Projects
ICRC superintends and regulates PPPs in Nigeria

Projects Under Development and Procurement (Pre-contract)


 

 

INFRASTRUCTURE CONCESSION REGULATORY COMMISSION 

PRE-CONTRACT PROJECTS (AT DEVELOPMENT AND PROCUREMENT) STATUS REPORT, AS AT DECEMBER 31, 2022

(IN SECTOR FORMAT)

 

S/N

 

MDA

 

PROJECT / DESCRIPTION

 

SECTOR

 

STATUS

 

PHASE

1

Federal Ministry of Agriculture and Rural Development

 

Deployment of 2,000 units of tractors and other mechanized equipment to Federal Ministry of Agriculture and Rural Development through SMART total mechanization package.AgricultureOn April 16, 2018 representatives of FMARD and Nigeria Agriculture Mechanization and Equipment Leasing Limited (NAMEL) made a presentation to the Commission on the proposed PPP arrangement titled ‘Solutions for Sustainable Food Production’.Development
2Federal Ministry of Agriculture and Rural Development

Projects, involving PPPs on:

i.      Federal Coastal Fishery Terminal, Ebughu, Akwa Ibom State

ii.     Federal Coastal Fishery Terminal, Borokiri Rivers State

iii.   Fish Processing Centre, Jebba, Kwara State

iv.   Agro Aviation Hangar, Kaduna

 

AgricultureFederal Executive Council approved the project on February 16, 2022 for a concession period of 11 yearsProcurement
3Federal Ministry of Education/University of AbujaDevelopment of Commercial Farm

Agriculture/

Education

Declined issuance of OBC Certificate of Compliance due to non-compliance on the 16th of June 2022

Development

 

 

 

 

 

4National Veterinary Research Institute/
Federal Ministry of Health
 
Vaccine Production Facility
National Veterinary Research Institute (NVRI) is desirous to commercialize vaccine production within the institute. 

Agri-Health

 

The Commission advised NVRI on the composition of the Project Steering Committee (PSC).Development
5

Federal Ministry of Aviation

 

Concession of Mallam Aminu Kano International Airport, Kano
The FGN proposed to concession the Mallam Aminu Kano International Airport Terminal Building, Kano State as part of aviation sector reform programme 
Aviation

The Commission participated on the bidder’s conference held in Abuja on 20th June, 2022 and also the site visit with the pre-qualified bidder on 21st June, 2022

 

Next step:

Submissions of RfP by the pre-qualified bidders

 

Procurement
6

Federal Ministry of Aviation

 

Concession of Port Harcourt International Airport
The FGN proposed to concession the Port Harcourt International Airport Terminal Building, Rivers State as part of aviation sector reform programme 
Aviation

The Commission participated on the bidder’s conference held in Abuja on 20th June, 2022 and also the site visit with the pre-qualified bidder on 22nd June, 2022

Next step:

Submissions of RfP by the pre-qualified bidders

 

Procurement
7

Federal Ministry of Aviation

 

Concession of Murtala Muhammed International Airport, Lagos
The FGN proposed to concession the Murtala Muhammed International Airport Terminal Building, Lagos State as part of aviation sector reform programme 
Aviation

The Commission participated on the bidder’s conference held in Abuja on 20th June, 2022 and also the site visit with the pre-qualified bidder on 23rd June, 2022

Next step:

Submissions of RfP by the pre-qualified bidders

 

Procurement

 

 

 

 

 

 

8

Federal Ministry of Aviation

 

Concession of Nnamdi Azikiwe International Airport, Abuja
The FGN proposed to concession the Nnamdi Azikiwe International Airport Terminal as part of aviation sector reform programme 

 

Aviation

The Commission participated on the bidder’s conference and the site visit with the pre-qualified bidder, held in Abuja on 20th June, 2022

Next step:

Submissions of RfP by the pre-qualified bidders

 

Procurement
9

Federal Ministry of Aviation

 

Development of a Maintenance, Repairs and Overhaul (MRO) Facility
The FGN intends to establish an MRO facility for aircraft maintenance, inspections and supply of parts to the aviation sector 

Aviation

 

 

Catamaran Consortium was procured as Transaction Advisers (TAs).

OBC Compliance Certificate issued 21st May, 2018.

FBC Certificate of Compliance issued on August 18, 2022

 

Project approved by FEC on October 12, 2022

Procurement
10

Federal Ministry of Aviation

 

Establishment of an Aviation Leasing Company (ALC)
The FGN intends to establish an ALC for the leasing of aircrafts to operators in the country and the continent as none exist in Africa at the moment.
Aviation

Awaiting report of the evaluation process with selection of the preferred bidder from the Ministry

Draft Contract Agreement for the project was sent to the Commission on June 21, 2021

 

FBC Certificate of Compliance issued on August 18, 2022

Procurement

 

 

 

 

 

 

 

 

 

 

11

Federal Ministry of Aviation

 

Development of an Aerotropolis (Airport City)
The FGN intends to develop an Aerotropolis in a suitable location to be determined by the TA. This entails the setting up and development of structures that will support the activities around the airport and aviation in general. 
Aviation

OBC Compliance Certificate issued 1st March, 2022.

 

Next step:

Investor procurement and Negotiation stages.

Procurement
12

Federal Ministry of Aviation

 

Development of a 6 Cargo/Agro Airports in the Geo-Political zones
The FGN intends to develop 6 Cargo/Agro airports in each of the geo-political zones to provide cargo handling and specialized logistics for agro products. 
Aviation

OBC Compliance Certificate to FMoA on 1st June, 2022 and RFQ has been advertised for prospective investors

 

Next step: Investor procurement and Negotiation stages.

Procurement
13Federal Ministry of AviationEstablishment of a National Carrier
The FGN intends to establish a National Carrier for the country through a PPP arrangement. The national carrier will have a hub in a designated airport as one of the outcomes of the assignment from the TA.
AviationEthiopian Air Consortium has emerged the preferred bidder of the National CarrierProcurement
14Nigeria police ForceConcession of Nigerian Police Air Wing aircrafts and facilitiesAviation

RfQ evaluation Completed on September 20, 2022

Next Steps:

Submission of evaluation report following RfQ

Procurement
15National Commission for Museums & Monuments/ Federal Ministry of Information & CultureDevelopment of Recreational Park within the Museum premises, Enugu.
(Unsolicited Proposal): An unsolicited proposal submitted to the National Commission for Museums & Monuments to develop recreational park in Enugu, within the Museum premises.
CultureNo correspondence from the Ministry on this since 2017. Awaiting formal correspondence on the way forward from  NCFMM & MoI&C.

Development

 

 

 

 

 

 

 

16Federal Ministry of Information and CultureNational Theatre
(Solicited Proposal)
: The project involves the development of 65 hectares of the 134 hectares fallow land around the National Theatre by building 5-star hotel, office buildings, leisure Park, shopping mall and Multi Level car park.
Culture

Full Business Case (FBC) Certificate of Compliance revalidation has been granted by ICRC.

Ministry is to submit FBC for approval by FEC

Procurement
17Federal Ministry of Information and CultureDevelopment of National Council for Arts and Culture’s land through PPP
The Council is desirous of developing an edifice on its parcel of Land located at Central Business District, Abuja through PPP that will comprise the following:
i.  Culture and Arts Theatre
ii. Office Development for use by
NCAC
iii. Conference and event exhibition hall,
Shopping Mall
CultureThe Ministry is required to engage a Transaction Adviser to prepare an Outline Business Case to determine project viability and bankability.Development
18Federal Ministry of EducationPPPs involving the following:
i. Upgrade of the ICT Laboratories/Business Centers in Federal Schools
ii. Upgrade of existing libraries
Upgrade of vocational schools
EducationThe Ministry is in the process of procuring Transaction Advisers to prepare Outline Business Cases to determine the projects’ viability and bankability.Development
19Federal Ministry of EducationNational Mathematical Center
i. Development of an International Conference Center
Construction of National Mathematical Centre-International Science Academy (NMC-IMSA)
EducationThe Ministry is in the process of procuring Transaction Advisers to prepare Outline Business Cases to determine the projects’ viability and bankability.Development
20Federal Ministry of Education / Federal University Gusau (FUG) PPPs involving the following:
i. Proposed construction of Students Hostel, 500-Units of Staff Housing, Roads & Drainages, Shopping Mall, Staff/Students Cafeteria, Bio-gas Electricity Power plant and Poultry Farm
ii. On-line application System for e-registration platform, Computation / compilation of Students’ results, e-Learning and web portal development.
Proposed construction of Vice Chancellor’s Lodge, Pro-Chancellor’s Lodge, Principal Officers’ Quarters, Senior Staff Housing, Junior Staff Housing, External Electrification, Borehole & Overhead Tanks, etc
EducationThe University is in the process of procuring Transaction Advisers to prepare an Outline Business Cases to determine the projects’ viability and bankability
ICRC reviewed the submitted documents in line with statutory processes. University written to supply additional information on the project and also confirm availability of land space for the entire project. 
Development
21Federal Ministry of EducationComputer Based Test Centre (National Business and Technical Examinations Board)
The Computer Based Test (CBT) Centre project is to enhance efficiencies of candidates in Technical and Vocational Education through Information and Computer Technology.
EducationThe Project is currently functional but the NABTEB has been asked by the Commission to forward relevant documents on the project to the Commission.
The Business Case and Executed Contract Agreement were reviewed and it was found that it did not satisfy the key features of PPP contracts. The Commission requested additional documents to incorporate the issues raised.The Board has been advised to submit a Joint OBC/FBC for review.
Procurement
22Federal Ministry of EducationDevelopment of Commercial Hub at National Open University of Nigeria (NOUN)
The National Open University of Nigeria is desirous of building a commercial hub for the University Community within the campus at Jabi, Abuja using the PPP arrangement.  The complex will have the following facilities Banking malls, Supermarket, Restaurants, Bookstore, retail shops etc
EducationICRC issued an OBC Certificate of Compliance on the October 7, 2017Procurement
23Federal Ministry of Education/ University of AbujaDevelopment of Students Hostel at University of Abuja
The University intends to build hostels for its teeming students as well as staff housing estate using PPP
EducationOBC certificate of Compliance was granted on 23rd September, 2020.
Letter nominating PSC and PDT members was sent to UNIABUJA on 20/11/2020.
Procurement
24Upgrade and concession of hostel at Public Service Institute of NigeriaUpgrade and Concession of Properties through PPP methodology
Public Service Institute of Nigeria is desirous of using PPP procurement methodology to upgrade and concession to private party its 108 rooms female hostel and 27 rooms guest chalet.
EducationThe project is currently in development phase. The Institute is working with consultants to prepare an Outline Business Case to determine project viability and bankability.Development
25Federal Ministry of Health/UCH, IbadanDevelopment of Shopping Mall, University College Hospital (UCH), Ibadan
UCH seeks to develop a Shopping Mall through PPP Procurement.
Education

Sensitization workshop and Inaugural PDT meeting held on October 17 & 19, 2017 at the Hospital premises.

Arrangements are in place to regularize the existing MoU with the Concessionaire. A meeting took place at Federal Ministry of Health in October 2020.

Development
26Federal University, Wukari/Federal Ministry of EducationDevelopment of hostel facilities and accommodation for Staff and StudentsEducationThe submitted project proposal document has been reviewed and the University was advised to prepare an OBC.
Awaiting the University’s response.
Development
27Federal Ministry of Education / Federal College of Education, Ogun StateDevelopment of Student Hostels at Federal College of Education Abeokuta, Ogun State
Federal College of Education Abeokuta seeks guidance to develop hostel accommodation using PPP procurement process.
EducationNo correspondence from the Ministry on this since 2019. Awaiting formal correspondence on the way forward from Federal Ministry of Education / Federal College of Education, Ogun State.Development
28Federal Ministry of PowerEnergizing Education Program
Electrification Program of Tertiary Institutions initiated by the FMPW&H to develop off-grid power plant projects in order to provide uninterrupted and dedicated power supply to forty (40) Federal Universities and neighboring University Teaching Hospitals across the Federation.
EducationThe FMPW&H is to prepare a structuring report and submit to ICRC.Development
29University of Calabar/ Federal Ministry of Education400 Room Students Hostel
The project consists of two hostels that will comprise 400 rooms on a 1.9 Hectares land within the University of Calabar premises and is estimated to cost N1,326,000,000 with a completion period of 9 months
EducationUNICAL has been advised to repackage the project to meet requirements of N4P and ICRC Act.Development
30Federal Ministry of Education/ National Commission for Colleges of Education (NCCE)Development of Hostel Accommodation for Colleges of Education
The Ministry received an unsolicited proposal by Adonai Ventures Ltd to build hostel accommodation for Colleges of Education in Nigeria.
EducationNo correspondence from the Ministry on this since 2019. Awaiting formal correspondence on the way forward from Federal Ministry of Education / NCCEDevelopment

31

 

 

 

 

Federal Ministry of Education/University of Port-Harcourt

 

Regularization of Build Operate and Transfer Process for the development of Retail and Entertainment Centre
The University of Port-Harcourt seeks to regularize an ongoing PPP Project to conform with National PPP Laws  
Education

ICRC reviewed a signed agreement with regards to the project with the aim of regularizing and legalizing the PPP process that was started by the University, but which had not gone through ICRC, to conform with the ICRC Act.

Inaugurated the PSC and PDT as well as due diligence visit to UNIPORT from 26th- 28th Jan 2022.

Procurement
32Federal Ministry of Education/University of Port-HarcourtDevelopment and Construction of Private Students’ Hostel Accommodation For University Of Port-HarcourtEducationThe Commission has reviewed the submitted OBC and has advised the University accordingly.

Development

 

 

 

 

 

33Federal Ministry of Education/University of Port-HarcourtRegularization of Build Operate and Transfer Process for the development of Entertainment Centre
The University of Port-Harcourt seeks to regularize an ongoing PPP Project to conform with National PPP Laws
Education

The review of the Project Structuring report is ongoing.

A letter highlighting the discussions and next steps during the project site assessment and monitoring visit at the UNIPORT was sent to the university on the 30th of March, 2022

Development
34Federal Ministry of Education/Federal University of Petroleum Resources, EffurunEstablishment of a Bespoke food Court on Design, Finance, Build, Operate and Transfer (DFBOT) Scheme.Education

OBC Compliance Certificate issued on the 30th of September, 2021.

PDT & PSC inaugurated on 21st April 2022

Procurement
35Federal Ministry of Education/University of Port Harcourt

PPP Projects:

The University seeks to develop and construct 110 units of shops. The shopping complex is to be procured via PPP with OSIWOKS Nig. Ltd and is to be located close to the Presidential and Medical hostels in the Abuja Park.

Education Declined issuance of OBC Certificate of Compliance via letter dated 30th Dec, 2021 pending provision of more information in line with N4P.Development
36Federal Ministry of Education/University of Port Harcourt

PPP Projects:

The University seeks for the establishment of a Loading Bay for Taxis/Buses, University Park by the main gate area (Abuja Park).

EducationLetter issued to the University on 11th June, 2021 declining the issuance of OBC Certificate. Declined issuance of OBC Certificate of Compliance via letter dated 30th Dec, 2021 pending provision of more information in line with N4P.Development
37Federal Ministry of Education/ University of UyoConstruction Of students Hostels on a PPP arrangement.
The University of Uyo is seeking to collaborate with a Private Proponent for the development of student’s hostels at the various campuses of the University with a capacity for 12,000 bed spaces.
Education

Issued certificate of Compliance on the 25th of May, 2022.

A letter dated 14th July, 2022 on the draft advert was sent to University of Uyo.

Procurement
38Federal Ministry of Health/University College Hospital Ibadan

PPP Projects:

Establishment and Operation of an Independent Power Plant in the Hospital

Education/ EnergyA letter dated 2nd July, 2021 was sent to the Ministry to provide more information to confirm viability and bankability of the project.Development
39Federal Ministry of Health/ University of Ibadan College HospitalEstablishment and Operation of an Independent Power Plant in the University College HospitalEducation/ PowerOBC Certificate of Compliance issued on the 20th of April, 2022Procurement
40Airforce Institute of Technology, Kaduna

Unsolicited PPP proposal:

submitted by private proponents on the development of students’ hostels

Education/ Urban DevelopmentMet with the Management team on the 9th June 2021 and highlighted the processes of Solicited and Unsolicited processes.Development
41Ahmadu Bello University ZariaDevelopment of Shopping Complex and Luxury Apartments at GRA Zaria through a PPP arrangementEducation/Urban DevelopmentOBC certificate of Compliance issued on September 22, 2022Procurement
42Federal Ministry of Education/Federal Polytechnic Ado-Ekiti

Development of Hostel complex

At Fed-Poly Ado-Ekiti

Education/ Urban DevelopmentDeclined issuance of OBC Certificate of Compliance on the 19th of April, 2022Development
43Federal Polytechnic, BauchiConstruction of Students Residential Hostel Blocks (Federal Polytechnic, Bauchi and EMKOANAL International Nigeria Limited)EducationA letter was sent on 11th October, 2022 was sent to Federal Polytechnic, Bauchi stating that the contract agreement with the project proponent was disagreed to by the commission, due to the stage of the projectDevelopment
44Federal Ministry of Water ResourcesGurara 2 Greenfield Multi-Purpose Dam
The Concession of the Gurara 2 Greenfield multi-purpose Dam, Niger State includes 300MW of hydropower components of the dam.
EnergyThe project is currently in Development Phase. The project land is encumbered and the Ministry is resolving the issue. Thereafter, the Outline Business Case is expected to be forwarded to ICRC. Awaiting the Ministry’s response.Development
45Federal Ministry of Water ResourcesOwena Multi-Purpose Dam water supply (Unsolicited Proposal)
The project will provide about 1.5kwh of electricity to the national grid.
EnergyThe Commission granted OBC Certificate of Compliance on March 10, 2017.Procurement
46Federal Ministry of Water ResourcesDevelopment of 9MW Oyan Dam Unsolicited
This involves the Operations and Maintenance of 9MW hydroelectric power.
EnergyThe Commission has revalidated the OBC Certificate of Compliance (which expired on March 8, 2018) since all key parameters remained the same.Procurement
47Federal Ministry of Water ResourcesDevelopment of 220MW River Mada Medium hydropower plant in Nasarawa State
This involves the Operations and Maintenance of 220MW hydroelectric power.
EnergyThe Commission reviewed the updated OBC and issued a Compliance Certificate on February 23, 2018.Procurement
48Federal Ministry of Water ResourcesOther PPP Projects:
i. Concession of Oturkpo Dam for Hydro Power and other purposes.
ii Development of Dasin Hausa Dam for Hydro power and other purposes.
EnergyThe Ministry has been advised to procure a Transaction Adviser that will prepare a bankable OBC report for the project.

Development

 

 

 

 

 

 

49Federal Ministry of Mines and SteelAjaokuta Steel company Ltd & National Iron Ore Mining Company (NIOMCO)
Rehabilitation, completion, management and operation of Ajaokuta Steel Company and National Iron Ore Mining Company (NIOMCO) through PPP Concession agreement.
Energy

Meeting with the Ministry and the TA held on 2nd September, 2022.

 

Status update meeting with the Honorable Minister of State for Mines and Steel Development held on the 25th of November 2022.

Development
50Federal Ministry of Power/Nigerian Electricity Management Services Agency (NEMSA)Transformer Repair Services
The project is an unsolicited proposal submitted by Kilowatt Electrics Limited (KWEL) to the NEMSA. KWEL is proposing a joint venture partnership with NEMSA to operate the transformer repairs workshop in Ijora Lagos and construction of transformer repair workshops in Port Harcourt and Kaduna centers. The partnership will also include the role of electrical inspection, testing and certification of all electrical installation hitherto performed by NEMSA.
EnergyTechnical Bid opening for concessionaire took place on May 17, 2021
Financial Bid opening for concessionaire took place on  June 7, 2021.
Procurement
51Federal Capital Territory/ Abuja Infrastructure Investment Center (AIIC)Small Hydropower Embedded Power from the Wupa Water Treatment Plant Effluent Discharge
Wupa Water Treatment Plant Project on a Build Operate and Transfer (BOT) PPP model to produce electric power from the effluent discharge from the plant. Power generation capacity is estimated at 3,346.29kW/day which would power the WWTP and also provide the input for the production of fertilizer and plastics.
The power plant is expected to sell excess power to the national grid.
EnergyNo correspondence from the Ministry on this since 2017. Awaiting formal correspondence on the way forward from Federal Capital Territory/AIIC.Development
52Federal Ministry of PowerConcession of 1.2MW Grid Connected PV Solar Power Plant
Concession of 1.2MW Grid Connected PV Solar Power Plant at Lower Usuma Dam, Abuja under the Japanese Grant-In-Aid to the FGN
Energy

OBC Certificate of Compliance was issued on 13th September, 2017.

 

 

 

 

Procurement

 

 

 

 

 

 

 

 

 

53Federal Ministry of Petroleum ResourcesNNPC Refineries Rehabilitation Project
The project will involve the rehabilitation of refineries across the country.
Energy

Virtual Bid Opening for EPC Contracts on Port-Harcourt Refinery took place on July 24, 2020.

Virtual Bid Opening for EPC Contacts on Warri and Kaduna Refineries took place on 25 August, 2020.

Procurement
54Federal Ministry of Petroleum ResourcesConstruction Of LPG And Ethanol/Methanol Plants At Emede Uzere Delta State (On Public Private Partnership (PPP) Basis)
The construction of an LPG and Ethanol/Methanol Plant at Emede Uzere, Delta State from Everlinksourcing Ltd to the Ministry of Petroleum Resources.   Identification of Public Private Partnership projects for Petroleum Equalization Fund,
EnergyNo further Correspondence from Ministry on this project

Development

 

 

 

 

 

 

 

 

 

 

 

 

55Federal Ministry of Power700 MW Zungeru Hydro Electric Power Plant.Energy

Technical bid opening and evaluation for TA selection took place on June 23, 2021.

OBC certificate of compliance issued on September 5, 2022.

 

RfQ documentation submitted by BPE for ICRC concurrence on September 28, 2022. RfQ and advert reviewed and sent to BPE.

Review of 11 bids on the ZHPP held on the 28th and 29th of November 2022.

Procurement
56Federal Ministry of Petroleum Resources/NNPCFMoP have sent concept notes to the Commission and are keen to develop the following projects;
i. Concession and development of 25MW Katsina Wind Farm
ii. Concession and development of 215MW Kaduna Power Plant
iii. Concession and development of 10MW lake Chad Basin Development Authority, Borno.
Concession and development of 1.2MW Solar facilities at Lower Usuma Dam.
Energy

The Commission received concept notes on April 12, 2018. The Ministry has been requested to update the Concept Notes and engage a TA to assist with the process.

 

 

 

 

 

 

 

Development
57Federal Ministry of Power University of Benin 15MW Solar Project (Unsolicited Proposal)
The project is a 15MW PV Solar power to be sited on a 30Hectare parcel of land at the University of Benin Ugbowo Campus.
EnergyRFP evaluation exercise has been conducted by UNIBEN.
A virtual meeting was held between ICRC E&U Unit and UNIBEN project Team on the 3rd November 2020 to discuss critical dynamics of the project structure to ensure commercial close can be successful achieved.UNIBEN Team is to revert with all the actionable steps discussed and agreed.

Development

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

58Federal Ministry of EducationDevelopment of Hydro power from Kiri DamEnergySettlement meeting held on 14th Aug, 2019.
The Attorney General and Minister of Justice has issued a Legal Opinion for guidance vide a letter on 22nd July, 2020 on the Kiri suit.At the meeting held with the Minister on May 17 2021, ICRC informed that this procurement should be conducted through a solicited process, hence the ministry should engage a transaction adviser to prepare OBC and Financial Model.
Development
59Federal Ministry of Water ResourcesSolar Power Off-Grid Rural Electrification
The provision of off-grid solar power to the remote rural communities in Taraba, Gombe, Niger, Kogi, Ebonyi, Oyo, Ogun, Edo, Akwa Ibom, Katsina and Kebbi states
EnergyJoint OBC/FBC compliance certificate was Revalidated 7th October 2020.

Procurement

 

 

 

 

 

 

60Federal Ministry of Power/ Electrification Agency40 MW Kashimbila Dam Hydropower Station
Kashimbila Dam is a 32m high composite dam with a 40 MW hydropower station located on the Katsina-Ala River, Taraba State, a tributary of the Benue River, approximately 20 km downstream of the Nigeria-Cameroon border. It comprises a zoned rockfill embankment with a central mass gravity ogee spillway, an outlet works which consist of multi-level intakes and outlet structure.
Energy

The Commission granted OBC Compliance Certification on October 15th, 2018.

Evaluation of technical bids completed on the 16th and 17th of March 2022. Awaiting approval to open financial bids from the Honorable Minister.

Negotiations carried out with preferred bidder in September 2022.

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

 

61Federal Ministry of PowerMakurdi Hydropower Project
The Makurdi Hydropower Project (Makurdi HPP) was originally conceived as part of the Plan for Electric Power System Development issued by the then National Electric Power Authority [NEPA] in 1974. The planned dam site is located on the Benue River, the primary tributary of the Niger River in Nigeria, about 10 ~ 15 km upstream of Makurdi, the capital of Benue State.
Energy

The Commission granted OBC Compliance Certification on October 15th, 2018.

A joint stakeholder meeting was held on the 14th July 2022 at the BPE’s office to discuss the status of the project. A key highlight was the increase in the nameplate capacity from 1500MW to 1650MW.

Outline Business case CoC issued on the 28th of August 2022.

Project Steering Committee (PSC) was inaugurated on the 12th of December 2022. Key members included the Minister of Power and Water Resources who would serve as Chairman and Co-chairman.

Procurement
62Federal Ministry of PowerDevelopment of 136 MW Manya Hydropower Generation Facility, Taraba StateEnergyThe OBC compliance certificate for Manya Hydro Power Plant (HPP) was revalidated on 26th October 2020.OBC Certificate of Compliance revalidated on the 6th of May 2022.  RfQ documents reviewed and sent to the Ministry.

Procurement

 

 

 

 

 

 

 

 

63Federal Ministry of Water ResourcesDevelopment of 182 MW Bawarku Hydropower Generation, Benue StateEnergy

The OBC compliance certificate for Bawarku Hydro Power Plant (HPP) was revalidated on 26th October 2020.

OBC Certificate of Compliance revalidated on the 6th of May 2022.

Review of RfQ documents ongoing.

RfQ documents reviewed and sent to the Ministry.

Procurement
64Federal Ministry of Water ResourcesDevelopment of Hydroelectric power from existing 6 Small & Medium from dams across the Country
Federal Executive Council (FEC) gave an approval on the 30th November 2016 for 6 dams.
1. Bakolori Dam, Zamfara State
2. Omi - Kampe Dam, Kogi State
3. Doma Dam, Nasarawa State
4. Jibiya Dam, Katsina State
5. Zobe Dam, Katsina State
6. Ikere Gorge Dam, Oyo State
Energy

Ongoing finalization of the Concession Agreements between the Ministry and the Preferred. Bidders for onward transmission to the Federal Ministry of Justice for vetting.

A meeting took place between ICRC, FMOP, and their Legal Advisers AELEX Partners on 27 August 2020 to discuss ICRC’s recommendations for Ikere Gorge, Omi Kampe, Bakalori and Zobe & Jibiya hydro power plant Concession Agreements.

Ongoing review of FBC document for Ikere George Dam.

Procurement
65Federal Ministry of Power(Power)/ Federal Ministry of Water ResourcesDevelopment of Small, Medium and Large Hydropower Project Phase 2
Development of hydroelectric power from existing small, medium & large hydro dams in twelve (12) locations nationwide. As shown below:
Lot 3A
• 7MW Girmi Earth Hydropower Plant, Kaduna State (Brownfield)
• 1.2 MW Lower Usuma Hydropower Plant FCT (Brownfield)
• 9MW Oyan Hydropower Plant, Ogun State (Brownfield)
Lot 3B
• 138MW Dasin Hausa Hydropower Plant, Adamawa State (Greenfield)
• 40MW Kashimbilla Hydropower Plant, Taraba State (Brownfield)
• 92MW Garin Dalli Hydropower Plant, Benue State (Greenfield)
Lot 3C
• 182MW Bawarku Hydropower Plant, Benue State (Greenfield)
• 136MW Manya Hydropower Plant, Taraba State (Greenfield)
• 109MW Katsina Ala Hydropower Plant, Benue State (Greenfield)
Lot 3D
• 700MW Oguma Hydropower Plant, Kogi State (Greenfield)
• 1500MW Makurdi Hydropower Plant, Benue State (Greenfield)
• 441MW Onitsha Hydropower Plant, Anambra State (Greenfield)
Energy

The preferred and reserve bidders’ TA list will be communicated to the Commission once all assessments have been finalized by FMoP.

 

Makurdi Hydropower Project was upgraded to 1650MW. OBC Certificate issued on 29th August, 2022. Awaiting bidding documents.

 

Ongoing review of the 460MW Grand Katsina Ala OBC.

 

OBC Certificate of Compliance issued on the 15th of December 2022 for the 460MW Grand Katsina Ala hydropower project.

Development
66National Research Institute for Chemical Technology

Pyrolysis plant for the production of carbon black and diesel oil

 

EnergyOBC has been reviewed prior to the meeting and a report has been sent. Meeting between ICRC and the technical team of NARICT was held on the 20th of August 2021 to discuss on the OBC. NARICT is meant to re-submit the OBC effecting the corrections.Development
67National Research Institute for Chemical TechnologyPlant for the production of polyester yarn from waste materialsEnergyOBC has been reviewed prior to the meeting and a report has been sent. Meeting between ICRC and the technical team of NARICT was held on the 20th of August 2021 to discuss on the OBC. NARICT is meant to re-submit the OBC effecting the corrections.

Development

 

 

 

 

 

 

 

 

68National Research Institute for Chemical TechnologyPlant for the production of Bioplastic from biomassEnergyOBC reviewed and a report sent. Meeting between ICRC and the technical team of NARICT held on August 20 2021 to discuss on the OBC. NARICT is meant to re-submit the OBC effecting the corrections.Development
69Petroleum Equalization FundIdentification of Public Private Partnership projectsEnergyMeeting with the management staff of PEF and ICRC on the 19th day of August. PEF yet to decide projects to be undertaken as PPPs.Development
70Itisi Hydropower

Development of the 40MW hydropower in Kaduna State

 

Energy

Outline Business Case CoC issued on the 2nd of August 2022.

RfQ documents reviewed and sent to the Ministry.

Procurement
71Federal ministry of Water ResourcesDevelopment of Farin Ruwa Hydro projectEnergyOBC Certificate of Compliance issued on December 6, 2022 
72Federal  Ministry of Power Identification of PPP Projects for screening, prioritization and approval for procurement
Signed Memorandum of Understanding for Potential areas1 of collaboration.
The following projects are under consideration:
i. Establishment of Federal Ministry of Environment’s Clean and Green Campaign to end open defecation in public areas by 2019 by providing Public Toilets nationwide. Pilots to be in FCT public schools, motor parks and market places; and extended to the 36 States.
ii. Framework for Plastic Industry and other private sector companies to take plastic waste off the streets by 2019
iii. Development of a New Head Office for the Federal Ministry of Environment (to be completed in 2018)
iv. Establishment of Scrap metal recycling facility, Sokoto, Sokoto State.
v. Establishment of Scrap metal recycling facility, Kaduna, Kaduna State.
vi. Establishment of Scrap metal recycling plant, Emuoha, Rivers State.
vii. Establishment of Scrap metal recycling plant, Owerri, Imo State.
viii. Establishment of Ozone village in Ikenne Ogun State.
ix. A pilot indigenous project to capture Biogas from faeces/ urine in Federal Government Girls Secondary School, Abaji, Abuja FCT
Development of Pilot Cotter Mitigation from lanfill for Energy production Wupa Lanfill, Wupa Village Abuja
EnvironmentMeeting held on 30th May, 2019 between Ministry of Environment and ICRC regarding pipeline projects submitted to the Commission in 2018 and the way forward for reviving PPPs within the Ministry.Development
73Federal Ministry of Environment (FMoE)Establishment of a Bamboo Value Chain
Establishment of a Bamboo Value Chain Business including maintaining, managing and scaling up the Bamboo factory in Lokoja, Kogi state
EnvironmentAwaiting the submission of an updated OBC by the Ministry.Development
74Federal Ministry of HealthManagement Equipment Services (MES) project: To provide Medical Equipment and services in Government HospitalsHealthMeeting on MES sub-committee held on the 3rd and 29th of July 2019 review MES Concept note.Development
75Federal Ministry of Health/ University of Port Harcourt Teaching HospitalConstruction of staff housing estate, shopping complex and new House Officers’ (Doctors') quartersHealthAwaiting response from the University after a letter of non-viability was sent by ICRCProcurement
76Federal Ministry of HealthDevelopment of Oncology Centre of Excellence for Cancer Care in 8 Teaching Hospitals across the Geopolitical zones Federal Ministry of Health
The FGN through the Federal Ministry of Health seeks to procure and manage Oncology equipment in Federal Teaching Hospitals across the Country.
HealthThe PDT has adopted the option of Traditional Procurement / Leasing where payment is tied to equipment management and service/the continuous function of the machine on service delivery.
Awaiting further steps from the Ministry.

Procurement

 

 

 

 

 

 

 

 

 

77Federal Ministry of HealthUpgrade of the 3rd Phase of Teaching Hospital Rehabilitation Project
The Federal Government through the Federal Ministry of Health seeks to Rehabilitate 7 Teaching Hospitals and Construct a 500-bed state-of-the-art specialist hospital through PPP. This is the 3rd of the Teaching Hospitals rehabilitation process. The 1st and 2nd Phases were done with government funds
Urban Development

OBC Certificate of Compliance was revalidated and re-issued to the Federal Ministry of Health on the 24th of August, 2020, for an accelerated negotiated PPP pilot scheme for six (6) teaching hospitals, one in each of the Nation’s geopolitical zones.

 

OBC Certificate of Compliance was revalidated and re-issued to the Federal Ministry of Health with some adjustment of scope by the Federal Ministry of Health on the 30th of Dec, 2021.

Procurement
78Federal Ministry of HealthOrthopedic Hospital, Dala- Kano 
The proposed PPP seeks to construct staff quarters within the premises, conversion of existing bungalow within the hospital premises to commercial guest house, equipping of the Hospital mortuary building and Equipping, Furnishing and Operation of a Private wing of the Hospital.
HealthThe Ministry is in the process of procuring a Transaction Adviser to prepare an Outline Business Case to determine project viability and bankability.Development
79Federal Ministry of Health (FMoH)Establishment of Anti-Snake Venom Production Facility in Nigeria through PPP
The Ministry seeks the Establishment of Anti-Snake Venom Production Facility through PPP.
HealthInter-Ministerial Committee meeting held on 27th May, 2019 on proposed EDTV.

Development

 

 

 

 

80Federal Ministry of Health\ Federal College of Education (Technical) Bichi, Kano State.Development of hostel facilities and supermarket
FCE Bichi (Technical) seeks guidance to develop hostel accommodation.
HealthThe submitted document has been reviewed and the College has been asked to submit additional documents.
The Commission is awaiting response from FCE Bichi.

Development

 

 

 

 

 

 

81University of Calabar Teaching Hospital. Federal Ministry of HealthStudents & Staff residential accommodation
Unsolicited proposal for the Design, Build, Manage and Transfer of Students & Staff residential accommodation within the Hospital
HealthNo correspondence from the University on this project since 2020Development
82Federal Ministry of HealthOncology Centre and Operation of Oxygen Gas Plant at Aminu Kano Teaching Hospital, Kano
The management of Aminu Kano Teaching Hospital, kano wrote to the Honourable Minister proposing the implementation of the following projects through PPP: Establishment of Radiotherapy/Oncology Centre and Operation of Oxygen Gas Plant.
Health

Last PDT meeting was held on September 12th, 2018.

 

Development
83Federal Ministry of HealthDeployment of Thermal Health Scanners at the entry and exit points in Nigeria
In Compliance with International Health Regulations 2005 (IHR 2005) for the prevention and spread of diseases the Ministry of Health is desirous of deploying thermal health scanners at entry/exit points of the country.
HealthA PDT meeting was held on 5th July, 2019 to discuss issues raised by Federal Ministry of Finance on the OBC.Development
84Federal Ministry of HealthAbuja Healthcare City projectHealthPDT meeting held on 13th May 2019 to assess draft OBC.Development
85Federal Ministry of HealthNational Orthopaedic Hospital, EnuguHealthOBC Certificate of Compliance was withheld pending adjustments. Letter was dispatched on 20th July, 2020.Development
86Federal Ministry of Health/Usmanu Danfodio University, Sokoto

Public Private Partnership Initiative

Pharmaceutical Products and Surgical Consumables and Diagnostic Laboratory Services in Usman Danfodio University Teaching Hospital, Sokoto

HealthThe Commission has reviewed the submitted document and advised the University to provide more information to confirm viability and bankability of the project.Development
87Federal Ministry of HealthDEVELOPMENT OF ADVANCED SURGERIES CENTRES IN NIGERIA  The Federal Ministry of Health, submitted an unsolicited proposal developed by LAANJ International Ltd, requesting the Federal Government to allocate specific departments in three Nigerian Public hospitals, one each in Abuja, Jos and Port Harcourt, where they can bring in experts from India at intervals to perform advanced surgeries. The proposal aimed to be established as an Operation and Management (O & M) Pubic Private Partnership (PPP) modelHealthReview of the OBC completed. Awaiting response from FMoH.

Development

 

 

 

 

 

 

 

 

 

 

 

 

88Federal capital Territory Administration / Abuja Properties Development Company APDCDevelopment of District Hospitals
Development of district hospitals in Wuye, Galadimawa and Lugbe Districts of the Federal Capital City.
HealthMeeting between ICRC and officials of the FCT Hospitals Management Board held on February 17th 2021 on commencement of the PPP for the development of the hospitals.Development
89

Federal Ministry of Health

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MEMORANDUM OF UNDERSTANDING FOR THE PUBLIC PRIVATE PARTNERSHIP ON MEDICAL LABORATORY DIAGNOSTIC SERVICES AT THEAHMADU BELLO UNIVERSITY TEACHING HOSPITAL, ZARIA (ABUTH, ZARIA).
Federal Ministry of Health submitted an unsolicited proposal requesting the ABUTH Zaria to allocate space, electricity, water and security. While DNA LABS will supply all equipment and provide efficient Lab services in the following areas:
i. Chemical Pathology
ii. Immunology
iii. Microbiology
iv. Hematology
v. Forensics
vi. Molecular DiagnosticsThe Medical Laboratory Diagnostics Services is proposed to be established as a Supply, Operate and Management Pubic Private Partnership (PPP) which aims at making huge improvement in the quality-of-service delivery and earning capacity of the Hospital. 
HealthThe Commission has reviewed the document and advised the Ministry to provide more information to confirm viability and bankability of the project.Development
90Federal Ministry of Health/UCH IbadanProposed renovation and upgrading of School of Nursing students’ hostel in the hospitalHealth

OBC Certificate of Compliance issued on the 22nd of March, 2022.

Response letter written to UCH, Ibadan on the resubmission of OBC and financial model dated 23rd May, 2022

Development
91NNPC/NNPC Medical Services Limited (NMSL)

Development of Multi-Specialty Hospitals

The NNPC through its subsidiary seek to develop 5 Multi specialties hospitals in 5 locations, these locations are: Maiduguri, Port Harcourt, Lagos, Kaduna and Abuja. It also proposed the Establishment of Intravenous Fluid Plant in Kano through PPP methodology.

Health

OBC Compliance Certificates issued to NMSL on the 1st of April, 2022 for the proposed Multi-Specialist Hospitals (MSH) in Abuja and Port-Harcourt.

OBC Compliance Certificates issued to NMSL on the 21st of July, 2022 for the proposed Kano Intravenous Fluid (IVF) Plant project.

OBC Compliance Certificates issued to NMSL on the 21st of July, 2022 for the proposed Multi-Specialist Hospitals (MSH) in Lagos.

OBC Compliance Certificates issued to NMSL on the 21st of July, 2022 for the proposed Multi-Specialist Hospitals (MSH) in Maiduguri.

 

Procurement
92Federal Ministry of Health (Port Health)

Decontamination & Fumigation Project:

for vessels arriving all seaports in Nigeria (Lagos, Rivers, Delta, Calabar, etc)

Health

OBC Compliance Certificate issued on the 12th April, 2022.

A status report attached with Expression of Interest was sent to the ministry on the 23rd of December 2022.

Procurement
93University College Hospital Ibadan/Federal Ministry of HealthRehabilitation of Mortuary Facility in UCHHealthOBC Certificate of Compliance issued on September 2, 2022Procurement
94Federal Ministry of InteriorDevelopment of Advanced Passenger Information API, and Passenger Name Record PNR Portals
The Nigeria Immigration Service (NIS) through the Ministry of Interior are developing an Advanced Passenger Information API, and Passenger Name record PNR portals.
ICTNo correspondence from the Ministry on this since 2019Development
95National Lottery Regulatory Commission/ National Lottery Trust FundDeployment of Central Management System Platform
The National Lottery Regulatory Commission/ National Lottery Trust Fund are seeking to deploy of Central Management System Platform
ICTAwaiting formal correspondence on the way forward from NLRC/NLTF

Development

 

 

 

 

 

96Federal Fire ServiceDevelopment of National Fire Data Repository Center (NFDRC)
The project involves the upgrade, rehabilitation, operation and maintenance of the NFDRC Enterprise Unit through a PPP arrangement that provides an ICT-based system to ensures speedy detection and rapid response to fire emergencies in a self-funding and sustainable manner.
The project will cover the design and development of the NFDRC systems.
ICTFull Business Case revalidated on May 23, 2022Procurement
97Federal Fire Service/ Federal Ministry of InteriorSAFETY SYSTEMS NETWORKING, MONITORING AND DISPATCHER REAL-TIME INTEGRATION SYSTEM (LSSNMDI)ICT

OBC certificate of compliance issued on June 21, 2021.

RfQ closed evaluated

Direct negotiations with preferred bidder to commence on October 6, 2022

Procurement
98Federal Ministry of Finance, Budget and National PlanningDevelopment, deployment and management of Automated Customs Gateway Portal for Import Duty Exemption Certificate (IDEC) and Imported Vehicle identification Number Registration (VREG)ICT

FEC approved the project on November 29 2019

Next Step: contract Signing and custody of agreement

Procurement
99Federal Ministry of JusticeCriminal Justice Management Information System (CJMIS)
The (FMoJ) received an Unsolicited Proposal from ECR Technology Services Limited seeking to utilize the application of a Criminal Justice Management Information System that will enable an economically viable way of implementing the Criminal Justice Act (2015).
ICTAwaiting further correspondence on the project from the MOJ Development
100Federal Ministry of Industry, Trade & Investment (FMITI)Digital Industry Trade and Investment Platform (DITIP)ICTMeeting held with the Ministry on the 25th January, 2022 advising the Ministry on various options and their outcomes for the project.

Development

 

 

 

 

101National Communications Commission Deployment of a Centralized Device Management System (DMS)
The procurement of Device Management Solutions (DMS) to combat counterfeit and sub-standard ICT devises in Nigeria.
ICT / Communications

Engagement of TA is ongoing, involving:

A meeting was held with NCC and the proponent for the amendment of the scope of the project on the 7th of July 2022. The scope was adjusted to accommodate the monitoring of the activities within the digital economy.

RfP, technical and financial bid evaluation has been done. Awaiting evaluation report to be approved by the Project Steering Committee, bidder notification then posting of the preferred bidder guarantee and then negotiation can commence.

 

 

Procurement
102National Communications CommissionDeployment of a Revenue Assurance System (RAS)
The procurement of Revenue Assurance (RAS) to combat revenue leakages amounting to N1Trillion naira annually in the telecoms market generally.
ICT / Communications

NCC sent a letter on the 20th of May 2022 updating new financial partners for the project.

 

The Commission sent its opinion to NCC on the expansion of the scope on the 28th of August 2022.

 

An FBC Certificate of Compliance was issued to the expanded RAS/DSR project on December 8, 2022

 

Procurement
103National Space Research & Development Agency (NASRDA)

Research and Development of Satellite Technology and Equipment for the Provision of cost-effective satellite broadband to rural Nigeria.

 

ICT / Communications

Letter from the Office of the National

Security Adviser received on May 22, 2022.

Issuance of FBC CoC on the 27th of June 2022.

 

Project approved by FEC on November 30, 2022

Procurement
104National Space Research & Development Agency (NASRDA)Concession of Planetarium and Museum
The project seeks to equip, operate and maintain the Planetarium and Museum at the Obasanjo Space Centre Abuja.
ICT / Communications

Full Business Case Certificate of Compliance issued on July 25, 2022

 

Project approved by FEC on November 2 2022

Procurement

 

 

 

105Federal Ministry of Finance

Integrated Secure Track and Trace Solution

Designed to monitor goods and services subject to excise duties

ICT/Finance & revenueOutline Business Case Certificate issued on September 26, 2022Procurement
106Federal Ministry of Industry, Trade & InvestmentDevelopment of SME Portal
A technology enabled platform project that will encourage more MSMEs to be attracted into the formal sector.
The project is currently in Development Phase.
Industry, Trade and InvestmentFBC Certificate of Compliance was issued on the 26th April, 2019.
FEC has approved the FBC certificate.Next Step: contract Signing and custody of agreement

Procurement

 

 

 

 

 

107Federal Ministry of Industry, Trade and InvestmentDevelopment of Okerete Transnational Border Market at Saki West LGA, Oyo State
The Ministry intends to establish transnational border markets to promote regional integration, create employment in rural areas and reduce high incidence of smuggling across Nigeria’s borders. The intention is to create them at 6 geo-political zones of the country starting with Okerete, in South West region.
Industry, Trade and InvestmentIt was unanimously agreed at the Technical Committee meeting that the road leading to the site should be graded and tarred as well as include the construction of a bridge that will link Nigeria and the Republic of Benin.Development
108Federal Ministry of Industry, Trade & Investment and Niger StateBabanna Transnational Border & Regional Market Project
Integration of informal trade with the formal sector, Elimination of smuggling, Revenue generation, Enhancement of bilateral integration and trade, Enhancement of security along the border are all aspects of this Transnational border project.
Industry, Trade and InvestmentA Technical Committee meeting held on 23rd January, 2020 to chart a way forward for the project.
The meeting agreed to develop a TOR for the engagement of TA on the project.
Development
109Federal Ministry of Petroleum  Resources & NNPC

Rehabilitation of NNPC Pipelines Network and Storage Facilities Under a BOT Model

The project has been submitted by NNPC providing a Business Case for the BOT Model for the rehabilitation of the NNPC’s pipeline Network and Storage Facilities.

Petroleum/ Energy

OBC Certificate of Compliance issued on July 22, 2021

Virtual evaluation of bidders held between 25th July to 29th July 2022. Awaiting outcome of bidders and

reserve bidders

Procurement

 

 

 

 

 

 

 

 

 

110Nigerian Shippers’ CouncilDevelopment of Ibadan Inland Dry Port (IDP) under PPP Model
The NSC in facilitating trade and protection of cargo interest in all transport modes and its mandate as the economic port regulator is promoting the development of Ibadan Inland Dry Port (IIDP) in Ibadan, Oyo State under PPP arrangement. The NSC in partnership with Oyo State Government intend to enter into joint-venture PPP with a top tier private sector partner to establish an Inland Dry Port at Olorisaoko on the Iseyin-Ibadan road, Ibadan, Oyo State.
Port/ICD
Next steps:

• Conclusion and forwarding of FBC report to the Commission for issuance of compliance certificate.
• FEC approval
• Commercial Close
• Financial CloseNo communication since 2018
Procurement
111Federal Ministry of Transportation / Nigeria Shippers Council (NSC)The Dagbolu Inland Container Depot (ICD):
(Solicited Proposal) The project concerns the development of a Greenfield ICD in Osun State, South-West Nigeria. The ICD is being developed to exploit the strategic advantages in Nigeria's huge export and import market by making the country a trans-shipment hub for the West African region. The ICD when developed would provide storage and cargo handling facilities for export and import of containerized cargos to and from the hinterland of Nigeria especially around the Southwest states of Ondo, Ekiti, Osun; Edo State and Kwara State.
Ports Sector

The Commission reviewed the RFP and approved it for NSC to issue to the prequalified bidders.

Next step:

Advertisement in the print media for the selection of preferred concessionaire.

Procurement
112Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Inland Container Depot (ICD) in Lolo, Kebbi State:
(Unsolicited Proposal):
The Economic Reform Programme, approved the setting up of Lolo Inland Container Depots (ICD) to provide port services to shippers.
(OBC) received from the Nigeria Shippers Council (NSC) in respect of the unsolicited proposal developed by Deltatlantic Nigeria Ltd.
Ports Sector

The Commission re-issued an OBC Certificate November 8, 2017.

Negotiations have stalled with preferred bidder Deltatlantic Nigeria Limited despite repeated attempt to carryout due diligence on the land and the investor. This has delayed further progress on the project

Procurement
113Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Inland Container Depot (ICD) in Onitsha, Anambra State: This has a design that consists of an annual 5,000 TEUs capacity facility which can be expanded with increasing throughout.Ports SectorThe Commission issued an OBC Certificate November 8, 2017.
Next step:
Advertisement in the print media for the selection of preferred concessionaire.
Procurement
114Federal Ministry of Transportation / Akwa Ibom State GovernmentIbom Deep Sea Port Project
(Solicited Proposal): The Ibom Deep Sea Port (IDSP) project involves the development of a Greenfield Deepsea Port and accompanying Free Trade Zone (FTZ) in Akwa Ibom State in the South-South geopolitical zone of Nigeria. The proposed Port and FTZ are part of the proposed Ibom Industrial City initiative that will be established on a 14,400-hectare site donated by the Akwa Ibom State Government (AKSG) at no value. The IDSP project is intended to become a major national and regional economic gateway that will provide additional container handling capacity for the country. In addition to containers, the IDSP is expected to handle petroleum products (export and import), crude oil and natural gas (export), vehicles (import) and bulk trade in natural resources (import and export).
It is planned to be the deepest port in the West African sub-region.
Ports Sector

Preliminary negotiation meeting with the preferred bidder, (Bollore/Power China Consortium) was done on January 9th, 2020 in Lagos.

The Commission Revalidated the Full Business Compliance certificate to the FMoT/NPA on 12th Feb, 2020

After expiration of certificate, the Commission once again revalidated and re-issued FBC certificate on 17th September, 2020 with 6 months validity.

FEC approved the FBC on 16th December

Next Steps:
Commercial Close
Financial Close

Procurement
115Federal Ministry of Transportation (FMoT) / Nigeria Ports Authority (NPA)Kirikiri Port Lighter Terminal I & II
(Solicited Proposal): The Federal Government aims to procure concessionaires to rehabilitate and upgrade these terminals which were hitherto selected as fishing terminals.  The project development and procurement costs are being sponsored under International Development Association (IDA) Credit to the Federal Government of Nigeria for PPP support.
Ports Sector

The Financial bids for KLT II was opened and Tin Can Inland Container Terminal Limited (TICT) emerged as the preferred bidder.

Project Closeout & Negotiation with TICT for Kirikiri Lighter Terminals took place 11th – 14th June, 2018.

No correspondence on this project since 2018

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

116Federal Ministry of Transportation/ Nigerian Ports Authority The Development of Deep Sea Port in Badagry, Lagos
The project is a Greenfield development designed to cater for containers, dry bulk, liquids, Ro-Ro, oil & gas products, and also operate a free trade and local logistic zones.
Ports SectorProject approved by FEC on August 3, 2022 for 45 years concession periodProcurement
117Federal Ministry of Transportation/Cross River State Government (CRSG)The Development of the Bakassi Deep Sea Port
The Cross River State Government intends to develop a sea port at Bakassi under a PPP arrangement, in pursuance of which it sought the collaboration of the Federal Government of Nigeria in accordance with existing legal framework for port development in implementing the proposal.
Ports Sector

Outline Business Case Certificate of Compliance was granted for the project on 25th September,2019 to enable the project to proceed to procurement phase.

Bid opening of RfP took place on 17th June, 2022

Procurement
118Federal Ministry of Transportation / NPAPort Single Window
The project involves the introduction of electronic single window platform that can effectively coordinate all port related/cargo clearance activities capable of potentially transforming port operations to a seamless, paperless system by eliminating redundant procedures and duplications.
Ports SectorThe Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.
Next step:
Awaiting procurement of TA and preparation of OBC.
Development
119Federal Ministry of Transportation / NPANational Freight Intelligence and Transportation Hub (NAFITH)
The project involves an application of information and communications technology (ICT) in the management of transport problems. It seeks to leverage on new innovation to provide needed solutions to the teething transport problems in Apapa.
Ports Sector

The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.

Next step:
Awaiting procurement of TA and preparation of OBC

Development

 

 

 

 

 

 

 

120Federal Ministry of Transportation / NPAKoko Port Concession
FGN is seeking to grant a new Concession over the Koko Port in 2017. NPA is conducting hydrographic studies to determine the best way the channels leading to Koko port could be optimally utilized. The transaction for this general cargo port will consist of a 180 m quay and apron, and a transit shed.
A plan view of the Koko Terminal lease will consist of the following facilities:
A 175 m long quay and apron;
• Additional waterfront for future expansion;
• A five-bay transit shed;
• The port administrative buildings and entrance gate;
• Port support buildings including the fire station, security police building, the power station with backup generator, and the maintenance shops; and
• A disused warehouse and miscellaneous buildings behind the quay area, and all other lands and buildings inside the Koko Port perimeter.
Not included in this transaction are the jetty and other facilities or equipment currently used by Tower Petroleum for bulk liquid (bitumen) handling.
Ports Sector

The NPA is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
121Federal Ministry of Transportation / (NPA)Ikorodu Lighter Terminals
The port is dedicated to salvaging unclaimed or overtime containers in the ports, with a view to providing needed solutions to port congestions and pave way to smoothen the new concessionaire’s operations in the ports.
Ports Sector

The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
122Federal Ministry of Transportation / (NPA)Provision of Utilities to the Ports
The FGN is desirous in using PPP procurement method for the provision of utilities to the ports. These include, but are not limited to the provisions of power and water.
Ports Sector

The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
123Federal Ministry of Transportation / (NIMASA)

PPP Projects:

i. Ship building yard with breaking, recycling technology and wreck identification and removal.
ii. Management and operations of the modular/floating dry dock (outsourcing).
iii. Procurement of operational vessels, maritime patrol aircraft, coordination/surveillance centre and other operational equipment (Finance lease)
iv. Outsourcing of NIMASA’s Training Centre and Guest House at Nigerian Maritime Resource Development Centre (NMRDC), Kirikiri, Lagos state.
v. PPPs to develop a Multilevel car park at NIMASA Headquarters
vi. Unsolicited proposal for Development of platform for pollution
Verification Gross Mass Imo Solar- safety of life at sea

Ports Sector

The Ministry is in the process of procuring a Transaction Advisers to prepare an Outline Business Case to determine the project’s viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
124Federal Ministry of Transportation (FMoT)/ National Inland Waterways Authority (NIWA)PPPs for the following facilities:
i. Warri Dockyard
ii. Lokoja Dockyard
iii. Concession of Abam Ama Jetty at Port Harcourt
iv. Buoyage Vessels (B/V Anam at Onitsha)
v. Buoyage Vessels (B/V Bajibo at Lokoja, Kogi State)
vi. Buoyage Vessels (B/V Nembe at Lokoja, Kogi State)
vii. Buoyage Vessels (B/V Numan at Lokoja, Kogi State)
viii. Motor Ferry (M/F Calabar at Lokoja, Kogi State)
ix. Motor Ferry (M/F Effiat Mbo at Lokoja, Kogi State)
x. Motor Ferry (M/F Donga at Makurdi, Benue State)
xi. Water Bus (W/B) at Yauri, Kebbi State
xii. 3 Nos. 40-45 Passenger Sitter Ferries at Lokoja, Kogi State
xiii. Water Hyacinth Clearing Equipment (Water Master Classic III at Onitsha)
xiv. 2 Nos. 40-45 Passenger Sitter Ferries at Lagos
xv. Marina Jetty at Lagos
xvi. Apapa Jetty at Lagos
xvii. Oyingbo Jetty at Lagos
xviii. Maraoko Jetty at Lagos
xix. Abayomi Drive Jetty at Lagos
xx. Osborne Jetty at Lagos
Calabar Jetty at Calabar
Ports Sector

The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare an Outline Business Case to determine the projects’ viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
125Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Inland Container Depot (ICD) in Benin, Edo State
The Benin Dry Port is proposed to provide a one stop cargo reception and clearance facility to boost exports from and imports into Edo State particularly and Nigeria’s South-South, South East and some States in the Middle Belt regions in general. It is expected to provide proper handling and logistics services which emphasize promptness, dependability and cost effectiveness.
Ports SectorAccording to the NSC, there is need to conduct Gap-Analysis with a view of advising the proponent on the steps to be taken before declaring the project as port of Origin and port of Destination.Development
126Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Vehicle Transit Area (VTA) in Obollo-Afor, Enugu State
The NSC proposes to facilitate the development of VTAs through PPP with facilities for short-term breaks as well as long-term parking services where truck drivers can get fuel, food, restrooms, showers and basic supplies like oil and spare parts as well as servicing and repairs of haulage vehicles. The VTAs will have the following facilities including but not limited Gas Station, Hotel and Motel, Restaurants, Mechanic Workshop, Fire Station, Police Post, Automated Cargo Tracking System.
Ports Sector

The Commission revalidated the OBC 15th February, 2021.

Next Step: Process leading to the selection of concessionaire.

Procurement
127Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Vehicle Transit Area (VTA) in Lokoja, Kogi State
The NSC proposes to facilitate the development of VTAs through PPP with facilities for short-term breaks and also long-term parking services where truck drivers can get fuel, food, restrooms, showers and basic supplies like oil and spare parts as well as servicing and repairs of haulage vehicles. The VTA will have the following facilities including but not limited to Gas Station, Hotel and Motel, Restaurants, Mechanic Workshop, Fire Station, Police Post, Automated Cargo Tracking System.
Ports Sector

Halcrow Infrastructure Consortium appointed as Transaction Adviser.

OBC Certificate of Compliance was issued for the proposed project on 24th October, 2018.

Next Step:
Commencement of procurement process for the selection of concessionaire.
The Commission after review of updated OBC report revalidated the OBC 24th June, 2021.

Procurement
128

Federal Ministry of Transport/Nigerian Ports Authority

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The Rehabilitation and Expansion of the Burutu Port
Burutu Port is located in Burutu Local Government Area of Delta State. The current Port is on a 40.716 Hectares of Land and was originally built as a logistic Port for the export of Solid minerals and Agricultural Produce as well as importation and transportation of foreign goods from Europe for onward movement to the hinterland River Ports via the inland waterway.
Ports Sector

The Commission revalidated the updated

OBC on 1st February, 2021

 

Site visit to the Burutu port project took

place 28th-30th July, 2021

Next step:

Taking the project through Modified Swiss

Challenge Process

Procurement
129Federal Ministry of Transportation (FMoT)Development of Bonny Deep Water Port
The FGN intends to develop the Bonny Deep Water Port through PPP arrangements in order to improve transportation opportunities and boost economic activities along south-south, south east, north central and north east geo-political economic corridors and ease pressure on the western ports – Apapa and Tin Can Island which at the moment handles about 90% of cargo throughput in the country.
Ports Sector

The Commission granted the OBC Compliance Certificate on 22nd June, 2020; and granted the FBC Compliance Certificate on 24th August, 2020

FEC approved by the FBC on 7th October, 2020

Next Step:
• Commercial Close
• Financial Close

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

130Federal Ministry of Transportation (FMoT)/ National Inland Waterways Authority (NIWA)Re-development of NIWA Marina Land, Lagos State
The project involves the re-development of a narrow strip land measuring 3.9 hectares with plans to reclaim 39.2 hectares to a total of 41.1 hectares in Marina, Lagos; both the land and water areas are under the jurisdiction of the National Inland Waterways Authority (NIWA). The facility is currently being used for berthing and docking of passengers’ boats and other vessel services referred to as “marina land”.
Ports Sector

The Commission reviewed and granted the OBC Compliance Certificate to the Honourable Minster of Transportation on 29th December, 2020.

Next Step:
Commencement of procurement process for the selection of concessionaire.

Procurement
131

Federal Ministry of Transportation / (NIMASA)

 

 

 

 

 

 

 

 

 

 

 

 

Management Contract to Operate, Maintain and Transfer (OMT) of NIMASA Floating Dry Dock, Lagos

The concessionaire is to seek a management contract for the Management and Operations of the Modular/Floating Dry Dock to assist to put in place a Project Management Company for the Outsourcing of the operation and management of its Floating Dry Dock (FDD) through a competitive bidding process as technical partners on a commercial basis.

The NIMASA Modular Dry-Dock for the dry-docking of all possible vessels, including tugs supply vessels, fishing vessels and normal vessels has the following dimensions:

• Length over all – 110 m.
• Beam: 30.2m external.
• Depth: 12m
• Vessels draught docking capacity: 6m.
• Dry-dock lifting capacity: 5000 ton

 

 

Ports Sector

The Commission issued NIMASA an Outline Business Case Compliance Certificate on 3rd March, 2021 and therefore advice that the project proceeds to procurement phase that would lead to emergence of a preferred operator.

 

A contract negotiation meeting between NIMASA and Jmarine Logistics, the preferred bidders for the NIMASA Floating Dry Dock, Lagos, was held on Thursday, February, 25th 2022.

 

The Commission issued a Full Business Case (FBC) Compliance Certificate on 25th April, 2020 after detailed review of the FBC report submitted.

Full Business Case Certificate Revalidated on March 3, 2021.

FBC revalidated on December 15, 2022

Project Approved by FEC on December 21, 2022

 

Procurement
132Federal Ministry of Transportation / (NIMASA)

Eastern Offshore Waste Reception Facility (EOWREF) Concession under a Design, Finance, Build, Operate, Maintain and Transfer (DFBOMT) PPP arrangement.

 

In line with NIMASA’s vision, the Agency attempted to address the issue of setting up Offshore Reception Facilities between 2007 and 2012 but was unsuccessful due to the absence of regulations to back any proposals for the establishment of the facilities. Irrespective of the introduction of these new regulations, NIMASA has not been able to actualize its obligations of MARPOL 73/78 due to economic and budgetary challenges, hence the agency’s effort in sourcing the PPP procurement option. There’s currently no established OWRF to meet the needs of ships visiting offshore terminals.

Ports

OBC Certificate of Compliance was issued for the proposed project on 3rd September, 2021.

 

Due diligence was conducted on Frigate Upstream & Energy Services Ltd, the technical partner to XPO Marine Service LTD, the preferred proponent for the Eastern Offshore Waste Reception Facility on 12th and 13th January, 2022.

Full Business Case (FBC) was issued on Eastern Offshore Waste Reception Facility (EOWRF) on 22nd February, 2022.

Certificate Revalidated on December 12, 2022

 

Project Approved by FEC on December 21, 2022

 

Procurement
133Federal Ministry of Transportation / (NIMASA)

Central and Western Offshore Waste Reception Facility (CWOWREF) Concession under a Design, Finance, Build, Operate, Maintain and Transfer (DFBOMT) PPP arrangement.

 

Ports

Full Business Case (FBC) was issued on Central and Western Offshore Waste Reception Facility (CWOWRF), on 22nd February, 2022.

 

FBC Certificate revalidated on December 12, 2022

Project Approved by FEC on December 21, 2022

 

Procurement
134

Federal Ministry of Transportation / NPA

 

 

 

APAPA PORTS COMPLEX, LAGOS

The project entails the complete refurbishment and operation of the water system at the Apapa Port to ensure adequate water supply to vessels. NPA intends to increase the capacity of the water treatment plant from 50 to 100 cubic meter per hour.

Ports

OBC Certificate issued on 17th May, 2022 for the project to proceed to procurement phase subject to a Swiss Challenge.

 

Next step:

Procurement of Concessionaire

Procurement
135

Federal Ministry of Transportation / NPA)

 

TIN CAN ISLAND PORT LAGOS

Tin Can Island Port is located north-west of Apapa Port Complex, Lagos and it is the second busiest port in Nigeria. The port handles diversified cargoes with each terminal operator specializing in different forms of cargo (Dry and Wet bulk cargoes, Box-Containerized cargoes, RORO services). The port handles vessels ranging from 100m – 260m can handle ships of about 30,000 tonnes.

 

Ports

The Commission issued Nigerian Ports Authority (NPA) an OBC Certificate on 17th May, 2022 for the project to proceed to concessionaire procurement phase subject to a Swiss Challenge

 

Next step:

Procurement of Concessionaire

Procurement
136Federal Ministry of Transportation / Nigeria Shippers Council (NSC)

Concession of Tincan Island Truck Transit Park, Lagos State

 

The Federal Ministry of Work and Housing (FMoW&H) is desirous in engaging private sector investors for the concession of a Truck Transit Park in Apapa Tincan Island under a Public Private Partnership (PPP) arrangement.

Transport /Urban Development

OBC Certificate of Compliance was issued for the proposed project on 21st January, 2022

Next step:

PPP procurement stages of RFQ and RFP

Procurement
137Federal Ministry of Education/University of AbujaDevelopment of Trailer Park on BOT with Gwagwalada Area CouncilTransport/Urban development

Declined issuance of OBC Certificate of Compliance due to non-compliance on the 16th of June 2022

 

Development
138Federal Ministry of Transportation/ Nigerian Railway Corporation (NRC)Greenfield Railway Lines across Nigeria
• Lagos – Shagamu- Ijebu Ode- Ore- Benin City (300km) (standard gauge).
• Benin- Agbor-Ogwashi Uku- Asaba- Onitsha –Nnewi- Owerri-Aba with additional line from Onitsha-Enugu- Abakaliki (500km) (standard gauge).
• Ajaokuta(Eganyi)-Obajana-Jakura-Baro-Abuja with additional line from Ajaokuta- Otukpo(533km) (standard gauge)
• Zaria- Funtua- Tsafe- Gusau- Kaura- Namoda-Sokoto-Illela-Birnin Koni (520Km) (standard gauge).
• Lagos –Ibadan- Oshogbo-Baro-Abuja (615KM) (high speed).
Rail

The OBCs on these projects are being awaited.

Next step:
Awaiting procurement of TA and preparation of OBC.

Development

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

139Federal Ministry of TransportationProvision Of Enterprise Resource Planning (ERP) Solution for the Council for Regulation of Freight Forwarding in Nigeria (CRFFN)
The Council for the Regulation of Freight Forwarding in Nigeria Act No. 16 of 2007 was enacted into law on April 30, 2007. The Council is charged with, amongst other responsibilities, regulating and controlling the practice of Freight Forwarding in Nigeria, and promoting the highest standards of competence, practice and conduct among members of the profession.
Rail

Full Business Case submitted by CRFFN, reviewed and certificate of compliance issued 12th February, 2019 for the Design, Build, Operate and Transfer (DBOT) of an Enterprise Resource Planning Solution under a PPP arrangement with Messrs SW Global (SWG) as the Preferred PPP partner based on their old service provision performance.

Next Step:

Submission of FBC to FEC for approval.

Procurement
140Federal Ministry of Transportation (FMoT)

Development of Railway Industrial Park in Port Harcourt

The FGN intends to develop a Railway Industrial Park in Ubima, Rivers State through PPP arrangements with the following facility components for commercial vehicles and rolling stock assembly, Oil and Gas materials supply Industrial Park, Textile Industrial Park, Light Industry Park for Fast Moving Commodities and Goods (FMCGs).

Rail

The Commission granted the OBC Compliance Certificate on 22nd June, 2020; and also granted the FBC Compliance Certificate on 24th August, 2020.

FEC approved the FBC on 7th October, 2020

Next Step:
• Commercial Close
• Financial Close

Procurement
141Federal Ministry of Transport/ Nigerian Railway Corporation

THE DEVELOPMENT OF ABUJA-BARO-ITAKPE-AJAOKUTA-WARRI RAILWAY LINE (269.12KM) WITH BRANCH LINE AND EXTENSIONS FROM JAKURA-LOKOJA (41KM) AND AGBARHO-WARRI (5KM) AND WARRI NEW SEAPORT

The 2-projects are:
i. Abuja-Baro-Itakpe-Ajaokuta-Warri Railway Line (269.12km) with branch and extension lines to Jakura-Lokoja (41km) and Agbarho-Warri (5km)

ii. Development of Warri new Seaport, Warri, Delta State

The preferred PPP project model is Design-Build-Operate and Transfer (DBOT) model where CRCC will recoup its investments through user-fees. The proposed projects were designed to promote passenger and freight services, promote regional infrastructure development, preserve the life span of roads, encourage inter-model transport system, job creation and promote economic recovery and growth plans of the Federal Government, etc.

Rail/ Port

Messrs. China Railway Construction Company International (CRCC(I)) was competitively procured to develop these projects under a PPP arrangement.

Process included joint due diligence on the CRCC(I) offices in China by ICRC, FMOT, Federal Ministry of Finance, Nigerian Railway Corporation to confirm technical and financial capabilities to undertake the Project.

ICRC issued FBC Compliance Certificate on 27th November, 2018.

FEC approval of FBC obtained 2018
Incorporation of Special Purpose Vehicle for the project commenced in October 2020.

Procurement
142

Federal Ministry of Transport/ Nigerian Railway Corporation

 

SECURE TICKETING SOLUTION FOR THE LAGOS – IBADAN STANDARD TRAIN SERVICE.

 

To effectively harness the benefit of the development taking place in the Nigeria railway by way of revenue generation, there is need to put in place a ticketing solution on the LAGOS – IBADAN STANDARD TRAIN SERVICE that will enable passengers to buy their tickets from their offices and homes without physically doing same at the train station. This will help NRC manage the demand for tickets using the PPP option under DESIGN, FINANCE, BUILD, OPERATE, MAINTAIN AND TRANSFER Model.

 

Rail

The Commission confirms that the submission is in substantial compliance with ICRC Act and issued FBC Certificate of Compliance for the proposed project on 12th April, 2022 to FMOT/NRC.

 

The Commission also certified the draft Concession Agreement (CA) reports forwarded to the Commission.

 

Next step:

Awaiting the approval of FBC by FEC.

 

 

Procurement
143

Federal Ministry of Transport/ Nigerian Railway Corporation

 

SECURE TICKETING SOLUTION FOR WARRI – ITAKPE TRAIN SERVICE

 

To effectively harness the benefit of the development taking place in the Nigeria railway by way of revenue generation, there is need to put in place a ticketing solution on the WARRI – ITAKPE TRAIN SERVICE that will enable passengers to buy their tickets from their offices and homes without physically doing same at the train station. This will help NRC manage the demand for tickets using the PPP option under DESIGN, FINANCE, BUILD, OPERATE, MAINTAIN AND TRANSFER Model.

 

Rail

The Commission confirms that the submission is in substantial compliance with ICRC Act and issued FBC Certificate of Compliance for the proposed project on 12th April, 2022 to FMOT/NRC.

 

The Commission also certified the draft Concession Agreement (CA) reports forwarded to the Commission.

 

 

Next step:

Awaiting the approval of FBC by FEC.

 

Procurement
144Federal Capital Territory Administration (FCTA), Abuja.ONEX through Mpape-Gurku-Ado/Gurku-Nyanya in the Federal Capital Territory (FCT), Abuja. FCTA
The project involves the construction, operation and maintenance of Dual Carriage way from Outer Northern Express Way (Murtala Mohammed Way) through Mpape to Gurku, through Ado/Gurku.  The project was designed to ease congestion on Nyanya road and its surrounding axis.
RoadThe project is at development phase involving procurement of Transaction Adviser and preparation of Outline Business Case.

Development

 

 

 

 

 

 

 

 

 

 

145Federal Ministry of Works & Housing (FMW&H)Concession of 10 roads under the Highway Development & Management Initiative (HDMI)
1. Asaba-Agbor (Delta/Edo States)
2. Abuja-Lokoja (FCT/Kogi)
3. Kano-Katsina (Kano/Katsina)
4. Onitsha-Aba (Ananbra/Abia)
5. Shagamu-Benin (Ogun/Edo)
6. Abuja-Akwanga (FCT/Nasarawa)
7a. Kano-Shuari [lot 1] (Kano State);
7b.       Potiskum-Damaturu [lot 2] (Yobe State)
8. Lokoja-Auchi (Kogi/Edo)
9. Enugu-Port Harcourt (Enugu/Rivers)
10. Ilorin-Jebba (Kwara/Niger)
11. Lagos-Abeokuta (Lagos/Ogun)
12. Lagos-Badagry (Lagos)These routes have been selected for the 1st phase of the VAC.The routes have been further broken down into lots. This is to ease management and development, ensuring that the entire route is adequately accounted for.

Certain criteria have been used to ensure that the most suitable 1st phase routes have been chosen.

Roads & Bridges

Twelve (12) OBC reports have been submitted by Federal Ministry of Works & Housing (Works) to the Commission for validation.

The Commission after review of the 12 OBC reports granted OBC compliance Certificate to all 12 reports on 21st December, 2020.

Presentation of OBC certificates to the Honorable Minister held 29th January, 2021 at the Ministry Conference room.

RFQ adverts for HDMI projects in print media on 29th March, 2021 with deadline of submission on 3rd May, 2021.

 

Evaluation of RfQ concluded and approval of report.

 

RfP was also issued and preferred bidders was announced by the Federal Government on 30th April, 2022.

 

Next Step:

Submission of FBC to the Commission for review and certification.

 

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

146Federal Ministry of Interior/Nigeria Immigration ServiceEstablishment of Nigerian Passport Application Support Centers in the US, Canada etc
(Solicited Proposal):

This project has been designed by the Nigeria Immigration Service (NIS) to alleviate the hardship, difficulties and inconvenience experienced by Nigerians living in USA, United Kingdom, Continental Europe, Asia and South America in their bid to procure or renew their international passports.
SecurityThe Nigeria Immigration Service vide a letter dated September 16, 2021 Ref: NIS/HQ/ACG-PPTS//208/16/II conveyed the directive of the Ministry of Interior and the decision to discontinue the processes leading up to the project.

Procurement

 

 

 

 

 

 

 

 

 

 

 

147Federal Ministry of Defence (FMoD)Concession of Defence Jetty, Marina Lagos
Messrs. Inspium Multi-Services Limited (IMSL) is proposing through a Build-Operate and Transfer (BOT) PPP model the rehabilitation and construction of the Ministry of Defence Jetty at Marina, Lagos.
Once Complete the following services will be available:
Ferry Service Parking, Helicopter Parking, Car Parking, Office Letting, Berthing Services, Afloat Repair Services, Warehousing Services, Restaurants & Café, Professional Training Services.
Security

The Commission issued an Outline Business Case Certificate November 8, 2017.

Full Business Case Certificate of Compliance was issued on 29th November, 2018.

Procurement
148Federal Ministry of Police AffairsContingent Owned Equipment (COE)
Supply Own and Operate (SOO) for Peace Keeping Missions in CAR, South Sudan, Somalia, Dafur and Liberia.
Security

Joint OBC/FBC Compliance Certificate issued for presentation to FEC.

Next step:

Submission of FBC to FEC for approval.

Procurement

 

 

 

 

 

 

 

 

 

 

149Nigerian Correctional Service (formerly Prisons)Concession of Nigerian Prisons Land Swap Correctional Facility, Industrial Laundry Facility & Integrated Farm Facility.Security

First phase of Negotiation with preferred bidders for both Land Swap Correctional Facility (Halcrow Infrastructure Consortium) and Integrated Farm Facility (Nestoti Consortium) projects took place on June 28, 2016.

Project stalled

Procurement
150Ministry of Defence (MOD)The Naval Ship Dockyard, Lagos
This involves optimizing the capacity and functioning of the Naval Dockyard to attend to the maintenance services of existing fleet and facilitate building of new naval and commercial vessels under a PPP arrangement.
SecurityThe Commission once again revalidated and re-issued the FBC certificate of compliance to MOD on 14th April, 2021.
Next Step:Submission of FBC to FEC for approval.
Procurement
151

Federal Ministry of Interior

 

 

 

 

 

 

 

 

 

 

Immigration and Border Line Management
The Ministry seeks to use PPP procurement to design and develop an Intelligent Border Management System to reinforce the Federal Government’s capability to enhance border management processes, by comprehensively overhauling the surveillance and monitoring of passengers arriving or departing through the country’s major entry points.
Security

The Commission has issued OBC Compliance Certification.

Next Step:
Awaiting commencement of procurement process by the Ministry.

Procurement
152Federal Ministry of InteriorDevelopment and Deployment of a National Security and Civil registration system:
This involves the developing and deploying an ICT-based system to collate and up-to-date demographic, migration, biometric and bio-data on segments of the nation’s civil population, primarily employed in informal sectors, most of whom are generally invisible, to improve intelligence information on civilian population, in line with the Ministry’s civil defense and internal security mandate.
Security

The Commission has reviewed the submitted OBC and has advised the Ministry accordingly.

The Commission is awaiting the submission of an updated OBC.

Development
153Federal Ministry of InteriorProduction of Emergency Passports
Federal Ministry of Interior seeks to commence the production of Emergency Passports on a Public Private Partnership (PPP) Arrangement.
SecurityAwaiting further correspondence from the Ministry on this projectProcurement
154

Federal Ministry of Defence

 

 

 

 

 

 

 

Supply, Operate & Maintain arrangement for equipment to Federal Ministry of Defence (FMoD)

Leasing to the UN under CoE system on a letter of assist basis.

 

 

 

 

 

 

 

 

 

 

 

Security

The Commission granted Conditional FBC Certificate of Compliance on 2nd September, 2019. Final FBC Certificate granted 5th December, 2019 on successful completion of the conditions.

Next Step:

Awaiting Presidential Approval.

Procurement
155Federal Ministry of Interior (FMoI)/ Nigerian Police Service (NPS)National Public Security Communication System (NPSCS)
The NPSCS project aims to provide of a robust, reliable, secure and independent multimedia communications system for the Police and other agencies. Using the latest broadband technologies both current and future network standards will be managed to deliver quadruple-play (4x) telecommunications services for improved capacity in crime prevention and investigation as well as a reduction in the need for physical manpower input in intelligence services and aid emergency services to respond more rapidly to urgencies.
Security

Bid conference held on Wed, 14th Aug, 2019 to select the Baseline Auditor for the NPSCS Network

Meeting of the subcommittee of the Network Baseline Audit of the NPSCS held on 20th  Aug, 2019
Presentation of report on the Network Baseline Audit of NPSCS to the Project Management Team (PMT) held on 29th Aug, 2019.

FEC Approval obtained Wednesday 16th December 2020

Next Step
Commercial close

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

156Nigerian Correctional Services (NCS)

The Resuscitation of the NCoS Farm Center, Ozalla, Edo State

The Nigerian Correctional Service is desirous of exploring PPP options for the development and operations of the farm centers debuting with the Federal Correctional Farm Centre, Ozalla, Edo State as a pilot scheme.

Security

The Commission issued NCS an Outline Business Case Compliance Certificate on 6th July, 2021 to enable the project proceed to private sector procurement stage through a Swiss Challenge approach.

Bid Opening and evaluation took place on May 9-16, 2022 via Swiss Challenge procurement process

Next Step:

Submission of Full Business Case (FBC) to the Commission for review and certification

Procurement
157Federal Ministry of Youth and SportsPPPs involving the following:
i. Upgrading/rebuilding of National Stadium, Lagos
ii. Completion of Athletes’ hostel, Abuja
SportsPDT meeting held on September19th, 2018.  The Ministry has been advised to submit an OBC to the Commission. RFQ bids evaluated on 25th November 2020
Evaluation Team to submit report to PDT on 2nd December 2020
PDT Meeting held on Wednesday, the 2nd of December, 2020
Development
158Federal Ministry of Youth and SportsDevelopment of Multipurpose Facility at National Stadium, Abuja
The Federal Ministry of Sports & Youth Development seeks to develop Multipurpose Facility at National Stadium Abuja through PPP
Sports

Meeting on a proposal for Long Lease of Part of the Public Parking Lot in the National Stadium, Abuja held at the Federal Ministry of Youth & Sports Development (FMYSD) on March 27, 2018.

RFQ Advert for the two projects published on the 31st August 2020.

RFQ advert extended by 2 weeks.

Development
159Federal Ministry of Youth and SportsSponsorship And Promotion of The National Sports Festival (NSF)SportsAttended the MOU signing ceremony for sponsorship, marketing and promotion of National Sports Festival on 11 Jul 2018.
Following request by the Ministry through letter on 6/09/18 for a waiver to allow Abuja National Stadium to bear the name 'GLO' for the next two years, the Commission replied requesting for the draft Agreement to be forwarded to it and Federal Ministry of Justice (FMoJ) for review before execution.
Development
160Federal Ministry of Youth and Sports

Athletes Hostel

The Federal Ministry of Youth and Sports Development seeks to Concession a) National Stadium Complex & Athletes’ Hostel Surulere, Lagos. B) Athletes’ hostel Abuja

SportsRFQ Advert for the two projects published on the 31st August 2020Procurement
161Federal Ministry of Industry, Trade and Investment/National Automotive CouncilDevelopment of World Class Training Centre of Excellence:
(Solicited Proposal): The National Automotive Design Development Council wishes to develop a World Class Training Centre of Excellence through a PPP.
Trade and InvestmentThe Commission held a meeting on 31st January, 2020 to establish a way forward on the project.
It was agreed an updated Business Case will be sent to the Commission for review on 9th March, 2020.
Procurement
162Federal Ministry of Industry, Trade & Investment / Tafawa Balewa Square Management Board (TBSMB)Rehabilitation, Management and Operation of the National Trade and International Business Centre, Lagos (NTIBC)
The development of the NTIBC was conceived against the background of the FGN’s desire to develop one-stop investment hubs in order to sustain economic growth by encouraging export, enterprise and investments. The Independence building was built in 1959. The building consists of 25 floors, has approximately 8,100 square meters and a separate parking lot directly opposite with an area of 2,650 square meters.
The proposed NTIBC building will be a mixed-use facility to cater for businesses on a let basis, provide space for TBSMB and also residential usage.
The proposed facility will be multi-functional, to include:
i. Office for agencies under the FMITI
ii. Offices for other government MDAs
iii. Information hub on trade & investment in Nigeria
iv. Office for Blue-Chip companies
v. Conference & meeting rooms
vi. Exhibition and banquet halls
Restaurants & lounge bar
Trade and Investment

Procurement report submitted to Minister of Industry, Trade and Investment and approval granted to proceed to Negotiations.

 

Awaiting negotiations

Procurement
163Federal Ministry of Industry, Trade & Investment / National Automotive Council (NAC)Establishment of the Mechanic’s Villages
The mechanics’ villages’ project is an initiative of NAC, a body established pursuant to the National Automotive Council Act, Cap N8, Laws of the Federation of Nigeria, with responsibility for the development of the automotive industry in Nigeria.
The objective for the establishment of the mechanic’s villages is, among other things, to stimulate the growth and development of the mechanic business in a specialized and orderly manner. The project is aimed at developing the automotive value chain via the provision of 6 pilot modern mechanic villages in the nation’s 6 geopolitical zones.
Trade and Investment

Meeting for review and negotiation of concession fees held on February 21st, 2019

Site Visit took place on February 27th, 2019

Awaiting Sensitivity analysis to be run by both parties and to be sent to the Commission for review

Development

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

164Federal Ministry of Industry, Trade & Investment / Small and Medium Enterprises Development Agency of Nigeria (SMEDAN)Development of 23 Industrial Development Clusters (IDCs)
The objective of the project is to redevelop 23 Industrial Development Centers (IDCs) into Industrial Clusters across Nigeria (in 6 geopolitical zones) using the PPP Model.
Trade and InvestmentOBC Certificate of Compliance was granted on October 23rd, 2018 for six (6) identified IDCs namely; Idu Abuja, Maiduguri, Owerri, Ikorodu, Port Harcourt and Sokoto.Procurement
165Federal Ministry of Industry, Trade & Investment Federal Ministry of Industry Trade and Investment Abuja Head office Building Project
The Federal Ministry of Industry Trade and Investment is desirous to build their Abuja Head Office through a PPP Procurement method. Project Conceptualization is currently on-going.
Trade and InvestmentProject Conceptualization is currently on-going.Development
166Federal Ministry of Industry, Trade & Investment

Proposed concession of Calabar and Kano Special Economic Zones (SEZs)

 

 

 

 

 

 

 

 

 

 

 

Trade and Investment

A letter dated 14th of October, 2021 acknowledging receipt of OBC was issued to the Ministry.

OBC Certificate of Compliance issued on 17th November 2021

Wrote a letter to the Honourable Minister, FMITI on the 20th of April 2022 regarding RFQ advertised by BPE.

Responded to a letter from BPE inviting the Commission for evaluation of RfQ. The letter was dated 23rd May, 2022.

Procurement
167Tiga Fish FarmDevelopment of the Tiga Fish FarmTrade and Investment

Outline Business Case issued on the 1st of August 2022.

Awaiting procurement.

Procurement

 

 

 

 

 

 

 

168Industrial Training Fund (ITF)Proposed development of Industrial Skills Training CentreTrade and InvestmentProject development ongoingDevelopment
169Federal Ministry of Industry, Trade & Investment (FMITI)

Concession of Calabar & Kano Free Trade Zones

 

Trade and Investment

BPE invited ICRC for RfQ evaluation on the 15th of June, 2022.

 

Development
170Federal Capital Territory/ Abuja Infrastructure Investment Center (AIIC)IGR Automated Platform for AEPB:
Project Description (Solicited Proposal): The MDA proposes providing an automated system for managing revenue collections, via an e-Payment platform that incorporates Mobile POS devices and a powerful AEPB office revenue administration and monitoring platform.
Urban Development

Evidence of competitive bidding process and all documentation and approvals during the process were sent by AIIC to the Commission on October 3, 2017

Next Step:

Awaiting FBC submission for review.

Procurement

 

 

 

 

 

 

 

 

 

 

171Federal Ministry of Works & Housing and Council for the Regulation of Engineering in Nigeria (COREN)COREN Head Office Project
(Solicited Proposal): The proposal will involve the Construction of COREN head office complex in Abuja using PPP procurement methodology.
Urban DevelopmentThe Commission granted an OBC Certificate of Compliance on November 8, 2016 for the project
COREN has been advised to proceed to procurement.
Procurement
172Federal Capital Development Authority (FCDA)Automated Parking Centres
This involves the construction of Automated Parking Centres in designated car parks in the FCT.
Urban DevelopmentFCDA is in the process of procuring a Transaction Adviser to prepare an Outline Business Case to determine project viability and bankability.Development
173Federal Housing Authority (FHA)PPPs involving the following:
i. Development of new towns in Abuja at Kwali and Bwari Area Councils
ii. PPP to develop corporate head office of Federal Housing Authority (FHA) in Abuja located at the Central Business District of Abuja.
Urban DevelopmentFHA is in the process of procuring Transaction Advisers to prepare an Outline Business Cases.
Projects will soon be advertised for procurement of Transaction Adviser.
Development
174Federal Housing Authority (FHA)Development of a 200-hectare land at Lugbe.Urban Development

The commission certified the Outline Business Case (OBC) and issued CoC on 25th July 2022. Achieved bid closing and evaluation. Awaiting evaluation report from the Ministry.

Ongoing procurement.

Bid closed on 29th September 2022 and was reviewed on 11th October 2022.  Awaiting RfP documents

Development
175Federal Ministry of Works & Housing Marina Quayside Strip Project
The proposed project is a transformative urban/waterfront development Project intended to be a tourism centre that will provide Commercial & Housing Complexes.
Urban Development

Outline Business Case Certificate of Compliance granted on August 16, 2017.

No further correspondence since OBC was issued in 2017

Procurement

 

 

 

 

 

176Federal Ministry of Works & Housing New Eko Development Project, (Lagoon City) in Lagos
The project proposal involves the Sand-filling and reclamation of water bodies within the vicinity of existing Banana Island Estate. The project would redefine the Banana Island landscape and complement the development of Lagos lagoon to reflect its mega-city status.
Urban DevelopmentThe OBC is currently a work in progress by the FMW&H.

Development

 

 

 

 

 

 

 

 

177Federal Capital TerritoryLight Rail Lot 2 PPP Project
The proposed Abuja Light Rail PPP project includes the financing, designing, construction, operation and maintenance of the rail transit network route. The covering distance is 54.1 kilometers from Garki Area 11 passing through the interchange centre at Eagle Square to Gudu and down to Nyanya, Karu axis, in Abuja. It also connects to sector Centre D through Hilton Hotel, Gwarimpa FHA Estate and the light railway Lot 1 (Blue line currently under construction)
Urban DevelopmentA meeting was held on December 22, 2017 at the SGF's office where the private proponent (IRMG) made another presentation on the way forward with the project. No conclusive agreements were reached, due to absence of some stakeholders.  The meeting was adjourned to a later date.
New date to be communicated to the Commission.
Development
178National Commission for Museums and MonumentsLease of Land at National Museum, Jos for the development of Filling Station
The National Commission for Museums and Monuments seeks to develop part of its land via PPP
Urban Development

The Commission reviewed the OBC and issued an OBC Certificate of Compliance on February 27th, 2018.

NCMM was asked to prepare a negotiation position paper and draft Concession Agreement and submit to the Commission.

Procurement
179National Commission for Museums and MonumentsDevelopment of Infrastructure in National Museum, EnuguUrban Development

The Commission reviewed the OBC and issued an OBC Certificate of Compliance on October 11th, 2022.

ICRC attended the inauguration of a Project Delivery Team and Project Steering Committee team held on the 18th of November, 2022.

 

Development

180National Sugar Development CouncilOperation and Management of Sugarcane Bio-Factory, Zaria
The Council is proposing a PPP procurement in the Management and Operation of the facility to make it more efficient and productive after sinking in so much money with little output.
Urban DevelopmentPDT met on March 23, 2018. ICRC has advised the Council of the need to procure a TA that will guide in the conduct of the Swiss Challenge procurement and also prepare a RFQ and RFP documents.

Development

 

 

 

 

 

 

181Centre for Management DevelopmentDevelopment of CMD Headquarters, Abuja
The Centre for Management Development is desirous of constructing National Headquarters in Abuja.
Urban DevelopmentProfile of two contractors sent to the commission by CMD. The Commission reminded through letter of March 27, 2018 to develop and submit Project Structuring Report.

Procurement

 

 

 

 

 

 

182Office of the Head of Civil Service of the Federation (OHCSF)The Concession of Ground Floor of the Federal Secretariat Complex, Phase II to Commercial Use under PPP Arrangement Modalities on how to commercialize the ground floor of the Office of the Head of Civil Service of the Federation (OHCSF) building complex as a PPP pilot project under PPP arrangement.
some of the possible services that can be considered in the proposed scheme:
- Creche/Nursery
- Supermarket
- Laundry
- Car Park commercialization
- Complementary Transportation to and fro across the various routes of the Federal Secretariat (Staff Bus)
Urban Development

ICRC issued Pilot Implementation Certificate on 10th July, 2019 to fast-track improved facility management via a pilot PPP arrangement.

Next step:
The head of Service is to obtain endorsement of the Federal Ministry of Justice and the approval of the president for the Implementation phase prior to signing the Pilot Concession Agreement.

Procurement
183Federal Housing Authority (FHA)Development of Federal Housing Authority (FHA) Shopping Complex, Gwarinpa, Abuja
FHA currently has a site office located on 2,500sqm along 3rd Avenue Gwarinpa. There is an existing bungalow housing the Annex office of the Federal Housing Authority on the land. The building will be demolished to give way for a modern shopping complex. The FHA Annex office will be relocated to a temporary location in Gwarinpa. On completion of the plaza, some of the offices will be retained for the FHA Annex.
Urban Development

OBC Certificate of Compliance was granted on June 12th, 2018

Bid opening held on July 11th, 2018 with two (2) proposals submitted for evaluation; which took place and none of the bidders met the requirements of the RfQ

Awaiting detailed report from FHA on the procurement process.

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

184National Assembly/ PASAN Staff HousingThe National Assembly’s commitment to acquire housing for their civil service staff under the steer of the Parliamentary Staff Association of Nigeria (PASAN)Urban DevelopmentMeeting held with NASS/ PASAN on 20th May, 2019 regarding reviewed PSR and way forward for project.
NASS/ PASAN have been advised to procure a TA to develop a standard PSR for the project.

Development

 

 

 

 

 

 

 

185Federal Radio Corporation of Nigeria (FRCN)FRCN Land Lease, Owerri, Imo State.
The Federal Radio Corporation of Nigeria is interested in constructing and developing mixed-use development on 14 Hectares of its 21.11 Hectare landed property at Km-15 Umuahia Road, Owerri, Imo State.
The project consists of a high-end luxury estate with recreational support facilities, luxurious hotel and office blocks for commercial purposes.
Urban Development

A due Diligence visit to the site was conducted June 30, 2022.

 

Full Business Case Certificate Issued on November 22, 2022

Procurement

186

 

 

 

Federal Radio Corporation of Nigeria (FRCN)Federal Radio Corporation of Nigeria Properties
The Radio Corporation is desirous to develop its 10-Hectares of land into a mixed-use facility in Lagos.
Urban Development

FBC certificate of Compliance revalidated on May 23, 2022

Messrs Kingslane and Fish Valley Ltd are preferred bidders on the project. Fish Valley has been issued a FBC CoC on May 23, 2022 for FEC approval.

Concession agreement for Kingslane still under review

 

FBC revalidated for Fishvalley on December 5, 2022

FEC approves 6 hectare project to Fishvalley Nig Ltd on December 21, 2022

 

Procurement

 

 

 

 

 

 

 

 

187Niger Delta Development Commission (NDDC)Proposed Niger Delta Broadband Development Initiative (NDBDI) for a Region-Wide High-Speed Next Generation Broadband Infrastructure.
Provision of Broadband Internet Access, and associated Services in the Niger Delta region. it will serve as a platform for the recommended SP to deliver the Broadband Internet Services to Subscribers at a reduced cost, using 4G technologies such as LTE (Long Term Evolution) and WAN (Wide Access Networks) to deliver speeds of over 100Mbps.
Urban DevelopmentOBC Certificate issued on January 10, 2019.Procurement
188National Hajj Commission of Nigeria (NAHCON)

Development of Shopping Complex

The NAHCON seek to engage a private sector operator to DFBOT a building at its landed property located at Hajj Complex, along Katsina Road, Kano State.

Urban DevelopmentFBC CoC issued on
November 22, 2021FEC approved Project on December 12, 2021Concession Agreement signed on the 7th of September, 2022
Procurement
189Federal Ministry of Works and Housing

Federal Site and Services Housing Scheme

AVU-Owerri Imo State

Urban DevelopmentOBC certificate issued on July 22, 2021. Procurement
190Federal Capital Territory / Abuja Infrastructure Investment Center (AIIC)Development of Jabi Lake Tourism & Recreation Development Project.
The development of the Jabi Lake area into a Tourism and Recreation hub.
Urban DevelopmentOBC Certificate of Compliance issued for the project on February 19, 2021.
In the process of engaging a TA to conduct a Swiss Challenge process.OBC Certificate re-issued on the 21th June, 2022.
Procurement
191

Federal Capital Territory (FCT)

 

Maximization of revenue from water bills in FCTUrban Development

OBC Certificate of Compliance issued for the project on 22nd April 2022.

Full Business Cases & Concession Agreements reviewed and FBC issued on the 27th October 2022.

 

Procurement
192Federal Capital Territory (FCT)

On street park as you pay in the FCT.

 

Urban Development

OBC Certificate of Compliance issued for the project on 23rd February, 2022

 

Review of the Full Business Cases & Concession Agreement from NAJEC and ATB ongoing

Full Business Cases & Concession Agreements from NAJEC and ATB reviewed and FBC certificate has been issued on 8th August 2022.

 

Procurement
193Federal Ministry of Education/University of Port-HarcourtStudent Hostel - An unsolicited proposal for the development of 4000- bedspace standard green building hostel facilityUrban DevelopmentA response letter was sent to UNIPORT declining the issuance of Certificate of Compliance dated 10th March, 2022Development
194The Nigeria Police ForceRedevelopment of the Nigerian Police DIG Quarters at Maitama District, Abuja, through Public Private Partnership arrangementUrban Development

Full Business Case Certificate issued on March 11, 2022 Preferred bidder – Cosgrove Nigeria Ltd

A site visit was conducted on March 29, 2022 as part of the due diligence.

Procurement
195Federal Ministry of Works & Housing

The Concession of Central Workshop, Ijora, Lagos Central Workshop, Ijora (CWI),

CWI was an appendage of the defunct Public Works Department (PWD).

Urban Development

OBC Certificate of Compliance was issued for the proposed project on 21st December, 2021.

 

Next step:

PPP procurement stages of RFQ and RFP.

Procurement

 

 

 

 

 

 

 

 

 

 

196The Nigeria Police Force (NPF)Development of senior police officers’ quarters at Ikeja, Lagos through PPP arrangement
The redevelopment of 6.750 hectare of land at Ikeja into senior police officer’s housing units using 2.1 hectares of the land and use of 4.65 hectares for the development of 130 four-bedroom duplex housing units.
Urban DevelopmentFull Business Case Certificate of Compliance was issued on July 26, 2022Procurement
197The Nigeria Police Force (NPF)Redevelopment of Police Barracks in Falomo, Ikoyi; and Ijeh, Obalende Lagos. This involves the demolition and redesign of the two barracks and the relocation of the POWA shopping complex in Falomo.Urban Development

RfQ evaluation Completed on September 20, 2022

Next Steps:

Submission of evaluation report following RfQ

Procurement

 

 

 

 

 

 

 

 

 

198The Nigeria Police Force (NPF)The Development of the Police Conference and Four-Star Hotel at Guzape District Abuja through PPP. The proposed project involves the demolition of the structures currently standing on SARS headquarters and a comprehensive re-development of the 15.5 hectares belonging to the Police.Urban development

OBC Certificate of Compliance issued on March 16, 2022

 

A site visit was conducted on March 29, 2022 as part of the due diligence.

Awaiting documents for regularization from the NPF

Procurement
199National Hajj Commission of Nigeria (NAHCON)Commercial Development of Residential Houses through PPPUrban development

Site visit to Lagos held between the 26th and 29th April, 2022.

OBC Certificate of Compliance issued on September 22, 2022

Development
200Federal Ministry of Education/University of Nigeria NsukkaConstruction of students’ hostel on BOT ModelUrban developmentDeclined issuance of OBC Compliance on the 24th of May, 2022Development
201Federal Ministry of Education/Ahmadu Bello University Zaria

Development of Shopping Complex and Luxury Apartments at GRA Zaria through a PPP arrangement

The University proposes to develop infrastructure through PPP

Urban developmentOBC Certificate of Compliance issued on September 22, 2022Procurement
202Federal Ministry of Education/University of BeninDevelopment of Shopping Mall in the University CampusUrban development

OBC Certificate of Compliance issued on September 16, 2022.

Letter sent out detailing the process of engaging a TA, to conduct a Swiss Challenge process

Development
203University of Maiduguri Teaching hospitalProposed development of Liaison officeUrban developmentThe Commission wrote to the University via a letter dated 27th July, 2022Development

 

INFRASTRUCTURE CONCESSION REGULATORY COMMISSION

 

PRE-CONTRACT PROJECTS (AT DEVELOPMENT AND PROCUREMENT) STATUS REPORT, AS AT DECEMBER 31, 2022

(IN SECTOR FORMAT)

 

S/N

 

MDA

 

PROJECT / DESCRIPTION

 

SECTOR

 

STATUS

 

PHASE

1

Federal Ministry of Agriculture and Rural Development

 

Deployment of 2,000 units of tractors and other mechanized equipment to Federal Ministry of Agriculture and Rural Development through SMART total mechanization package.AgricultureOn April 16, 2018 representatives of FMARD and Nigeria Agriculture Mechanization and Equipment Leasing Limited (NAMEL) made a presentation to the Commission on the proposed PPP arrangement titled ‘Solutions for Sustainable Food Production’.Development
2Federal Ministry of Agriculture and Rural Development

Projects, involving PPPs on:

i.      Federal Coastal Fishery Terminal, Ebughu, Akwa Ibom State

ii.     Federal Coastal Fishery Terminal, Borokiri Rivers State

iii.   Fish Processing Centre, Jebba, Kwara State

iv.   Agro Aviation Hangar, Kaduna

 

AgricultureFederal Executive Council approved the project on February 16, 2022 for a concession period of 11 yearsProcurement
3Federal Ministry of Education/University of AbujaDevelopment of Commercial Farm

Agriculture/

Education

Declined issuance of OBC Certificate of Compliance due to non-compliance on the 16th of June 2022

Development

 

 

 

 

 

4National Veterinary Research Institute/
Federal Ministry of Health
 
Vaccine Production Facility
National Veterinary Research Institute (NVRI) is desirous to commercialize vaccine production within the institute. 

Agri-Health

 

The Commission advised NVRI on the composition of the Project Steering Committee (PSC).Development
5

Federal Ministry of Aviation

 

Concession of Mallam Aminu Kano International Airport, Kano
The FGN proposed to concession the Mallam Aminu Kano International Airport Terminal Building, Kano State as part of aviation sector reform programme 
Aviation

The Commission participated on the bidder’s conference held in Abuja on 20th June, 2022 and also the site visit with the pre-qualified bidder on 21st June, 2022

 

Next step:

Submissions of RfP by the pre-qualified bidders

 

Procurement
6

Federal Ministry of Aviation

 

Concession of Port Harcourt International Airport
The FGN proposed to concession the Port Harcourt International Airport Terminal Building, Rivers State as part of aviation sector reform programme 
Aviation

The Commission participated on the bidder’s conference held in Abuja on 20th June, 2022 and also the site visit with the pre-qualified bidder on 22nd June, 2022

Next step:

Submissions of RfP by the pre-qualified bidders

 

Procurement
7

Federal Ministry of Aviation

 

Concession of Murtala Muhammed International Airport, Lagos
The FGN proposed to concession the Murtala Muhammed International Airport Terminal Building, Lagos State as part of aviation sector reform programme 
Aviation

The Commission participated on the bidder’s conference held in Abuja on 20th June, 2022 and also the site visit with the pre-qualified bidder on 23rd June, 2022

Next step:

Submissions of RfP by the pre-qualified bidders

 

Procurement

 

 

 

 

 

 

8

Federal Ministry of Aviation

 

Concession of Nnamdi Azikiwe International Airport, Abuja
The FGN proposed to concession the Nnamdi Azikiwe International Airport Terminal as part of aviation sector reform programme 

 

Aviation

The Commission participated on the bidder’s conference and the site visit with the pre-qualified bidder, held in Abuja on 20th June, 2022

Next step:

Submissions of RfP by the pre-qualified bidders

 

Procurement
9

Federal Ministry of Aviation

 

Development of a Maintenance, Repairs and Overhaul (MRO) Facility
The FGN intends to establish an MRO facility for aircraft maintenance, inspections and supply of parts to the aviation sector 

Aviation

 

 

Catamaran Consortium was procured as Transaction Advisers (TAs).

OBC Compliance Certificate issued 21st May, 2018.

FBC Certificate of Compliance issued on August 18, 2022

 

Project approved by FEC on October 12, 2022

Procurement
10

Federal Ministry of Aviation

 

Establishment of an Aviation Leasing Company (ALC)
The FGN intends to establish an ALC for the leasing of aircrafts to operators in the country and the continent as none exist in Africa at the moment.
Aviation

Awaiting report of the evaluation process with selection of the preferred bidder from the Ministry

Draft Contract Agreement for the project was sent to the Commission on June 21, 2021

 

FBC Certificate of Compliance issued on August 18, 2022

Procurement

 

 

 

 

 

 

 

 

 

 

11

Federal Ministry of Aviation

 

Development of an Aerotropolis (Airport City)
The FGN intends to develop an Aerotropolis in a suitable location to be determined by the TA. This entails the setting up and development of structures that will support the activities around the airport and aviation in general. 
Aviation

OBC Compliance Certificate issued 1st March, 2022.

 

Next step:

Investor procurement and Negotiation stages.

Procurement
12

Federal Ministry of Aviation

 

Development of a 6 Cargo/Agro Airports in the Geo-Political zones
The FGN intends to develop 6 Cargo/Agro airports in each of the geo-political zones to provide cargo handling and specialized logistics for agro products. 
Aviation

OBC Compliance Certificate to FMoA on 1st June, 2022 and RFQ has been advertised for prospective investors

 

Next step: Investor procurement and Negotiation stages.

Procurement
13Federal Ministry of AviationEstablishment of a National Carrier
The FGN intends to establish a National Carrier for the country through a PPP arrangement. The national carrier will have a hub in a designated airport as one of the outcomes of the assignment from the TA.
AviationEthiopian Air Consortium has emerged the preferred bidder of the National CarrierProcurement
14Nigeria police ForceConcession of Nigerian Police Air Wing aircrafts and facilitiesAviation

RfQ evaluation Completed on September 20, 2022

Next Steps:

Submission of evaluation report following RfQ

Procurement
15National Commission for Museums & Monuments/ Federal Ministry of Information & CultureDevelopment of Recreational Park within the Museum premises, Enugu.
(Unsolicited Proposal): An unsolicited proposal submitted to the National Commission for Museums & Monuments to develop recreational park in Enugu, within the Museum premises.
CultureNo correspondence from the Ministry on this since 2017. Awaiting formal correspondence on the way forward from  NCFMM & MoI&C.

Development

 

 

 

 

 

 

 

16Federal Ministry of Information and CultureNational Theatre
(Solicited Proposal)
: The project involves the development of 65 hectares of the 134 hectares fallow land around the National Theatre by building 5-star hotel, office buildings, leisure Park, shopping mall and Multi Level car park.
Culture

Full Business Case (FBC) Certificate of Compliance revalidation has been granted by ICRC.

Ministry is to submit FBC for approval by FEC

Procurement
17Federal Ministry of Information and CultureDevelopment of National Council for Arts and Culture’s land through PPP
The Council is desirous of developing an edifice on its parcel of Land located at Central Business District, Abuja through PPP that will comprise the following:
i.  Culture and Arts Theatre
ii. Office Development for use by
NCAC
iii. Conference and event exhibition hall,
Shopping Mall
CultureThe Ministry is required to engage a Transaction Adviser to prepare an Outline Business Case to determine project viability and bankability.Development
18Federal Ministry of EducationPPPs involving the following:
i. Upgrade of the ICT Laboratories/Business Centers in Federal Schools
ii. Upgrade of existing libraries
Upgrade of vocational schools
EducationThe Ministry is in the process of procuring Transaction Advisers to prepare Outline Business Cases to determine the projects’ viability and bankability.Development
19Federal Ministry of EducationNational Mathematical Center
i. Development of an International Conference Center
Construction of National Mathematical Centre-International Science Academy (NMC-IMSA)
EducationThe Ministry is in the process of procuring Transaction Advisers to prepare Outline Business Cases to determine the projects’ viability and bankability.Development
20Federal Ministry of Education / Federal University Gusau (FUG) PPPs involving the following:
i. Proposed construction of Students Hostel, 500-Units of Staff Housing, Roads & Drainages, Shopping Mall, Staff/Students Cafeteria, Bio-gas Electricity Power plant and Poultry Farm
ii. On-line application System for e-registration platform, Computation / compilation of Students’ results, e-Learning and web portal development.
Proposed construction of Vice Chancellor’s Lodge, Pro-Chancellor’s Lodge, Principal Officers’ Quarters, Senior Staff Housing, Junior Staff Housing, External Electrification, Borehole & Overhead Tanks, etc
EducationThe University is in the process of procuring Transaction Advisers to prepare an Outline Business Cases to determine the projects’ viability and bankability
ICRC reviewed the submitted documents in line with statutory processes. University written to supply additional information on the project and also confirm availability of land space for the entire project. 
Development
21Federal Ministry of EducationComputer Based Test Centre (National Business and Technical Examinations Board)
The Computer Based Test (CBT) Centre project is to enhance efficiencies of candidates in Technical and Vocational Education through Information and Computer Technology.
EducationThe Project is currently functional but the NABTEB has been asked by the Commission to forward relevant documents on the project to the Commission.
The Business Case and Executed Contract Agreement were reviewed and it was found that it did not satisfy the key features of PPP contracts. The Commission requested additional documents to incorporate the issues raised.The Board has been advised to submit a Joint OBC/FBC for review.
Procurement
22Federal Ministry of EducationDevelopment of Commercial Hub at National Open University of Nigeria (NOUN)
The National Open University of Nigeria is desirous of building a commercial hub for the University Community within the campus at Jabi, Abuja using the PPP arrangement.  The complex will have the following facilities Banking malls, Supermarket, Restaurants, Bookstore, retail shops etc
EducationICRC issued an OBC Certificate of Compliance on the October 7, 2017Procurement
23Federal Ministry of Education/ University of AbujaDevelopment of Students Hostel at University of Abuja
The University intends to build hostels for its teeming students as well as staff housing estate using PPP
EducationOBC certificate of Compliance was granted on 23rd September, 2020.
Letter nominating PSC and PDT members was sent to UNIABUJA on 20/11/2020.
Procurement
24Upgrade and concession of hostel at Public Service Institute of NigeriaUpgrade and Concession of Properties through PPP methodology
Public Service Institute of Nigeria is desirous of using PPP procurement methodology to upgrade and concession to private party its 108 rooms female hostel and 27 rooms guest chalet.
EducationThe project is currently in development phase. The Institute is working with consultants to prepare an Outline Business Case to determine project viability and bankability.Development
25Federal Ministry of Health/UCH, IbadanDevelopment of Shopping Mall, University College Hospital (UCH), Ibadan
UCH seeks to develop a Shopping Mall through PPP Procurement.
Education

Sensitization workshop and Inaugural PDT meeting held on October 17 & 19, 2017 at the Hospital premises.

Arrangements are in place to regularize the existing MoU with the Concessionaire. A meeting took place at Federal Ministry of Health in October 2020.

Development
26Federal University, Wukari/Federal Ministry of EducationDevelopment of hostel facilities and accommodation for Staff and StudentsEducationThe submitted project proposal document has been reviewed and the University was advised to prepare an OBC.
Awaiting the University’s response.
Development
27Federal Ministry of Education / Federal College of Education, Ogun StateDevelopment of Student Hostels at Federal College of Education Abeokuta, Ogun State
Federal College of Education Abeokuta seeks guidance to develop hostel accommodation using PPP procurement process.
EducationNo correspondence from the Ministry on this since 2019. Awaiting formal correspondence on the way forward from Federal Ministry of Education / Federal College of Education, Ogun State.Development
28Federal Ministry of PowerEnergizing Education Program
Electrification Program of Tertiary Institutions initiated by the FMPW&H to develop off-grid power plant projects in order to provide uninterrupted and dedicated power supply to forty (40) Federal Universities and neighboring University Teaching Hospitals across the Federation.
EducationThe FMPW&H is to prepare a structuring report and submit to ICRC.Development
29University of Calabar/ Federal Ministry of Education400 Room Students Hostel
The project consists of two hostels that will comprise 400 rooms on a 1.9 Hectares land within the University of Calabar premises and is estimated to cost N1,326,000,000 with a completion period of 9 months
EducationUNICAL has been advised to repackage the project to meet requirements of N4P and ICRC Act.Development
30Federal Ministry of Education/ National Commission for Colleges of Education (NCCE)Development of Hostel Accommodation for Colleges of Education
The Ministry received an unsolicited proposal by Adonai Ventures Ltd to build hostel accommodation for Colleges of Education in Nigeria.
EducationNo correspondence from the Ministry on this since 2019. Awaiting formal correspondence on the way forward from Federal Ministry of Education / NCCEDevelopment

31

 

 

 

 

Federal Ministry of Education/University of Port-Harcourt

 

Regularization of Build Operate and Transfer Process for the development of Retail and Entertainment Centre
The University of Port-Harcourt seeks to regularize an ongoing PPP Project to conform with National PPP Laws  
Education

ICRC reviewed a signed agreement with regards to the project with the aim of regularizing and legalizing the PPP process that was started by the University, but which had not gone through ICRC, to conform with the ICRC Act.

Inaugurated the PSC and PDT as well as due diligence visit to UNIPORT from 26th- 28th Jan 2022.

Procurement
32Federal Ministry of Education/University of Port-HarcourtDevelopment and Construction of Private Students’ Hostel Accommodation For University Of Port-HarcourtEducationThe Commission has reviewed the submitted OBC and has advised the University accordingly.

Development

 

 

 

 

 

33Federal Ministry of Education/University of Port-HarcourtRegularization of Build Operate and Transfer Process for the development of Entertainment Centre
The University of Port-Harcourt seeks to regularize an ongoing PPP Project to conform with National PPP Laws
Education

The review of the Project Structuring report is ongoing.

A letter highlighting the discussions and next steps during the project site assessment and monitoring visit at the UNIPORT was sent to the university on the 30th of March, 2022

Development
34Federal Ministry of Education/Federal University of Petroleum Resources, EffurunEstablishment of a Bespoke food Court on Design, Finance, Build, Operate and Transfer (DFBOT) Scheme.Education

OBC Compliance Certificate issued on the 30th of September, 2021.

PDT & PSC inaugurated on 21st April 2022

Procurement
35Federal Ministry of Education/University of Port Harcourt

PPP Projects:

The University seeks to develop and construct 110 units of shops. The shopping complex is to be procured via PPP with OSIWOKS Nig. Ltd and is to be located close to the Presidential and Medical hostels in the Abuja Park.

Education Declined issuance of OBC Certificate of Compliance via letter dated 30th Dec, 2021 pending provision of more information in line with N4P.Development
36Federal Ministry of Education/University of Port Harcourt

PPP Projects:

The University seeks for the establishment of a Loading Bay for Taxis/Buses, University Park by the main gate area (Abuja Park).

EducationLetter issued to the University on 11th June, 2021 declining the issuance of OBC Certificate. Declined issuance of OBC Certificate of Compliance via letter dated 30th Dec, 2021 pending provision of more information in line with N4P.Development
37Federal Ministry of Education/ University of UyoConstruction Of students Hostels on a PPP arrangement.
The University of Uyo is seeking to collaborate with a Private Proponent for the development of student’s hostels at the various campuses of the University with a capacity for 12,000 bed spaces.
Education

Issued certificate of Compliance on the 25th of May, 2022.

A letter dated 14th July, 2022 on the draft advert was sent to University of Uyo.

Procurement
38Federal Ministry of Health/University College Hospital Ibadan

PPP Projects:

Establishment and Operation of an Independent Power Plant in the Hospital

Education/ EnergyA letter dated 2nd July, 2021 was sent to the Ministry to provide more information to confirm viability and bankability of the project.Development
39Federal Ministry of Health/ University of Ibadan College HospitalEstablishment and Operation of an Independent Power Plant in the University College HospitalEducation/ PowerOBC Certificate of Compliance issued on the 20th of April, 2022Procurement
40Airforce Institute of Technology, Kaduna

Unsolicited PPP proposal:

submitted by private proponents on the development of students’ hostels

Education/ Urban DevelopmentMet with the Management team on the 9th June 2021 and highlighted the processes of Solicited and Unsolicited processes.Development
41Ahmadu Bello University ZariaDevelopment of Shopping Complex and Luxury Apartments at GRA Zaria through a PPP arrangementEducation/Urban DevelopmentOBC certificate of Compliance issued on September 22, 2022Procurement
42Federal Ministry of Education/Federal Polytechnic Ado-Ekiti

Development of Hostel complex

At Fed-Poly Ado-Ekiti

Education/ Urban DevelopmentDeclined issuance of OBC Certificate of Compliance on the 19th of April, 2022Development
43Federal Polytechnic, BauchiConstruction of Students Residential Hostel Blocks (Federal Polytechnic, Bauchi and EMKOANAL International Nigeria Limited)EducationA letter was sent on 11th October, 2022 was sent to Federal Polytechnic, Bauchi stating that the contract agreement with the project proponent was disagreed to by the commission, due to the stage of the projectDevelopment
44Federal Ministry of Water ResourcesGurara 2 Greenfield Multi-Purpose Dam
The Concession of the Gurara 2 Greenfield multi-purpose Dam, Niger State includes 300MW of hydropower components of the dam.
EnergyThe project is currently in Development Phase. The project land is encumbered and the Ministry is resolving the issue. Thereafter, the Outline Business Case is expected to be forwarded to ICRC. Awaiting the Ministry’s response.Development
45Federal Ministry of Water ResourcesOwena Multi-Purpose Dam water supply (Unsolicited Proposal)
The project will provide about 1.5kwh of electricity to the national grid.
EnergyThe Commission granted OBC Certificate of Compliance on March 10, 2017.Procurement
46Federal Ministry of Water ResourcesDevelopment of 9MW Oyan Dam Unsolicited
This involves the Operations and Maintenance of 9MW hydroelectric power.
EnergyThe Commission has revalidated the OBC Certificate of Compliance (which expired on March 8, 2018) since all key parameters remained the same.Procurement
47Federal Ministry of Water ResourcesDevelopment of 220MW River Mada Medium hydropower plant in Nasarawa State
This involves the Operations and Maintenance of 220MW hydroelectric power.
EnergyThe Commission reviewed the updated OBC and issued a Compliance Certificate on February 23, 2018.Procurement
48Federal Ministry of Water ResourcesOther PPP Projects:
i. Concession of Oturkpo Dam for Hydro Power and other purposes.
ii Development of Dasin Hausa Dam for Hydro power and other purposes.
EnergyThe Ministry has been advised to procure a Transaction Adviser that will prepare a bankable OBC report for the project.

Development

 

 

 

 

 

 

49Federal Ministry of Mines and SteelAjaokuta Steel company Ltd & National Iron Ore Mining Company (NIOMCO)
Rehabilitation, completion, management and operation of Ajaokuta Steel Company and National Iron Ore Mining Company (NIOMCO) through PPP Concession agreement.
Energy

Meeting with the Ministry and the TA held on 2nd September, 2022.

 

Status update meeting with the Honorable Minister of State for Mines and Steel Development held on the 25th of November 2022.

Development
50Federal Ministry of Power/Nigerian Electricity Management Services Agency (NEMSA)Transformer Repair Services
The project is an unsolicited proposal submitted by Kilowatt Electrics Limited (KWEL) to the NEMSA. KWEL is proposing a joint venture partnership with NEMSA to operate the transformer repairs workshop in Ijora Lagos and construction of transformer repair workshops in Port Harcourt and Kaduna centers. The partnership will also include the role of electrical inspection, testing and certification of all electrical installation hitherto performed by NEMSA.
EnergyTechnical Bid opening for concessionaire took place on May 17, 2021
Financial Bid opening for concessionaire took place on  June 7, 2021.
Procurement
51Federal Capital Territory/ Abuja Infrastructure Investment Center (AIIC)Small Hydropower Embedded Power from the Wupa Water Treatment Plant Effluent Discharge
Wupa Water Treatment Plant Project on a Build Operate and Transfer (BOT) PPP model to produce electric power from the effluent discharge from the plant. Power generation capacity is estimated at 3,346.29kW/day which would power the WWTP and also provide the input for the production of fertilizer and plastics.
The power plant is expected to sell excess power to the national grid.
EnergyNo correspondence from the Ministry on this since 2017. Awaiting formal correspondence on the way forward from Federal Capital Territory/AIIC.Development
52Federal Ministry of PowerConcession of 1.2MW Grid Connected PV Solar Power Plant
Concession of 1.2MW Grid Connected PV Solar Power Plant at Lower Usuma Dam, Abuja under the Japanese Grant-In-Aid to the FGN
Energy

OBC Certificate of Compliance was issued on 13th September, 2017.

 

 

 

 

Procurement

 

 

 

 

 

 

 

 

 

53Federal Ministry of Petroleum ResourcesNNPC Refineries Rehabilitation Project
The project will involve the rehabilitation of refineries across the country.
Energy

Virtual Bid Opening for EPC Contracts on Port-Harcourt Refinery took place on July 24, 2020.

Virtual Bid Opening for EPC Contacts on Warri and Kaduna Refineries took place on 25 August, 2020.

Procurement
54Federal Ministry of Petroleum ResourcesConstruction Of LPG And Ethanol/Methanol Plants At Emede Uzere Delta State (On Public Private Partnership (PPP) Basis)
The construction of an LPG and Ethanol/Methanol Plant at Emede Uzere, Delta State from Everlinksourcing Ltd to the Ministry of Petroleum Resources.   Identification of Public Private Partnership projects for Petroleum Equalization Fund,
EnergyNo further Correspondence from Ministry on this project

Development

 

 

 

 

 

 

 

 

 

 

 

 

55Federal Ministry of Power700 MW Zungeru Hydro Electric Power Plant.Energy

Technical bid opening and evaluation for TA selection took place on June 23, 2021.

OBC certificate of compliance issued on September 5, 2022.

 

RfQ documentation submitted by BPE for ICRC concurrence on September 28, 2022. RfQ and advert reviewed and sent to BPE.

Review of 11 bids on the ZHPP held on the 28th and 29th of November 2022.

Procurement
56Federal Ministry of Petroleum Resources/NNPCFMoP have sent concept notes to the Commission and are keen to develop the following projects;
i. Concession and development of 25MW Katsina Wind Farm
ii. Concession and development of 215MW Kaduna Power Plant
iii. Concession and development of 10MW lake Chad Basin Development Authority, Borno.
Concession and development of 1.2MW Solar facilities at Lower Usuma Dam.
Energy

The Commission received concept notes on April 12, 2018. The Ministry has been requested to update the Concept Notes and engage a TA to assist with the process.

 

 

 

 

 

 

 

Development
57Federal Ministry of Power University of Benin 15MW Solar Project (Unsolicited Proposal)
The project is a 15MW PV Solar power to be sited on a 30Hectare parcel of land at the University of Benin Ugbowo Campus.
EnergyRFP evaluation exercise has been conducted by UNIBEN.
A virtual meeting was held between ICRC E&U Unit and UNIBEN project Team on the 3rd November 2020 to discuss critical dynamics of the project structure to ensure commercial close can be successful achieved.UNIBEN Team is to revert with all the actionable steps discussed and agreed.

Development

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

58Federal Ministry of EducationDevelopment of Hydro power from Kiri DamEnergySettlement meeting held on 14th Aug, 2019.
The Attorney General and Minister of Justice has issued a Legal Opinion for guidance vide a letter on 22nd July, 2020 on the Kiri suit.At the meeting held with the Minister on May 17 2021, ICRC informed that this procurement should be conducted through a solicited process, hence the ministry should engage a transaction adviser to prepare OBC and Financial Model.
Development
59Federal Ministry of Water ResourcesSolar Power Off-Grid Rural Electrification
The provision of off-grid solar power to the remote rural communities in Taraba, Gombe, Niger, Kogi, Ebonyi, Oyo, Ogun, Edo, Akwa Ibom, Katsina and Kebbi states
EnergyJoint OBC/FBC compliance certificate was Revalidated 7th October 2020.

Procurement

 

 

 

 

 

 

60Federal Ministry of Power/ Electrification Agency40 MW Kashimbila Dam Hydropower Station
Kashimbila Dam is a 32m high composite dam with a 40 MW hydropower station located on the Katsina-Ala River, Taraba State, a tributary of the Benue River, approximately 20 km downstream of the Nigeria-Cameroon border. It comprises a zoned rockfill embankment with a central mass gravity ogee spillway, an outlet works which consist of multi-level intakes and outlet structure.
Energy

The Commission granted OBC Compliance Certification on October 15th, 2018.

Evaluation of technical bids completed on the 16th and 17th of March 2022. Awaiting approval to open financial bids from the Honorable Minister.

Negotiations carried out with preferred bidder in September 2022.

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

 

61Federal Ministry of PowerMakurdi Hydropower Project
The Makurdi Hydropower Project (Makurdi HPP) was originally conceived as part of the Plan for Electric Power System Development issued by the then National Electric Power Authority [NEPA] in 1974. The planned dam site is located on the Benue River, the primary tributary of the Niger River in Nigeria, about 10 ~ 15 km upstream of Makurdi, the capital of Benue State.
Energy

The Commission granted OBC Compliance Certification on October 15th, 2018.

A joint stakeholder meeting was held on the 14th July 2022 at the BPE’s office to discuss the status of the project. A key highlight was the increase in the nameplate capacity from 1500MW to 1650MW.

Outline Business case CoC issued on the 28th of August 2022.

Project Steering Committee (PSC) was inaugurated on the 12th of December 2022. Key members included the Minister of Power and Water Resources who would serve as Chairman and Co-chairman.

Procurement
62Federal Ministry of PowerDevelopment of 136 MW Manya Hydropower Generation Facility, Taraba StateEnergyThe OBC compliance certificate for Manya Hydro Power Plant (HPP) was revalidated on 26th October 2020.OBC Certificate of Compliance revalidated on the 6th of May 2022.  RfQ documents reviewed and sent to the Ministry.

Procurement

 

 

 

 

 

 

 

 

63Federal Ministry of Water ResourcesDevelopment of 182 MW Bawarku Hydropower Generation, Benue StateEnergy

The OBC compliance certificate for Bawarku Hydro Power Plant (HPP) was revalidated on 26th October 2020.

OBC Certificate of Compliance revalidated on the 6th of May 2022.

Review of RfQ documents ongoing.

RfQ documents reviewed and sent to the Ministry.

Procurement
64Federal Ministry of Water ResourcesDevelopment of Hydroelectric power from existing 6 Small & Medium from dams across the Country
Federal Executive Council (FEC) gave an approval on the 30th November 2016 for 6 dams.
1. Bakolori Dam, Zamfara State
2. Omi - Kampe Dam, Kogi State
3. Doma Dam, Nasarawa State
4. Jibiya Dam, Katsina State
5. Zobe Dam, Katsina State
6. Ikere Gorge Dam, Oyo State
Energy

Ongoing finalization of the Concession Agreements between the Ministry and the Preferred. Bidders for onward transmission to the Federal Ministry of Justice for vetting.

A meeting took place between ICRC, FMOP, and their Legal Advisers AELEX Partners on 27 August 2020 to discuss ICRC’s recommendations for Ikere Gorge, Omi Kampe, Bakalori and Zobe & Jibiya hydro power plant Concession Agreements.

Ongoing review of FBC document for Ikere George Dam.

Procurement
65Federal Ministry of Power(Power)/ Federal Ministry of Water ResourcesDevelopment of Small, Medium and Large Hydropower Project Phase 2
Development of hydroelectric power from existing small, medium & large hydro dams in twelve (12) locations nationwide. As shown below:
Lot 3A
• 7MW Girmi Earth Hydropower Plant, Kaduna State (Brownfield)
• 1.2 MW Lower Usuma Hydropower Plant FCT (Brownfield)
• 9MW Oyan Hydropower Plant, Ogun State (Brownfield)
Lot 3B
• 138MW Dasin Hausa Hydropower Plant, Adamawa State (Greenfield)
• 40MW Kashimbilla Hydropower Plant, Taraba State (Brownfield)
• 92MW Garin Dalli Hydropower Plant, Benue State (Greenfield)
Lot 3C
• 182MW Bawarku Hydropower Plant, Benue State (Greenfield)
• 136MW Manya Hydropower Plant, Taraba State (Greenfield)
• 109MW Katsina Ala Hydropower Plant, Benue State (Greenfield)
Lot 3D
• 700MW Oguma Hydropower Plant, Kogi State (Greenfield)
• 1500MW Makurdi Hydropower Plant, Benue State (Greenfield)
• 441MW Onitsha Hydropower Plant, Anambra State (Greenfield)
Energy

The preferred and reserve bidders’ TA list will be communicated to the Commission once all assessments have been finalized by FMoP.

 

Makurdi Hydropower Project was upgraded to 1650MW. OBC Certificate issued on 29th August, 2022. Awaiting bidding documents.

 

Ongoing review of the 460MW Grand Katsina Ala OBC.

 

OBC Certificate of Compliance issued on the 15th of December 2022 for the 460MW Grand Katsina Ala hydropower project.

Development
66National Research Institute for Chemical Technology

Pyrolysis plant for the production of carbon black and diesel oil

 

EnergyOBC has been reviewed prior to the meeting and a report has been sent. Meeting between ICRC and the technical team of NARICT was held on the 20th of August 2021 to discuss on the OBC. NARICT is meant to re-submit the OBC effecting the corrections.Development
67National Research Institute for Chemical TechnologyPlant for the production of polyester yarn from waste materialsEnergyOBC has been reviewed prior to the meeting and a report has been sent. Meeting between ICRC and the technical team of NARICT was held on the 20th of August 2021 to discuss on the OBC. NARICT is meant to re-submit the OBC effecting the corrections.

Development

 

 

 

 

 

 

 

 

68National Research Institute for Chemical TechnologyPlant for the production of Bioplastic from biomassEnergyOBC reviewed and a report sent. Meeting between ICRC and the technical team of NARICT held on August 20 2021 to discuss on the OBC. NARICT is meant to re-submit the OBC effecting the corrections.Development
69Petroleum Equalization FundIdentification of Public Private Partnership projectsEnergyMeeting with the management staff of PEF and ICRC on the 19th day of August. PEF yet to decide projects to be undertaken as PPPs.Development
70Itisi Hydropower

Development of the 40MW hydropower in Kaduna State

 

Energy

Outline Business Case CoC issued on the 2nd of August 2022.

RfQ documents reviewed and sent to the Ministry.

Procurement
71Federal ministry of Water ResourcesDevelopment of Farin Ruwa Hydro projectEnergyOBC Certificate of Compliance issued on December 6, 2022 
72Federal  Ministry of Power Identification of PPP Projects for screening, prioritization and approval for procurement
Signed Memorandum of Understanding for Potential areas1 of collaboration.
The following projects are under consideration:
i. Establishment of Federal Ministry of Environment’s Clean and Green Campaign to end open defecation in public areas by 2019 by providing Public Toilets nationwide. Pilots to be in FCT public schools, motor parks and market places; and extended to the 36 States.
ii. Framework for Plastic Industry and other private sector companies to take plastic waste off the streets by 2019
iii. Development of a New Head Office for the Federal Ministry of Environment (to be completed in 2018)
iv. Establishment of Scrap metal recycling facility, Sokoto, Sokoto State.
v. Establishment of Scrap metal recycling facility, Kaduna, Kaduna State.
vi. Establishment of Scrap metal recycling plant, Emuoha, Rivers State.
vii. Establishment of Scrap metal recycling plant, Owerri, Imo State.
viii. Establishment of Ozone village in Ikenne Ogun State.
ix. A pilot indigenous project to capture Biogas from faeces/ urine in Federal Government Girls Secondary School, Abaji, Abuja FCT
Development of Pilot Cotter Mitigation from lanfill for Energy production Wupa Lanfill, Wupa Village Abuja
EnvironmentMeeting held on 30th May, 2019 between Ministry of Environment and ICRC regarding pipeline projects submitted to the Commission in 2018 and the way forward for reviving PPPs within the Ministry.Development
73Federal Ministry of Environment (FMoE)Establishment of a Bamboo Value Chain
Establishment of a Bamboo Value Chain Business including maintaining, managing and scaling up the Bamboo factory in Lokoja, Kogi state
EnvironmentAwaiting the submission of an updated OBC by the Ministry.Development
74Federal Ministry of HealthManagement Equipment Services (MES) project: To provide Medical Equipment and services in Government HospitalsHealthMeeting on MES sub-committee held on the 3rd and 29th of July 2019 review MES Concept note.Development
75Federal Ministry of Health/ University of Port Harcourt Teaching HospitalConstruction of staff housing estate, shopping complex and new House Officers’ (Doctors') quartersHealthAwaiting response from the University after a letter of non-viability was sent by ICRCProcurement
76Federal Ministry of HealthDevelopment of Oncology Centre of Excellence for Cancer Care in 8 Teaching Hospitals across the Geopolitical zones Federal Ministry of Health
The FGN through the Federal Ministry of Health seeks to procure and manage Oncology equipment in Federal Teaching Hospitals across the Country.
HealthThe PDT has adopted the option of Traditional Procurement / Leasing where payment is tied to equipment management and service/the continuous function of the machine on service delivery.
Awaiting further steps from the Ministry.

Procurement

 

 

 

 

 

 

 

 

 

77Federal Ministry of HealthUpgrade of the 3rd Phase of Teaching Hospital Rehabilitation Project
The Federal Government through the Federal Ministry of Health seeks to Rehabilitate 7 Teaching Hospitals and Construct a 500-bed state-of-the-art specialist hospital through PPP. This is the 3rd of the Teaching Hospitals rehabilitation process. The 1st and 2nd Phases were done with government funds
Urban Development

OBC Certificate of Compliance was revalidated and re-issued to the Federal Ministry of Health on the 24th of August, 2020, for an accelerated negotiated PPP pilot scheme for six (6) teaching hospitals, one in each of the Nation’s geopolitical zones.

 

OBC Certificate of Compliance was revalidated and re-issued to the Federal Ministry of Health with some adjustment of scope by the Federal Ministry of Health on the 30th of Dec, 2021.

Procurement
78Federal Ministry of HealthOrthopedic Hospital, Dala- Kano 
The proposed PPP seeks to construct staff quarters within the premises, conversion of existing bungalow within the hospital premises to commercial guest house, equipping of the Hospital mortuary building and Equipping, Furnishing and Operation of a Private wing of the Hospital.
HealthThe Ministry is in the process of procuring a Transaction Adviser to prepare an Outline Business Case to determine project viability and bankability.Development
79Federal Ministry of Health (FMoH)Establishment of Anti-Snake Venom Production Facility in Nigeria through PPP
The Ministry seeks the Establishment of Anti-Snake Venom Production Facility through PPP.
HealthInter-Ministerial Committee meeting held on 27th May, 2019 on proposed EDTV.

Development

 

 

 

 

80Federal Ministry of Health\ Federal College of Education (Technical) Bichi, Kano State.Development of hostel facilities and supermarket
FCE Bichi (Technical) seeks guidance to develop hostel accommodation.
HealthThe submitted document has been reviewed and the College has been asked to submit additional documents.
The Commission is awaiting response from FCE Bichi.

Development

 

 

 

 

 

 

81University of Calabar Teaching Hospital. Federal Ministry of HealthStudents & Staff residential accommodation
Unsolicited proposal for the Design, Build, Manage and Transfer of Students & Staff residential accommodation within the Hospital
HealthNo correspondence from the University on this project since 2020Development
82Federal Ministry of HealthOncology Centre and Operation of Oxygen Gas Plant at Aminu Kano Teaching Hospital, Kano
The management of Aminu Kano Teaching Hospital, kano wrote to the Honourable Minister proposing the implementation of the following projects through PPP: Establishment of Radiotherapy/Oncology Centre and Operation of Oxygen Gas Plant.
Health

Last PDT meeting was held on September 12th, 2018.

 

Development
83Federal Ministry of HealthDeployment of Thermal Health Scanners at the entry and exit points in Nigeria
In Compliance with International Health Regulations 2005 (IHR 2005) for the prevention and spread of diseases the Ministry of Health is desirous of deploying thermal health scanners at entry/exit points of the country.
HealthA PDT meeting was held on 5th July, 2019 to discuss issues raised by Federal Ministry of Finance on the OBC.Development
84Federal Ministry of HealthAbuja Healthcare City projectHealthPDT meeting held on 13th May 2019 to assess draft OBC.Development
85Federal Ministry of HealthNational Orthopaedic Hospital, EnuguHealthOBC Certificate of Compliance was withheld pending adjustments. Letter was dispatched on 20th July, 2020.Development
86Federal Ministry of Health/Usmanu Danfodio University, Sokoto

Public Private Partnership Initiative

Pharmaceutical Products and Surgical Consumables and Diagnostic Laboratory Services in Usman Danfodio University Teaching Hospital, Sokoto

HealthThe Commission has reviewed the submitted document and advised the University to provide more information to confirm viability and bankability of the project.Development
87Federal Ministry of HealthDEVELOPMENT OF ADVANCED SURGERIES CENTRES IN NIGERIA  The Federal Ministry of Health, submitted an unsolicited proposal developed by LAANJ International Ltd, requesting the Federal Government to allocate specific departments in three Nigerian Public hospitals, one each in Abuja, Jos and Port Harcourt, where they can bring in experts from India at intervals to perform advanced surgeries. The proposal aimed to be established as an Operation and Management (O & M) Pubic Private Partnership (PPP) modelHealthReview of the OBC completed. Awaiting response from FMoH.

Development

 

 

 

 

 

 

 

 

 

 

 

 

88Federal capital Territory Administration / Abuja Properties Development Company APDCDevelopment of District Hospitals
Development of district hospitals in Wuye, Galadimawa and Lugbe Districts of the Federal Capital City.
HealthMeeting between ICRC and officials of the FCT Hospitals Management Board held on February 17th 2021 on commencement of the PPP for the development of the hospitals.Development
89

Federal Ministry of Health

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MEMORANDUM OF UNDERSTANDING FOR THE PUBLIC PRIVATE PARTNERSHIP ON MEDICAL LABORATORY DIAGNOSTIC SERVICES AT THEAHMADU BELLO UNIVERSITY TEACHING HOSPITAL, ZARIA (ABUTH, ZARIA).
Federal Ministry of Health submitted an unsolicited proposal requesting the ABUTH Zaria to allocate space, electricity, water and security. While DNA LABS will supply all equipment and provide efficient Lab services in the following areas:
i. Chemical Pathology
ii. Immunology
iii. Microbiology
iv. Hematology
v. Forensics
vi. Molecular DiagnosticsThe Medical Laboratory Diagnostics Services is proposed to be established as a Supply, Operate and Management Pubic Private Partnership (PPP) which aims at making huge improvement in the quality-of-service delivery and earning capacity of the Hospital. 
HealthThe Commission has reviewed the document and advised the Ministry to provide more information to confirm viability and bankability of the project.Development
90Federal Ministry of Health/UCH IbadanProposed renovation and upgrading of School of Nursing students’ hostel in the hospitalHealth

OBC Certificate of Compliance issued on the 22nd of March, 2022.

Response letter written to UCH, Ibadan on the resubmission of OBC and financial model dated 23rd May, 2022

Development
91NNPC/NNPC Medical Services Limited (NMSL)

Development of Multi-Specialty Hospitals

The NNPC through its subsidiary seek to develop 5 Multi specialties hospitals in 5 locations, these locations are: Maiduguri, Port Harcourt, Lagos, Kaduna and Abuja. It also proposed the Establishment of Intravenous Fluid Plant in Kano through PPP methodology.

Health

OBC Compliance Certificates issued to NMSL on the 1st of April, 2022 for the proposed Multi-Specialist Hospitals (MSH) in Abuja and Port-Harcourt.

OBC Compliance Certificates issued to NMSL on the 21st of July, 2022 for the proposed Kano Intravenous Fluid (IVF) Plant project.

OBC Compliance Certificates issued to NMSL on the 21st of July, 2022 for the proposed Multi-Specialist Hospitals (MSH) in Lagos.

OBC Compliance Certificates issued to NMSL on the 21st of July, 2022 for the proposed Multi-Specialist Hospitals (MSH) in Maiduguri.

 

Procurement
92Federal Ministry of Health (Port Health)

Decontamination & Fumigation Project:

for vessels arriving all seaports in Nigeria (Lagos, Rivers, Delta, Calabar, etc)

Health

OBC Compliance Certificate issued on the 12th April, 2022.

A status report attached with Expression of Interest was sent to the ministry on the 23rd of December 2022.

Procurement
93University College Hospital Ibadan/Federal Ministry of HealthRehabilitation of Mortuary Facility in UCHHealthOBC Certificate of Compliance issued on September 2, 2022Procurement
94Federal Ministry of InteriorDevelopment of Advanced Passenger Information API, and Passenger Name Record PNR Portals
The Nigeria Immigration Service (NIS) through the Ministry of Interior are developing an Advanced Passenger Information API, and Passenger Name record PNR portals.
ICTNo correspondence from the Ministry on this since 2019Development
95National Lottery Regulatory Commission/ National Lottery Trust FundDeployment of Central Management System Platform
The National Lottery Regulatory Commission/ National Lottery Trust Fund are seeking to deploy of Central Management System Platform
ICTAwaiting formal correspondence on the way forward from NLRC/NLTF

Development

 

 

 

 

 

96Federal Fire ServiceDevelopment of National Fire Data Repository Center (NFDRC)
The project involves the upgrade, rehabilitation, operation and maintenance of the NFDRC Enterprise Unit through a PPP arrangement that provides an ICT-based system to ensures speedy detection and rapid response to fire emergencies in a self-funding and sustainable manner.
The project will cover the design and development of the NFDRC systems.
ICTFull Business Case revalidated on May 23, 2022Procurement
97Federal Fire Service/ Federal Ministry of InteriorSAFETY SYSTEMS NETWORKING, MONITORING AND DISPATCHER REAL-TIME INTEGRATION SYSTEM (LSSNMDI)ICT

OBC certificate of compliance issued on June 21, 2021.

RfQ closed evaluated

Direct negotiations with preferred bidder to commence on October 6, 2022

Procurement
98Federal Ministry of Finance, Budget and National PlanningDevelopment, deployment and management of Automated Customs Gateway Portal for Import Duty Exemption Certificate (IDEC) and Imported Vehicle identification Number Registration (VREG)ICT

FEC approved the project on November 29 2019

Next Step: contract Signing and custody of agreement

Procurement
99Federal Ministry of JusticeCriminal Justice Management Information System (CJMIS)
The (FMoJ) received an Unsolicited Proposal from ECR Technology Services Limited seeking to utilize the application of a Criminal Justice Management Information System that will enable an economically viable way of implementing the Criminal Justice Act (2015).
ICTAwaiting further correspondence on the project from the MOJ Development
100Federal Ministry of Industry, Trade & Investment (FMITI)Digital Industry Trade and Investment Platform (DITIP)ICTMeeting held with the Ministry on the 25th January, 2022 advising the Ministry on various options and their outcomes for the project.

Development

 

 

 

 

101National Communications Commission Deployment of a Centralized Device Management System (DMS)
The procurement of Device Management Solutions (DMS) to combat counterfeit and sub-standard ICT devises in Nigeria.
ICT / Communications

Engagement of TA is ongoing, involving:

A meeting was held with NCC and the proponent for the amendment of the scope of the project on the 7th of July 2022. The scope was adjusted to accommodate the monitoring of the activities within the digital economy.

RfP, technical and financial bid evaluation has been done. Awaiting evaluation report to be approved by the Project Steering Committee, bidder notification then posting of the preferred bidder guarantee and then negotiation can commence.

 

 

Procurement
102National Communications CommissionDeployment of a Revenue Assurance System (RAS)
The procurement of Revenue Assurance (RAS) to combat revenue leakages amounting to N1Trillion naira annually in the telecoms market generally.
ICT / Communications

NCC sent a letter on the 20th of May 2022 updating new financial partners for the project.

 

The Commission sent its opinion to NCC on the expansion of the scope on the 28th of August 2022.

 

An FBC Certificate of Compliance was issued to the expanded RAS/DSR project on December 8, 2022

 

Procurement
103National Space Research & Development Agency (NASRDA)

Research and Development of Satellite Technology and Equipment for the Provision of cost-effective satellite broadband to rural Nigeria.

 

ICT / Communications

Letter from the Office of the National

Security Adviser received on May 22, 2022.

Issuance of FBC CoC on the 27th of June 2022.

 

Project approved by FEC on November 30, 2022

Procurement
104National Space Research & Development Agency (NASRDA)Concession of Planetarium and Museum
The project seeks to equip, operate and maintain the Planetarium and Museum at the Obasanjo Space Centre Abuja.
ICT / Communications

Full Business Case Certificate of Compliance issued on July 25, 2022

 

Project approved by FEC on November 2 2022

Procurement

 

 

 

105Federal Ministry of Finance

Integrated Secure Track and Trace Solution

Designed to monitor goods and services subject to excise duties

ICT/Finance & revenueOutline Business Case Certificate issued on September 26, 2022Procurement
106Federal Ministry of Industry, Trade & InvestmentDevelopment of SME Portal
A technology enabled platform project that will encourage more MSMEs to be attracted into the formal sector.
The project is currently in Development Phase.
Industry, Trade and InvestmentFBC Certificate of Compliance was issued on the 26th April, 2019.
FEC has approved the FBC certificate.Next Step: contract Signing and custody of agreement

Procurement

 

 

 

 

 

107Federal Ministry of Industry, Trade and InvestmentDevelopment of Okerete Transnational Border Market at Saki West LGA, Oyo State
The Ministry intends to establish transnational border markets to promote regional integration, create employment in rural areas and reduce high incidence of smuggling across Nigeria’s borders. The intention is to create them at 6 geo-political zones of the country starting with Okerete, in South West region.
Industry, Trade and InvestmentIt was unanimously agreed at the Technical Committee meeting that the road leading to the site should be graded and tarred as well as include the construction of a bridge that will link Nigeria and the Republic of Benin.Development
108Federal Ministry of Industry, Trade & Investment and Niger StateBabanna Transnational Border & Regional Market Project
Integration of informal trade with the formal sector, Elimination of smuggling, Revenue generation, Enhancement of bilateral integration and trade, Enhancement of security along the border are all aspects of this Transnational border project.
Industry, Trade and InvestmentA Technical Committee meeting held on 23rd January, 2020 to chart a way forward for the project.
The meeting agreed to develop a TOR for the engagement of TA on the project.
Development
109Federal Ministry of Petroleum  Resources & NNPC

Rehabilitation of NNPC Pipelines Network and Storage Facilities Under a BOT Model

The project has been submitted by NNPC providing a Business Case for the BOT Model for the rehabilitation of the NNPC’s pipeline Network and Storage Facilities.

Petroleum/ Energy

OBC Certificate of Compliance issued on July 22, 2021

Virtual evaluation of bidders held between 25th July to 29th July 2022. Awaiting outcome of bidders and

reserve bidders

Procurement

 

 

 

 

 

 

 

 

 

110Nigerian Shippers’ CouncilDevelopment of Ibadan Inland Dry Port (IDP) under PPP Model
The NSC in facilitating trade and protection of cargo interest in all transport modes and its mandate as the economic port regulator is promoting the development of Ibadan Inland Dry Port (IIDP) in Ibadan, Oyo State under PPP arrangement. The NSC in partnership with Oyo State Government intend to enter into joint-venture PPP with a top tier private sector partner to establish an Inland Dry Port at Olorisaoko on the Iseyin-Ibadan road, Ibadan, Oyo State.
Port/ICD
Next steps:

• Conclusion and forwarding of FBC report to the Commission for issuance of compliance certificate.
• FEC approval
• Commercial Close
• Financial CloseNo communication since 2018
Procurement
111Federal Ministry of Transportation / Nigeria Shippers Council (NSC)The Dagbolu Inland Container Depot (ICD):
(Solicited Proposal) The project concerns the development of a Greenfield ICD in Osun State, South-West Nigeria. The ICD is being developed to exploit the strategic advantages in Nigeria's huge export and import market by making the country a trans-shipment hub for the West African region. The ICD when developed would provide storage and cargo handling facilities for export and import of containerized cargos to and from the hinterland of Nigeria especially around the Southwest states of Ondo, Ekiti, Osun; Edo State and Kwara State.
Ports Sector

The Commission reviewed the RFP and approved it for NSC to issue to the prequalified bidders.

Next step:

Advertisement in the print media for the selection of preferred concessionaire.

Procurement
112Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Inland Container Depot (ICD) in Lolo, Kebbi State:
(Unsolicited Proposal):
The Economic Reform Programme, approved the setting up of Lolo Inland Container Depots (ICD) to provide port services to shippers.
(OBC) received from the Nigeria Shippers Council (NSC) in respect of the unsolicited proposal developed by Deltatlantic Nigeria Ltd.
Ports Sector

The Commission re-issued an OBC Certificate November 8, 2017.

Negotiations have stalled with preferred bidder Deltatlantic Nigeria Limited despite repeated attempt to carryout due diligence on the land and the investor. This has delayed further progress on the project

Procurement
113Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Inland Container Depot (ICD) in Onitsha, Anambra State: This has a design that consists of an annual 5,000 TEUs capacity facility which can be expanded with increasing throughout.Ports SectorThe Commission issued an OBC Certificate November 8, 2017.
Next step:
Advertisement in the print media for the selection of preferred concessionaire.
Procurement
114Federal Ministry of Transportation / Akwa Ibom State GovernmentIbom Deep Sea Port Project
(Solicited Proposal): The Ibom Deep Sea Port (IDSP) project involves the development of a Greenfield Deepsea Port and accompanying Free Trade Zone (FTZ) in Akwa Ibom State in the South-South geopolitical zone of Nigeria. The proposed Port and FTZ are part of the proposed Ibom Industrial City initiative that will be established on a 14,400-hectare site donated by the Akwa Ibom State Government (AKSG) at no value. The IDSP project is intended to become a major national and regional economic gateway that will provide additional container handling capacity for the country. In addition to containers, the IDSP is expected to handle petroleum products (export and import), crude oil and natural gas (export), vehicles (import) and bulk trade in natural resources (import and export).
It is planned to be the deepest port in the West African sub-region.
Ports Sector

Preliminary negotiation meeting with the preferred bidder, (Bollore/Power China Consortium) was done on January 9th, 2020 in Lagos.

The Commission Revalidated the Full Business Compliance certificate to the FMoT/NPA on 12th Feb, 2020

After expiration of certificate, the Commission once again revalidated and re-issued FBC certificate on 17th September, 2020 with 6 months validity.

FEC approved the FBC on 16th December

Next Steps:
Commercial Close
Financial Close

Procurement
115Federal Ministry of Transportation (FMoT) / Nigeria Ports Authority (NPA)Kirikiri Port Lighter Terminal I & II
(Solicited Proposal): The Federal Government aims to procure concessionaires to rehabilitate and upgrade these terminals which were hitherto selected as fishing terminals.  The project development and procurement costs are being sponsored under International Development Association (IDA) Credit to the Federal Government of Nigeria for PPP support.
Ports Sector

The Financial bids for KLT II was opened and Tin Can Inland Container Terminal Limited (TICT) emerged as the preferred bidder.

Project Closeout & Negotiation with TICT for Kirikiri Lighter Terminals took place 11th – 14th June, 2018.

No correspondence on this project since 2018

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

116Federal Ministry of Transportation/ Nigerian Ports Authority The Development of Deep Sea Port in Badagry, Lagos
The project is a Greenfield development designed to cater for containers, dry bulk, liquids, Ro-Ro, oil & gas products, and also operate a free trade and local logistic zones.
Ports SectorProject approved by FEC on August 3, 2022 for 45 years concession periodProcurement
117Federal Ministry of Transportation/Cross River State Government (CRSG)The Development of the Bakassi Deep Sea Port
The Cross River State Government intends to develop a sea port at Bakassi under a PPP arrangement, in pursuance of which it sought the collaboration of the Federal Government of Nigeria in accordance with existing legal framework for port development in implementing the proposal.
Ports Sector

Outline Business Case Certificate of Compliance was granted for the project on 25th September,2019 to enable the project to proceed to procurement phase.

Bid opening of RfP took place on 17th June, 2022

Procurement
118Federal Ministry of Transportation / NPAPort Single Window
The project involves the introduction of electronic single window platform that can effectively coordinate all port related/cargo clearance activities capable of potentially transforming port operations to a seamless, paperless system by eliminating redundant procedures and duplications.
Ports SectorThe Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.
Next step:
Awaiting procurement of TA and preparation of OBC.
Development
119Federal Ministry of Transportation / NPANational Freight Intelligence and Transportation Hub (NAFITH)
The project involves an application of information and communications technology (ICT) in the management of transport problems. It seeks to leverage on new innovation to provide needed solutions to the teething transport problems in Apapa.
Ports Sector

The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.

Next step:
Awaiting procurement of TA and preparation of OBC

Development

 

 

 

 

 

 

 

120Federal Ministry of Transportation / NPAKoko Port Concession
FGN is seeking to grant a new Concession over the Koko Port in 2017. NPA is conducting hydrographic studies to determine the best way the channels leading to Koko port could be optimally utilized. The transaction for this general cargo port will consist of a 180 m quay and apron, and a transit shed.
A plan view of the Koko Terminal lease will consist of the following facilities:
A 175 m long quay and apron;
• Additional waterfront for future expansion;
• A five-bay transit shed;
• The port administrative buildings and entrance gate;
• Port support buildings including the fire station, security police building, the power station with backup generator, and the maintenance shops; and
• A disused warehouse and miscellaneous buildings behind the quay area, and all other lands and buildings inside the Koko Port perimeter.
Not included in this transaction are the jetty and other facilities or equipment currently used by Tower Petroleum for bulk liquid (bitumen) handling.
Ports Sector

The NPA is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
121Federal Ministry of Transportation / (NPA)Ikorodu Lighter Terminals
The port is dedicated to salvaging unclaimed or overtime containers in the ports, with a view to providing needed solutions to port congestions and pave way to smoothen the new concessionaire’s operations in the ports.
Ports Sector

The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
122Federal Ministry of Transportation / (NPA)Provision of Utilities to the Ports
The FGN is desirous in using PPP procurement method for the provision of utilities to the ports. These include, but are not limited to the provisions of power and water.
Ports Sector

The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case to determine the project’s viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
123Federal Ministry of Transportation / (NIMASA)

PPP Projects:

i. Ship building yard with breaking, recycling technology and wreck identification and removal.
ii. Management and operations of the modular/floating dry dock (outsourcing).
iii. Procurement of operational vessels, maritime patrol aircraft, coordination/surveillance centre and other operational equipment (Finance lease)
iv. Outsourcing of NIMASA’s Training Centre and Guest House at Nigerian Maritime Resource Development Centre (NMRDC), Kirikiri, Lagos state.
v. PPPs to develop a Multilevel car park at NIMASA Headquarters
vi. Unsolicited proposal for Development of platform for pollution
Verification Gross Mass Imo Solar- safety of life at sea

Ports Sector

The Ministry is in the process of procuring a Transaction Advisers to prepare an Outline Business Case to determine the project’s viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
124Federal Ministry of Transportation (FMoT)/ National Inland Waterways Authority (NIWA)PPPs for the following facilities:
i. Warri Dockyard
ii. Lokoja Dockyard
iii. Concession of Abam Ama Jetty at Port Harcourt
iv. Buoyage Vessels (B/V Anam at Onitsha)
v. Buoyage Vessels (B/V Bajibo at Lokoja, Kogi State)
vi. Buoyage Vessels (B/V Nembe at Lokoja, Kogi State)
vii. Buoyage Vessels (B/V Numan at Lokoja, Kogi State)
viii. Motor Ferry (M/F Calabar at Lokoja, Kogi State)
ix. Motor Ferry (M/F Effiat Mbo at Lokoja, Kogi State)
x. Motor Ferry (M/F Donga at Makurdi, Benue State)
xi. Water Bus (W/B) at Yauri, Kebbi State
xii. 3 Nos. 40-45 Passenger Sitter Ferries at Lokoja, Kogi State
xiii. Water Hyacinth Clearing Equipment (Water Master Classic III at Onitsha)
xiv. 2 Nos. 40-45 Passenger Sitter Ferries at Lagos
xv. Marina Jetty at Lagos
xvi. Apapa Jetty at Lagos
xvii. Oyingbo Jetty at Lagos
xviii. Maraoko Jetty at Lagos
xix. Abayomi Drive Jetty at Lagos
xx. Osborne Jetty at Lagos
Calabar Jetty at Calabar
Ports Sector

The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare an Outline Business Case to determine the projects’ viability and bankability.

Next Step:
Awaiting procurement of TA and preparation of OBC.

Development
125Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Inland Container Depot (ICD) in Benin, Edo State
The Benin Dry Port is proposed to provide a one stop cargo reception and clearance facility to boost exports from and imports into Edo State particularly and Nigeria’s South-South, South East and some States in the Middle Belt regions in general. It is expected to provide proper handling and logistics services which emphasize promptness, dependability and cost effectiveness.
Ports SectorAccording to the NSC, there is need to conduct Gap-Analysis with a view of advising the proponent on the steps to be taken before declaring the project as port of Origin and port of Destination.Development
126Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Vehicle Transit Area (VTA) in Obollo-Afor, Enugu State
The NSC proposes to facilitate the development of VTAs through PPP with facilities for short-term breaks as well as long-term parking services where truck drivers can get fuel, food, restrooms, showers and basic supplies like oil and spare parts as well as servicing and repairs of haulage vehicles. The VTAs will have the following facilities including but not limited Gas Station, Hotel and Motel, Restaurants, Mechanic Workshop, Fire Station, Police Post, Automated Cargo Tracking System.
Ports Sector

The Commission revalidated the OBC 15th February, 2021.

Next Step: Process leading to the selection of concessionaire.

Procurement
127Federal Ministry of Transportation / Nigeria Shippers Council (NSC)Development of Vehicle Transit Area (VTA) in Lokoja, Kogi State
The NSC proposes to facilitate the development of VTAs through PPP with facilities for short-term breaks and also long-term parking services where truck drivers can get fuel, food, restrooms, showers and basic supplies like oil and spare parts as well as servicing and repairs of haulage vehicles. The VTA will have the following facilities including but not limited to Gas Station, Hotel and Motel, Restaurants, Mechanic Workshop, Fire Station, Police Post, Automated Cargo Tracking System.
Ports Sector

Halcrow Infrastructure Consortium appointed as Transaction Adviser.

OBC Certificate of Compliance was issued for the proposed project on 24th October, 2018.

Next Step:
Commencement of procurement process for the selection of concessionaire.
The Commission after review of updated OBC report revalidated the OBC 24th June, 2021.

Procurement
128

Federal Ministry of Transport/Nigerian Ports Authority

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The Rehabilitation and Expansion of the Burutu Port
Burutu Port is located in Burutu Local Government Area of Delta State. The current Port is on a 40.716 Hectares of Land and was originally built as a logistic Port for the export of Solid minerals and Agricultural Produce as well as importation and transportation of foreign goods from Europe for onward movement to the hinterland River Ports via the inland waterway.
Ports Sector

The Commission revalidated the updated

OBC on 1st February, 2021

 

Site visit to the Burutu port project took

place 28th-30th July, 2021

Next step:

Taking the project through Modified Swiss

Challenge Process

Procurement
129Federal Ministry of Transportation (FMoT)Development of Bonny Deep Water Port
The FGN intends to develop the Bonny Deep Water Port through PPP arrangements in order to improve transportation opportunities and boost economic activities along south-south, south east, north central and north east geo-political economic corridors and ease pressure on the western ports – Apapa and Tin Can Island which at the moment handles about 90% of cargo throughput in the country.
Ports Sector

The Commission granted the OBC Compliance Certificate on 22nd June, 2020; and granted the FBC Compliance Certificate on 24th August, 2020

FEC approved by the FBC on 7th October, 2020

Next Step:
• Commercial Close
• Financial Close

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

130Federal Ministry of Transportation (FMoT)/ National Inland Waterways Authority (NIWA)Re-development of NIWA Marina Land, Lagos State
The project involves the re-development of a narrow strip land measuring 3.9 hectares with plans to reclaim 39.2 hectares to a total of 41.1 hectares in Marina, Lagos; both the land and water areas are under the jurisdiction of the National Inland Waterways Authority (NIWA). The facility is currently being used for berthing and docking of passengers’ boats and other vessel services referred to as “marina land”.
Ports Sector

The Commission reviewed and granted the OBC Compliance Certificate to the Honourable Minster of Transportation on 29th December, 2020.

Next Step:
Commencement of procurement process for the selection of concessionaire.

Procurement
131

Federal Ministry of Transportation / (NIMASA)

 

 

 

 

 

 

 

 

 

 

 

 

Management Contract to Operate, Maintain and Transfer (OMT) of NIMASA Floating Dry Dock, Lagos

The concessionaire is to seek a management contract for the Management and Operations of the Modular/Floating Dry Dock to assist to put in place a Project Management Company for the Outsourcing of the operation and management of its Floating Dry Dock (FDD) through a competitive bidding process as technical partners on a commercial basis.

The NIMASA Modular Dry-Dock for the dry-docking of all possible vessels, including tugs supply vessels, fishing vessels and normal vessels has the following dimensions:

• Length over all – 110 m.
• Beam: 30.2m external.
• Depth: 12m
• Vessels draught docking capacity: 6m.
• Dry-dock lifting capacity: 5000 ton

 

 

Ports Sector

The Commission issued NIMASA an Outline Business Case Compliance Certificate on 3rd March, 2021 and therefore advice that the project proceeds to procurement phase that would lead to emergence of a preferred operator.

 

A contract negotiation meeting between NIMASA and Jmarine Logistics, the preferred bidders for the NIMASA Floating Dry Dock, Lagos, was held on Thursday, February, 25th 2022.

 

The Commission issued a Full Business Case (FBC) Compliance Certificate on 25th April, 2020 after detailed review of the FBC report submitted.

Full Business Case Certificate Revalidated on March 3, 2021.

FBC revalidated on December 15, 2022

Project Approved by FEC on December 21, 2022

 

Procurement
132Federal Ministry of Transportation / (NIMASA)

Eastern Offshore Waste Reception Facility (EOWREF) Concession under a Design, Finance, Build, Operate, Maintain and Transfer (DFBOMT) PPP arrangement.

 

In line with NIMASA’s vision, the Agency attempted to address the issue of setting up Offshore Reception Facilities between 2007 and 2012 but was unsuccessful due to the absence of regulations to back any proposals for the establishment of the facilities. Irrespective of the introduction of these new regulations, NIMASA has not been able to actualize its obligations of MARPOL 73/78 due to economic and budgetary challenges, hence the agency’s effort in sourcing the PPP procurement option. There’s currently no established OWRF to meet the needs of ships visiting offshore terminals.

Ports

OBC Certificate of Compliance was issued for the proposed project on 3rd September, 2021.

 

Due diligence was conducted on Frigate Upstream & Energy Services Ltd, the technical partner to XPO Marine Service LTD, the preferred proponent for the Eastern Offshore Waste Reception Facility on 12th and 13th January, 2022.

Full Business Case (FBC) was issued on Eastern Offshore Waste Reception Facility (EOWRF) on 22nd February, 2022.

Certificate Revalidated on December 12, 2022

 

Project Approved by FEC on December 21, 2022

 

Procurement
133Federal Ministry of Transportation / (NIMASA)

Central and Western Offshore Waste Reception Facility (CWOWREF) Concession under a Design, Finance, Build, Operate, Maintain and Transfer (DFBOMT) PPP arrangement.

 

Ports

Full Business Case (FBC) was issued on Central and Western Offshore Waste Reception Facility (CWOWRF), on 22nd February, 2022.

 

FBC Certificate revalidated on December 12, 2022

Project Approved by FEC on December 21, 2022

 

Procurement
134

Federal Ministry of Transportation / NPA

 

 

 

APAPA PORTS COMPLEX, LAGOS

The project entails the complete refurbishment and operation of the water system at the Apapa Port to ensure adequate water supply to vessels. NPA intends to increase the capacity of the water treatment plant from 50 to 100 cubic meter per hour.

Ports

OBC Certificate issued on 17th May, 2022 for the project to proceed to procurement phase subject to a Swiss Challenge.

 

Next step:

Procurement of Concessionaire

Procurement
135

Federal Ministry of Transportation / NPA)

 

TIN CAN ISLAND PORT LAGOS

Tin Can Island Port is located north-west of Apapa Port Complex, Lagos and it is the second busiest port in Nigeria. The port handles diversified cargoes with each terminal operator specializing in different forms of cargo (Dry and Wet bulk cargoes, Box-Containerized cargoes, RORO services). The port handles vessels ranging from 100m – 260m can handle ships of about 30,000 tonnes.

 

Ports

The Commission issued Nigerian Ports Authority (NPA) an OBC Certificate on 17th May, 2022 for the project to proceed to concessionaire procurement phase subject to a Swiss Challenge

 

Next step:

Procurement of Concessionaire

Procurement
136Federal Ministry of Transportation / Nigeria Shippers Council (NSC)

Concession of Tincan Island Truck Transit Park, Lagos State

 

The Federal Ministry of Work and Housing (FMoW&H) is desirous in engaging private sector investors for the concession of a Truck Transit Park in Apapa Tincan Island under a Public Private Partnership (PPP) arrangement.

Transport /Urban Development

OBC Certificate of Compliance was issued for the proposed project on 21st January, 2022

Next step:

PPP procurement stages of RFQ and RFP

Procurement
137Federal Ministry of Education/University of AbujaDevelopment of Trailer Park on BOT with Gwagwalada Area CouncilTransport/Urban development

Declined issuance of OBC Certificate of Compliance due to non-compliance on the 16th of June 2022

 

Development
138Federal Ministry of Transportation/ Nigerian Railway Corporation (NRC)Greenfield Railway Lines across Nigeria
• Lagos – Shagamu- Ijebu Ode- Ore- Benin City (300km) (standard gauge).
• Benin- Agbor-Ogwashi Uku- Asaba- Onitsha –Nnewi- Owerri-Aba with additional line from Onitsha-Enugu- Abakaliki (500km) (standard gauge).
• Ajaokuta(Eganyi)-Obajana-Jakura-Baro-Abuja with additional line from Ajaokuta- Otukpo(533km) (standard gauge)
• Zaria- Funtua- Tsafe- Gusau- Kaura- Namoda-Sokoto-Illela-Birnin Koni (520Km) (standard gauge).
• Lagos –Ibadan- Oshogbo-Baro-Abuja (615KM) (high speed).
Rail

The OBCs on these projects are being awaited.

Next step:
Awaiting procurement of TA and preparation of OBC.

Development

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

139Federal Ministry of TransportationProvision Of Enterprise Resource Planning (ERP) Solution for the Council for Regulation of Freight Forwarding in Nigeria (CRFFN)
The Council for the Regulation of Freight Forwarding in Nigeria Act No. 16 of 2007 was enacted into law on April 30, 2007. The Council is charged with, amongst other responsibilities, regulating and controlling the practice of Freight Forwarding in Nigeria, and promoting the highest standards of competence, practice and conduct among members of the profession.
Rail

Full Business Case submitted by CRFFN, reviewed and certificate of compliance issued 12th February, 2019 for the Design, Build, Operate and Transfer (DBOT) of an Enterprise Resource Planning Solution under a PPP arrangement with Messrs SW Global (SWG) as the Preferred PPP partner based on their old service provision performance.

Next Step:

Submission of FBC to FEC for approval.

Procurement
140Federal Ministry of Transportation (FMoT)

Development of Railway Industrial Park in Port Harcourt

The FGN intends to develop a Railway Industrial Park in Ubima, Rivers State through PPP arrangements with the following facility components for commercial vehicles and rolling stock assembly, Oil and Gas materials supply Industrial Park, Textile Industrial Park, Light Industry Park for Fast Moving Commodities and Goods (FMCGs).

Rail

The Commission granted the OBC Compliance Certificate on 22nd June, 2020; and also granted the FBC Compliance Certificate on 24th August, 2020.

FEC approved the FBC on 7th October, 2020

Next Step:
• Commercial Close
• Financial Close

Procurement
141Federal Ministry of Transport/ Nigerian Railway Corporation

THE DEVELOPMENT OF ABUJA-BARO-ITAKPE-AJAOKUTA-WARRI RAILWAY LINE (269.12KM) WITH BRANCH LINE AND EXTENSIONS FROM JAKURA-LOKOJA (41KM) AND AGBARHO-WARRI (5KM) AND WARRI NEW SEAPORT

The 2-projects are:
i. Abuja-Baro-Itakpe-Ajaokuta-Warri Railway Line (269.12km) with branch and extension lines to Jakura-Lokoja (41km) and Agbarho-Warri (5km)

ii. Development of Warri new Seaport, Warri, Delta State

The preferred PPP project model is Design-Build-Operate and Transfer (DBOT) model where CRCC will recoup its investments through user-fees. The proposed projects were designed to promote passenger and freight services, promote regional infrastructure development, preserve the life span of roads, encourage inter-model transport system, job creation and promote economic recovery and growth plans of the Federal Government, etc.

Rail/ Port

Messrs. China Railway Construction Company International (CRCC(I)) was competitively procured to develop these projects under a PPP arrangement.

Process included joint due diligence on the CRCC(I) offices in China by ICRC, FMOT, Federal Ministry of Finance, Nigerian Railway Corporation to confirm technical and financial capabilities to undertake the Project.

ICRC issued FBC Compliance Certificate on 27th November, 2018.

FEC approval of FBC obtained 2018
Incorporation of Special Purpose Vehicle for the project commenced in October 2020.

Procurement
142

Federal Ministry of Transport/ Nigerian Railway Corporation

 

SECURE TICKETING SOLUTION FOR THE LAGOS – IBADAN STANDARD TRAIN SERVICE.

 

To effectively harness the benefit of the development taking place in the Nigeria railway by way of revenue generation, there is need to put in place a ticketing solution on the LAGOS – IBADAN STANDARD TRAIN SERVICE that will enable passengers to buy their tickets from their offices and homes without physically doing same at the train station. This will help NRC manage the demand for tickets using the PPP option under DESIGN, FINANCE, BUILD, OPERATE, MAINTAIN AND TRANSFER Model.

 

Rail

The Commission confirms that the submission is in substantial compliance with ICRC Act and issued FBC Certificate of Compliance for the proposed project on 12th April, 2022 to FMOT/NRC.

 

The Commission also certified the draft Concession Agreement (CA) reports forwarded to the Commission.

 

Next step:

Awaiting the approval of FBC by FEC.

 

 

Procurement
143

Federal Ministry of Transport/ Nigerian Railway Corporation

 

SECURE TICKETING SOLUTION FOR WARRI – ITAKPE TRAIN SERVICE

 

To effectively harness the benefit of the development taking place in the Nigeria railway by way of revenue generation, there is need to put in place a ticketing solution on the WARRI – ITAKPE TRAIN SERVICE that will enable passengers to buy their tickets from their offices and homes without physically doing same at the train station. This will help NRC manage the demand for tickets using the PPP option under DESIGN, FINANCE, BUILD, OPERATE, MAINTAIN AND TRANSFER Model.

 

Rail

The Commission confirms that the submission is in substantial compliance with ICRC Act and issued FBC Certificate of Compliance for the proposed project on 12th April, 2022 to FMOT/NRC.

 

The Commission also certified the draft Concession Agreement (CA) reports forwarded to the Commission.

 

 

Next step:

Awaiting the approval of FBC by FEC.

 

Procurement
144Federal Capital Territory Administration (FCTA), Abuja.ONEX through Mpape-Gurku-Ado/Gurku-Nyanya in the Federal Capital Territory (FCT), Abuja. FCTA
The project involves the construction, operation and maintenance of Dual Carriage way from Outer Northern Express Way (Murtala Mohammed Way) through Mpape to Gurku, through Ado/Gurku.  The project was designed to ease congestion on Nyanya road and its surrounding axis.
RoadThe project is at development phase involving procurement of Transaction Adviser and preparation of Outline Business Case.

Development

 

 

 

 

 

 

 

 

 

 

145Federal Ministry of Works & Housing (FMW&H)Concession of 10 roads under the Highway Development & Management Initiative (HDMI)
1. Asaba-Agbor (Delta/Edo States)
2. Abuja-Lokoja (FCT/Kogi)
3. Kano-Katsina (Kano/Katsina)
4. Onitsha-Aba (Ananbra/Abia)
5. Shagamu-Benin (Ogun/Edo)
6. Abuja-Akwanga (FCT/Nasarawa)
7a. Kano-Shuari [lot 1] (Kano State);
7b.       Potiskum-Damaturu [lot 2] (Yobe State)
8. Lokoja-Auchi (Kogi/Edo)
9. Enugu-Port Harcourt (Enugu/Rivers)
10. Ilorin-Jebba (Kwara/Niger)
11. Lagos-Abeokuta (Lagos/Ogun)
12. Lagos-Badagry (Lagos)These routes have been selected for the 1st phase of the VAC.The routes have been further broken down into lots. This is to ease management and development, ensuring that the entire route is adequately accounted for.

Certain criteria have been used to ensure that the most suitable 1st phase routes have been chosen.

Roads & Bridges

Twelve (12) OBC reports have been submitted by Federal Ministry of Works & Housing (Works) to the Commission for validation.

The Commission after review of the 12 OBC reports granted OBC compliance Certificate to all 12 reports on 21st December, 2020.

Presentation of OBC certificates to the Honorable Minister held 29th January, 2021 at the Ministry Conference room.

RFQ adverts for HDMI projects in print media on 29th March, 2021 with deadline of submission on 3rd May, 2021.

 

Evaluation of RfQ concluded and approval of report.

 

RfP was also issued and preferred bidders was announced by the Federal Government on 30th April, 2022.

 

Next Step:

Submission of FBC to the Commission for review and certification.

 

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

146Federal Ministry of Interior/Nigeria Immigration ServiceEstablishment of Nigerian Passport Application Support Centers in the US, Canada etc
(Solicited Proposal):

This project has been designed by the Nigeria Immigration Service (NIS) to alleviate the hardship, difficulties and inconvenience experienced by Nigerians living in USA, United Kingdom, Continental Europe, Asia and South America in their bid to procure or renew their international passports.
SecurityThe Nigeria Immigration Service vide a letter dated September 16, 2021 Ref: NIS/HQ/ACG-PPTS//208/16/II conveyed the directive of the Ministry of Interior and the decision to discontinue the processes leading up to the project.

Procurement

 

 

 

 

 

 

 

 

 

 

 

147Federal Ministry of Defence (FMoD)Concession of Defence Jetty, Marina Lagos
Messrs. Inspium Multi-Services Limited (IMSL) is proposing through a Build-Operate and Transfer (BOT) PPP model the rehabilitation and construction of the Ministry of Defence Jetty at Marina, Lagos.
Once Complete the following services will be available:
Ferry Service Parking, Helicopter Parking, Car Parking, Office Letting, Berthing Services, Afloat Repair Services, Warehousing Services, Restaurants & Café, Professional Training Services.
Security

The Commission issued an Outline Business Case Certificate November 8, 2017.

Full Business Case Certificate of Compliance was issued on 29th November, 2018.

Procurement
148Federal Ministry of Police AffairsContingent Owned Equipment (COE)
Supply Own and Operate (SOO) for Peace Keeping Missions in CAR, South Sudan, Somalia, Dafur and Liberia.
Security

Joint OBC/FBC Compliance Certificate issued for presentation to FEC.

Next step:

Submission of FBC to FEC for approval.

Procurement

 

 

 

 

 

 

 

 

 

 

149Nigerian Correctional Service (formerly Prisons)Concession of Nigerian Prisons Land Swap Correctional Facility, Industrial Laundry Facility & Integrated Farm Facility.Security

First phase of Negotiation with preferred bidders for both Land Swap Correctional Facility (Halcrow Infrastructure Consortium) and Integrated Farm Facility (Nestoti Consortium) projects took place on June 28, 2016.

Project stalled

Procurement
150Ministry of Defence (MOD)The Naval Ship Dockyard, Lagos
This involves optimizing the capacity and functioning of the Naval Dockyard to attend to the maintenance services of existing fleet and facilitate building of new naval and commercial vessels under a PPP arrangement.
SecurityThe Commission once again revalidated and re-issued the FBC certificate of compliance to MOD on 14th April, 2021.
Next Step:Submission of FBC to FEC for approval.
Procurement
151

Federal Ministry of Interior

 

 

 

 

 

 

 

 

 

 

Immigration and Border Line Management
The Ministry seeks to use PPP procurement to design and develop an Intelligent Border Management System to reinforce the Federal Government’s capability to enhance border management processes, by comprehensively overhauling the surveillance and monitoring of passengers arriving or departing through the country’s major entry points.
Security

The Commission has issued OBC Compliance Certification.

Next Step:
Awaiting commencement of procurement process by the Ministry.

Procurement
152Federal Ministry of InteriorDevelopment and Deployment of a National Security and Civil registration system:
This involves the developing and deploying an ICT-based system to collate and up-to-date demographic, migration, biometric and bio-data on segments of the nation’s civil population, primarily employed in informal sectors, most of whom are generally invisible, to improve intelligence information on civilian population, in line with the Ministry’s civil defense and internal security mandate.
Security

The Commission has reviewed the submitted OBC and has advised the Ministry accordingly.

The Commission is awaiting the submission of an updated OBC.

Development
153Federal Ministry of InteriorProduction of Emergency Passports
Federal Ministry of Interior seeks to commence the production of Emergency Passports on a Public Private Partnership (PPP) Arrangement.
SecurityAwaiting further correspondence from the Ministry on this projectProcurement
154

Federal Ministry of Defence

 

 

 

 

 

 

 

Supply, Operate & Maintain arrangement for equipment to Federal Ministry of Defence (FMoD)

Leasing to the UN under CoE system on a letter of assist basis.

 

 

 

 

 

 

 

 

 

 

 

Security

The Commission granted Conditional FBC Certificate of Compliance on 2nd September, 2019. Final FBC Certificate granted 5th December, 2019 on successful completion of the conditions.

Next Step:

Awaiting Presidential Approval.

Procurement
155Federal Ministry of Interior (FMoI)/ Nigerian Police Service (NPS)National Public Security Communication System (NPSCS)
The NPSCS project aims to provide of a robust, reliable, secure and independent multimedia communications system for the Police and other agencies. Using the latest broadband technologies both current and future network standards will be managed to deliver quadruple-play (4x) telecommunications services for improved capacity in crime prevention and investigation as well as a reduction in the need for physical manpower input in intelligence services and aid emergency services to respond more rapidly to urgencies.
Security

Bid conference held on Wed, 14th Aug, 2019 to select the Baseline Auditor for the NPSCS Network

Meeting of the subcommittee of the Network Baseline Audit of the NPSCS held on 20th  Aug, 2019
Presentation of report on the Network Baseline Audit of NPSCS to the Project Management Team (PMT) held on 29th Aug, 2019.

FEC Approval obtained Wednesday 16th December 2020

Next Step
Commercial close

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

156Nigerian Correctional Services (NCS)

The Resuscitation of the NCoS Farm Center, Ozalla, Edo State

The Nigerian Correctional Service is desirous of exploring PPP options for the development and operations of the farm centers debuting with the Federal Correctional Farm Centre, Ozalla, Edo State as a pilot scheme.

Security

The Commission issued NCS an Outline Business Case Compliance Certificate on 6th July, 2021 to enable the project proceed to private sector procurement stage through a Swiss Challenge approach.

Bid Opening and evaluation took place on May 9-16, 2022 via Swiss Challenge procurement process

Next Step:

Submission of Full Business Case (FBC) to the Commission for review and certification

Procurement
157Federal Ministry of Youth and SportsPPPs involving the following:
i. Upgrading/rebuilding of National Stadium, Lagos
ii. Completion of Athletes’ hostel, Abuja
SportsPDT meeting held on September19th, 2018.  The Ministry has been advised to submit an OBC to the Commission. RFQ bids evaluated on 25th November 2020
Evaluation Team to submit report to PDT on 2nd December 2020
PDT Meeting held on Wednesday, the 2nd of December, 2020
Development
158Federal Ministry of Youth and SportsDevelopment of Multipurpose Facility at National Stadium, Abuja
The Federal Ministry of Sports & Youth Development seeks to develop Multipurpose Facility at National Stadium Abuja through PPP
Sports

Meeting on a proposal for Long Lease of Part of the Public Parking Lot in the National Stadium, Abuja held at the Federal Ministry of Youth & Sports Development (FMYSD) on March 27, 2018.

RFQ Advert for the two projects published on the 31st August 2020.

RFQ advert extended by 2 weeks.

Development
159Federal Ministry of Youth and SportsSponsorship And Promotion of The National Sports Festival (NSF)SportsAttended the MOU signing ceremony for sponsorship, marketing and promotion of National Sports Festival on 11 Jul 2018.
Following request by the Ministry through letter on 6/09/18 for a waiver to allow Abuja National Stadium to bear the name 'GLO' for the next two years, the Commission replied requesting for the draft Agreement to be forwarded to it and Federal Ministry of Justice (FMoJ) for review before execution.
Development
160Federal Ministry of Youth and Sports

Athletes Hostel

The Federal Ministry of Youth and Sports Development seeks to Concession a) National Stadium Complex & Athletes’ Hostel Surulere, Lagos. B) Athletes’ hostel Abuja

SportsRFQ Advert for the two projects published on the 31st August 2020Procurement
161Federal Ministry of Industry, Trade and Investment/National Automotive CouncilDevelopment of World Class Training Centre of Excellence:
(Solicited Proposal): The National Automotive Design Development Council wishes to develop a World Class Training Centre of Excellence through a PPP.
Trade and InvestmentThe Commission held a meeting on 31st January, 2020 to establish a way forward on the project.
It was agreed an updated Business Case will be sent to the Commission for review on 9th March, 2020.
Procurement
162Federal Ministry of Industry, Trade & Investment / Tafawa Balewa Square Management Board (TBSMB)Rehabilitation, Management and Operation of the National Trade and International Business Centre, Lagos (NTIBC)
The development of the NTIBC was conceived against the background of the FGN’s desire to develop one-stop investment hubs in order to sustain economic growth by encouraging export, enterprise and investments. The Independence building was built in 1959. The building consists of 25 floors, has approximately 8,100 square meters and a separate parking lot directly opposite with an area of 2,650 square meters.
The proposed NTIBC building will be a mixed-use facility to cater for businesses on a let basis, provide space for TBSMB and also residential usage.
The proposed facility will be multi-functional, to include:
i. Office for agencies under the FMITI
ii. Offices for other government MDAs
iii. Information hub on trade & investment in Nigeria
iv. Office for Blue-Chip companies
v. Conference & meeting rooms
vi. Exhibition and banquet halls
Restaurants & lounge bar
Trade and Investment

Procurement report submitted to Minister of Industry, Trade and Investment and approval granted to proceed to Negotiations.

 

Awaiting negotiations

Procurement
163Federal Ministry of Industry, Trade & Investment / National Automotive Council (NAC)Establishment of the Mechanic’s Villages
The mechanics’ villages’ project is an initiative of NAC, a body established pursuant to the National Automotive Council Act, Cap N8, Laws of the Federation of Nigeria, with responsibility for the development of the automotive industry in Nigeria.
The objective for the establishment of the mechanic’s villages is, among other things, to stimulate the growth and development of the mechanic business in a specialized and orderly manner. The project is aimed at developing the automotive value chain via the provision of 6 pilot modern mechanic villages in the nation’s 6 geopolitical zones.
Trade and Investment

Meeting for review and negotiation of concession fees held on February 21st, 2019

Site Visit took place on February 27th, 2019

Awaiting Sensitivity analysis to be run by both parties and to be sent to the Commission for review

Development

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

164Federal Ministry of Industry, Trade & Investment / Small and Medium Enterprises Development Agency of Nigeria (SMEDAN)Development of 23 Industrial Development Clusters (IDCs)
The objective of the project is to redevelop 23 Industrial Development Centers (IDCs) into Industrial Clusters across Nigeria (in 6 geopolitical zones) using the PPP Model.
Trade and InvestmentOBC Certificate of Compliance was granted on October 23rd, 2018 for six (6) identified IDCs namely; Idu Abuja, Maiduguri, Owerri, Ikorodu, Port Harcourt and Sokoto.Procurement
165Federal Ministry of Industry, Trade & Investment Federal Ministry of Industry Trade and Investment Abuja Head office Building Project
The Federal Ministry of Industry Trade and Investment is desirous to build their Abuja Head Office through a PPP Procurement method. Project Conceptualization is currently on-going.
Trade and InvestmentProject Conceptualization is currently on-going.Development
166Federal Ministry of Industry, Trade & Investment

Proposed concession of Calabar and Kano Special Economic Zones (SEZs)

 

 

 

 

 

 

 

 

 

 

 

Trade and Investment

A letter dated 14th of October, 2021 acknowledging receipt of OBC was issued to the Ministry.

OBC Certificate of Compliance issued on 17th November 2021

Wrote a letter to the Honourable Minister, FMITI on the 20th of April 2022 regarding RFQ advertised by BPE.

Responded to a letter from BPE inviting the Commission for evaluation of RfQ. The letter was dated 23rd May, 2022.

Procurement
167Tiga Fish FarmDevelopment of the Tiga Fish FarmTrade and Investment

Outline Business Case issued on the 1st of August 2022.

Awaiting procurement.

Procurement

 

 

 

 

 

 

 

168Industrial Training Fund (ITF)Proposed development of Industrial Skills Training CentreTrade and InvestmentProject development ongoingDevelopment
169Federal Ministry of Industry, Trade & Investment (FMITI)

Concession of Calabar & Kano Free Trade Zones

 

Trade and Investment

BPE invited ICRC for RfQ evaluation on the 15th of June, 2022.

 

Development
170Federal Capital Territory/ Abuja Infrastructure Investment Center (AIIC)IGR Automated Platform for AEPB:
Project Description (Solicited Proposal): The MDA proposes providing an automated system for managing revenue collections, via an e-Payment platform that incorporates Mobile POS devices and a powerful AEPB office revenue administration and monitoring platform.
Urban Development

Evidence of competitive bidding process and all documentation and approvals during the process were sent by AIIC to the Commission on October 3, 2017

Next Step:

Awaiting FBC submission for review.

Procurement

 

 

 

 

 

 

 

 

 

 

171Federal Ministry of Works & Housing and Council for the Regulation of Engineering in Nigeria (COREN)COREN Head Office Project
(Solicited Proposal): The proposal will involve the Construction of COREN head office complex in Abuja using PPP procurement methodology.
Urban DevelopmentThe Commission granted an OBC Certificate of Compliance on November 8, 2016 for the project
COREN has been advised to proceed to procurement.
Procurement
172Federal Capital Development Authority (FCDA)Automated Parking Centres
This involves the construction of Automated Parking Centres in designated car parks in the FCT.
Urban DevelopmentFCDA is in the process of procuring a Transaction Adviser to prepare an Outline Business Case to determine project viability and bankability.Development
173Federal Housing Authority (FHA)PPPs involving the following:
i. Development of new towns in Abuja at Kwali and Bwari Area Councils
ii. PPP to develop corporate head office of Federal Housing Authority (FHA) in Abuja located at the Central Business District of Abuja.
Urban DevelopmentFHA is in the process of procuring Transaction Advisers to prepare an Outline Business Cases.
Projects will soon be advertised for procurement of Transaction Adviser.
Development
174Federal Housing Authority (FHA)Development of a 200-hectare land at Lugbe.Urban Development

The commission certified the Outline Business Case (OBC) and issued CoC on 25th July 2022. Achieved bid closing and evaluation. Awaiting evaluation report from the Ministry.

Ongoing procurement.

Bid closed on 29th September 2022 and was reviewed on 11th October 2022.  Awaiting RfP documents

Development
175Federal Ministry of Works & Housing Marina Quayside Strip Project
The proposed project is a transformative urban/waterfront development Project intended to be a tourism centre that will provide Commercial & Housing Complexes.
Urban Development

Outline Business Case Certificate of Compliance granted on August 16, 2017.

No further correspondence since OBC was issued in 2017

Procurement

 

 

 

 

 

176Federal Ministry of Works & Housing New Eko Development Project, (Lagoon City) in Lagos
The project proposal involves the Sand-filling and reclamation of water bodies within the vicinity of existing Banana Island Estate. The project would redefine the Banana Island landscape and complement the development of Lagos lagoon to reflect its mega-city status.
Urban DevelopmentThe OBC is currently a work in progress by the FMW&H.

Development

 

 

 

 

 

 

 

 

177Federal Capital TerritoryLight Rail Lot 2 PPP Project
The proposed Abuja Light Rail PPP project includes the financing, designing, construction, operation and maintenance of the rail transit network route. The covering distance is 54.1 kilometers from Garki Area 11 passing through the interchange centre at Eagle Square to Gudu and down to Nyanya, Karu axis, in Abuja. It also connects to sector Centre D through Hilton Hotel, Gwarimpa FHA Estate and the light railway Lot 1 (Blue line currently under construction)
Urban DevelopmentA meeting was held on December 22, 2017 at the SGF's office where the private proponent (IRMG) made another presentation on the way forward with the project. No conclusive agreements were reached, due to absence of some stakeholders.  The meeting was adjourned to a later date.
New date to be communicated to the Commission.
Development
178National Commission for Museums and MonumentsLease of Land at National Museum, Jos for the development of Filling Station
The National Commission for Museums and Monuments seeks to develop part of its land via PPP
Urban Development

The Commission reviewed the OBC and issued an OBC Certificate of Compliance on February 27th, 2018.

NCMM was asked to prepare a negotiation position paper and draft Concession Agreement and submit to the Commission.

Procurement
179National Commission for Museums and MonumentsDevelopment of Infrastructure in National Museum, EnuguUrban Development

The Commission reviewed the OBC and issued an OBC Certificate of Compliance on October 11th, 2022.

ICRC attended the inauguration of a Project Delivery Team and Project Steering Committee team held on the 18th of November, 2022.

 

Development

180National Sugar Development CouncilOperation and Management of Sugarcane Bio-Factory, Zaria
The Council is proposing a PPP procurement in the Management and Operation of the facility to make it more efficient and productive after sinking in so much money with little output.
Urban DevelopmentPDT met on March 23, 2018. ICRC has advised the Council of the need to procure a TA that will guide in the conduct of the Swiss Challenge procurement and also prepare a RFQ and RFP documents.

Development

 

 

 

 

 

 

181Centre for Management DevelopmentDevelopment of CMD Headquarters, Abuja
The Centre for Management Development is desirous of constructing National Headquarters in Abuja.
Urban DevelopmentProfile of two contractors sent to the commission by CMD. The Commission reminded through letter of March 27, 2018 to develop and submit Project Structuring Report.

Procurement

 

 

 

 

 

 

182Office of the Head of Civil Service of the Federation (OHCSF)The Concession of Ground Floor of the Federal Secretariat Complex, Phase II to Commercial Use under PPP Arrangement Modalities on how to commercialize the ground floor of the Office of the Head of Civil Service of the Federation (OHCSF) building complex as a PPP pilot project under PPP arrangement.
some of the possible services that can be considered in the proposed scheme:
- Creche/Nursery
- Supermarket
- Laundry
- Car Park commercialization
- Complementary Transportation to and fro across the various routes of the Federal Secretariat (Staff Bus)
Urban Development

ICRC issued Pilot Implementation Certificate on 10th July, 2019 to fast-track improved facility management via a pilot PPP arrangement.

Next step:
The head of Service is to obtain endorsement of the Federal Ministry of Justice and the approval of the president for the Implementation phase prior to signing the Pilot Concession Agreement.

Procurement
183Federal Housing Authority (FHA)Development of Federal Housing Authority (FHA) Shopping Complex, Gwarinpa, Abuja
FHA currently has a site office located on 2,500sqm along 3rd Avenue Gwarinpa. There is an existing bungalow housing the Annex office of the Federal Housing Authority on the land. The building will be demolished to give way for a modern shopping complex. The FHA Annex office will be relocated to a temporary location in Gwarinpa. On completion of the plaza, some of the offices will be retained for the FHA Annex.
Urban Development

OBC Certificate of Compliance was granted on June 12th, 2018

Bid opening held on July 11th, 2018 with two (2) proposals submitted for evaluation; which took place and none of the bidders met the requirements of the RfQ

Awaiting detailed report from FHA on the procurement process.

Procurement

 

 

 

 

 

 

 

 

 

 

 

 

184National Assembly/ PASAN Staff HousingThe National Assembly’s commitment to acquire housing for their civil service staff under the steer of the Parliamentary Staff Association of Nigeria (PASAN)Urban DevelopmentMeeting held with NASS/ PASAN on 20th May, 2019 regarding reviewed PSR and way forward for project.
NASS/ PASAN have been advised to procure a TA to develop a standard PSR for the project.

Development

 

 

 

 

 

 

 

185Federal Radio Corporation of Nigeria (FRCN)FRCN Land Lease, Owerri, Imo State.
The Federal Radio Corporation of Nigeria is interested in constructing and developing mixed-use development on 14 Hectares of its 21.11 Hectare landed property at Km-15 Umuahia Road, Owerri, Imo State.
The project consists of a high-end luxury estate with recreational support facilities, luxurious hotel and office blocks for commercial purposes.
Urban Development

A due Diligence visit to the site was conducted June 30, 2022.

 

Full Business Case Certificate Issued on November 22, 2022

Procurement

186

 

 

 

Federal Radio Corporation of Nigeria (FRCN)Federal Radio Corporation of Nigeria Properties
The Radio Corporation is desirous to develop its 10-Hectares of land into a mixed-use facility in Lagos.
Urban Development

FBC certificate of Compliance revalidated on May 23, 2022

Messrs Kingslane and Fish Valley Ltd are preferred bidders on the project. Fish Valley has been issued a FBC CoC on May 23, 2022 for FEC approval.

Concession agreement for Kingslane still under review

 

FBC revalidated for Fishvalley on December 5, 2022

FEC approves 6 hectare project to Fishvalley Nig Ltd on December 21, 2022

 

Procurement

 

 

 

 

 

 

 

 

187Niger Delta Development Commission (NDDC)Proposed Niger Delta Broadband Development Initiative (NDBDI) for a Region-Wide High-Speed Next Generation Broadband Infrastructure.
Provision of Broadband Internet Access, and associated Services in the Niger Delta region. it will serve as a platform for the recommended SP to deliver the Broadband Internet Services to Subscribers at a reduced cost, using 4G technologies such as LTE (Long Term Evolution) and WAN (Wide Access Networks) to deliver speeds of over 100Mbps.
Urban DevelopmentOBC Certificate issued on January 10, 2019.Procurement
188National Hajj Commission of Nigeria (NAHCON)

Development of Shopping Complex

The NAHCON seek to engage a private sector operator to DFBOT a building at its landed property located at Hajj Complex, along Katsina Road, Kano State.

Urban DevelopmentFBC CoC issued on
November 22, 2021FEC approved Project on December 12, 2021Concession Agreement signed on the 7th of September, 2022
Procurement
189Federal Ministry of Works and Housing

Federal Site and Services Housing Scheme

AVU-Owerri Imo State

Urban DevelopmentOBC certificate issued on July 22, 2021. Procurement
190Federal Capital Territory / Abuja Infrastructure Investment Center (AIIC)Development of Jabi Lake Tourism & Recreation Development Project.
The development of the Jabi Lake area into a Tourism and Recreation hub.
Urban DevelopmentOBC Certificate of Compliance issued for the project on February 19, 2021.
In the process of engaging a TA to conduct a Swiss Challenge process.OBC Certificate re-issued on the 21th June, 2022.
Procurement
191

Federal Capital Territory (FCT)

 

Maximization of revenue from water bills in FCTUrban Development

OBC Certificate of Compliance issued for the project on 22nd April 2022.

Full Business Cases & Concession Agreements reviewed and FBC issued on the 27th October 2022.

 

Procurement
192Federal Capital Territory (FCT)

On street park as you pay in the FCT.

 

Urban Development

OBC Certificate of Compliance issued for the project on 23rd February, 2022

 

Review of the Full Business Cases & Concession Agreement from NAJEC and ATB ongoing

Full Business Cases & Concession Agreements from NAJEC and ATB reviewed and FBC certificate has been issued on 8th August 2022.

 

Procurement
193Federal Ministry of Education/University of Port-HarcourtStudent Hostel - An unsolicited proposal for the development of 4000- bedspace standard green building hostel facilityUrban DevelopmentA response letter was sent to UNIPORT declining the issuance of Certificate of Compliance dated 10th March, 2022Development
194The Nigeria Police ForceRedevelopment of the Nigerian Police DIG Quarters at Maitama District, Abuja, through Public Private Partnership arrangementUrban Development

Full Business Case Certificate issued on March 11, 2022 Preferred bidder – Cosgrove Nigeria Ltd

A site visit was conducted on March 29, 2022 as part of the due diligence.

Procurement
195Federal Ministry of Works & Housing

The Concession of Central Workshop, Ijora, Lagos Central Workshop, Ijora (CWI),

CWI was an appendage of the defunct Public Works Department (PWD).

Urban Development

OBC Certificate of Compliance was issued for the proposed project on 21st December, 2021.

 

Next step:

PPP procurement stages of RFQ and RFP.

Procurement

 

 

 

 

 

 

 

 

 

 

196The Nigeria Police Force (NPF)Development of senior police officers’ quarters at Ikeja, Lagos through PPP arrangement
The redevelopment of 6.750 hectare of land at Ikeja into senior police officer’s housing units using 2.1 hectares of the land and use of 4.65 hectares for the development of 130 four-bedroom duplex housing units.
Urban DevelopmentFull Business Case Certificate of Compliance was issued on July 26, 2022Procurement
197The Nigeria Police Force (NPF)Redevelopment of Police Barracks in Falomo, Ikoyi; and Ijeh, Obalende Lagos. This involves the demolition and redesign of the two barracks and the relocation of the POWA shopping complex in Falomo.Urban Development

RfQ evaluation Completed on September 20, 2022

Next Steps:

Submission of evaluation report following RfQ

Procurement

 

 

 

 

 

 

 

 

 

198The Nigeria Police Force (NPF)The Development of the Police Conference and Four-Star Hotel at Guzape District Abuja through PPP. The proposed project involves the demolition of the structures currently standing on SARS headquarters and a comprehensive re-development of the 15.5 hectares belonging to the Police.Urban development

OBC Certificate of Compliance issued on March 16, 2022

 

A site visit was conducted on March 29, 2022 as part of the due diligence.

Awaiting documents for regularization from the NPF

Procurement
199National Hajj Commission of Nigeria (NAHCON)Commercial Development of Residential Houses through PPPUrban development

Site visit to Lagos held between the 26th and 29th April, 2022.

OBC Certificate of Compliance issued on September 22, 2022

Development
200Federal Ministry of Education/University of Nigeria NsukkaConstruction of students’ hostel on BOT ModelUrban developmentDeclined issuance of OBC Compliance on the 24th of May, 2022Development
201Federal Ministry of Education/Ahmadu Bello University Zaria

Development of Shopping Complex and Luxury Apartments at GRA Zaria through a PPP arrangement

The University proposes to develop infrastructure through PPP

Urban developmentOBC Certificate of Compliance issued on September 22, 2022Procurement
202Federal Ministry of Education/University of BeninDevelopment of Shopping Mall in the University CampusUrban development

OBC Certificate of Compliance issued on September 16, 2022.

Letter sent out detailing the process of engaging a TA, to conduct a Swiss Challenge process

Development
203University of Maiduguri Teaching hospitalProposed development of Liaison officeUrban developmentThe Commission wrote to the University via a letter dated 27th July, 2022Development