified Concession Agreement entered into Commencement Date: 1st August, 2016

Agreement has duration of Seven (7) Years from Effective Date

Contract Suspended

The Commission is monitoring compliance with the terms and conditions of the agreement.

A Presidential Project Implementation Team (PPIT) has been set up to work out modalities towards resuscitating the Ajaokuta Steel Complex. ICRC is a member of the PPIT.

Defence Infrastructure Sector

47

Public Private Partnership and Joint Venture Agreement for the Establishment of a Military Clothing Factory

Kaduna, Kaduna State

Defence Industries Corporation of      Nigeria (DICON)

SUR Corporate Wear Tasarim Dani Manlik GYM SAN VE TIC AS (SUR) Turkey

50 years

24th October 2019 -
23 October 2069

Contract Signed

The Commission is monitoring compliance with the terms and conditions of the agreement.

The Construction work is at advanced stage  about 60% completed rate on the factory building.

48Concession contract for the Design, Finance, Upgrade, Operate and transfer of the Nigerian Correctional Service Shoe and garment Factories at Aba in Abia State and the Leather (Tannery) Factory at Janguza, Kano State, under a Public Private partnership arrangement.Nigerian Correctional Service (NCoS)Erojim Invesment Limited

20 years

13th January 2021-

12th January 2041

Contract Signed

The Commission has taken custody of the Contract and is monitoring compliance with the terms and conditions of the agreement.

49Concession contract of the integrated digital trunking communications system designed to provide a robust, reliable, secured and independent multimedia communication systems (voice, video and data) for the Nigerian Police Force and other security agencies of government.Federal Ministry of Police AffairsMessrs. MPS Technologies Ltd30 years, with the first 36 months designated for rehabilitation work

Contract Signed

Provision of Power to about 50 Base Stations are ongoing.

A Co-location license has been granted to MPS Tech. by the NCC.

Information Technology and Communication Infrastructure Sector

 

50

Concession for the Production of ECOWAS Biometric Identity Cards

Federal Ministry of InteriorEuphoria Press Limited

10 years

16th April 2019 –

15 April 2029

Contract Signed

Commission has taken custody of Concession Agreements and commenced monitoring of efficient execution of contractual terms.

51Concession contract for the Design, Development, and Management of a Secured Ticketing solution for the NRC Rail Services for the Five (5) stations along NRC rail Corridor between Abuja and Kaduna.Nigerian Railway Corporation (NRC)SecureID Limited

10 years

18th November, 2020 - 17th November, 2020, subject to any future amendment on the contract term

Contract Signed

Commission has taken custody of Concession Agreements and commenced monitoring of efficient execution of contractual terms.

52

Concession Agreement for the Implementation of the Nigeria Harmonised ECOWAS Electronic (SMART) Passport and Autogate Systems

Federal Ministry of Interior formerly Federal Ministry of Internal Affairs

IRIS Smart Technologies Ltd

Implementation was supposed to be for 2 years from 14th May, 2003

Contract Signed

Commission has taken custody of Concession Agreements and commenced monitoring of efficient execution of contractual terms.

Electricity (Hydro & Solar) Infrastructure Sector

53

Concession Agreements for the Operation, Maintenance, Design and Sales of electricity produce – Niger State

Kainji Hydro Electricity PlcMainstream Energy Solutions Ltd

30 Years

21st February 2013 –

20th February 2043

Under implementation.

The Operator has carried out replacement of 2 Hydraulic Power Unit (HPU) at Kainji and 3 sets of HPU at Jebba to ensure optimal power generation

54Concession Agreements for the Operation, Maintenance, Design and Sales of electricity produce – Niger StateShiroro Hydro Electric PlcNorth South Power Company Ltd

30 Years

21st February 2013 –

20th February 2043

Under implementation.

Currently generating about 150MW on the average. During off peak and peak period, the plant generates 100MW and 270MW respectively.

There’s high level of insecurity within surrounding communities of Shiroro Dam

55Concession for the Design, Construct, Install, Operate and Maintain the Dadin Kowa Hyro Dam for the purpose of Electricity Generation with a capacity of 39 MW – Gombe StateFederal Ministry of Water ResourcesMabon Limited

25 years from 4th July, 2005

Addendum to the agreement signed on 4th August, 2016

Commencement from Effective Date: Upon Reaching Financial Close

Under implementation.

The Hydro Station commenced generation in December, 2020

Generating 16mw of electricity and supplying to the National grid.

56Concession of Gurara Hydro Power Project Kaduna Operate and Maintain PPP project (30 Mega Watts)Federal Ministry of Water Resources

North South Power Company Limited

25 years from commencement date

Contract Signed; 12th May, 2020

Under implementation.

The Concessionaire is collaborating with TCN to carry out repairs on the transmission lines and substations;

Concessionaire is targeting 2nd Quarter 2022 to commence generation

57

Concession for the Service Management of Gurara Phase 1 Multipurpose Dam Facilities

Federal Ministry of Water Resources

Messrs Gams and Abell Ltd, in Conjunction with Ryzyn Global Inc USA

10 years

30th December 2019 – 29th December 2029

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Concessionaire is liaising with TCN, NBET, NERC to obtain approvals to support service operations.

58Concession of Rooftop solar Power,750 kilowatts (KW) solar power system for Federal Ministry of Power, Works and Housing (Power House) building in AbujaFederal Ministry of Power, Works and Housing (Power Sector)

Proserve Energy Ltd

10 years

14th March 2019 – 13th March 2029

Under implementation.

The Commission is monitoring compliance with the terms and conditions of the agreement.

Concessionaire has secured financing from the Nigerian Infrastructure Development Fund

Power Purchase Agreement (PPA) has been signed.

Agriculture (Silos- Storage) Infrastructure Sector

 

59Concession of Grain Storage Facilities for food storage (Silos) in Ado EkitiFederal Ministry of Agriculture and Rural Development

Agro-Universal
Consortium

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

60Concession of Grain Storage Facilities for food storage (Silos) in AkureFederal Ministry of Agriculture and Rural Development

Agro-Universal
Consortium

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

61Concession of Grain Storage Facilities for food storage (Silos) in GayaFederal Ministry of Agriculture and Rural Development

Agro-Universal
Consortium

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

62Concession of Grain Storage Facilities for food storage (Silos) in IkenneFederal Ministry of Agriculture and Rural Development

Agro-Universal
Consortium

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

63Concession of Grain Storage Facilities for food storage (Silos) in JosFederal Ministry of Agriculture and Rural Development

Agro-Universal
Consortium

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

64Concession of Grain Storage Facilities for food storage (Silos) in OgojaFederal Ministry of Agriculture and Rural Development

Agro-Universal
Consortium

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

65Concession of Grain Storage Facilities for food storage (Silos) in SokotoFederal Ministry of Agriculture and Rural Development

Agro-Universal
Consortium

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

66Concession of Grain Storage Facilities for food storage (Silos) in IgbariamFederal Ministry of Agriculture and Rural Development

Coscharis Farms Limited

 

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

67Concession of Grain Storage Facilities for food storage (Silos) in EzilloFederal Ministry of Agriculture and Rural Development

Ebony Agro Industries Ltd

 

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

68Concession of Grain Storage Facilities for food storage (Silos) in IbadanFederal Ministry of Agriculture and Rural Development

Independent Ltd

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

69Concession of Grain Storage Facilities for food storage (Silos) in BulasaFederal Ministry of Agriculture and Rural Development

Matrixville Consortium Ltd

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

70Concession of Grain Storage Facilities for food storage (Silos) in JahunFederal Ministry of Agriculture and Rural Development

Matrixville Consortium Ltd

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

71Concession of Grain Storage Facilities for food storage (Silos) in KadunaFederal Ministry of Agriculture and Rural Development

Matrixville Consortium Ltd

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

72Concession of Grain Storage Facilities for food storage (Silos) in Kwali,Federal Ministry of Agriculture and Rural Development

Matrixville Consortium Ltd

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

73Concession of Grain Storage Facilities for food storage (Silos) in Lafiagi,Federal Ministry of Agriculture and Rural Development

Matrixville Consortium Ltd

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

74Concession of Grain Storage Facilities for food storage (Silos) in UyoFederal Ministry of Agriculture and Rural Development

Neon Farms Ltd

 

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

75Concession of Grain Storage Facilities for food storage (Silos) in GombeFederal Ministry of Agriculture and Rural DevelopmentServewell Agricultural Services Limited

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.

76Concession of Grain Storage Facilities for food storage (Silos) in MakurdiFederal Ministry of Agriculture and Rural Development

Upland Grains Ltd

 

10 Years

2018 - 2028

Under implementation.

The Commission has taken custody of Concession Agreement and is collaborating with the Ministry to address contract challenges.