Lekki Deep Sea Port at 81 percent completion - ICRC

Lekki Deep Sea Port at 81 percent completion – ICRC

March 1, 2022 PRESS RELEASE Lekki Deep Sea Port at 81 percent completion – ICRC The Infrastructure Concession Regulatory Commission (ICRC) wishes to state that the Lekki Deep Sea Port project is now over 80 percent completed. Although it was widely reported across several media outlets that the project is at 96 percent completion, the Commission wishes to clarify that the project is at 81.14 percent completion. Breakdown of the completion status show that: dredging […]